Greater Manchester Combined Authority
Bee Network Committee, Thursday 27 November 2025 at 2.00pm

Metrolink Trafford Park Line Evaluation

Noted Committee 2 papers

AI summaryGreater Manchester's Bee Network Committee noted the post-implementation evaluation of the Metrolink Trafford Park Line, which was delivered 7 months early within its £350m budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedHeadline findings and broad action areas noted
MoneyNo new moneyNo further financial implications at this time
What happens nextReports to be publishedSummary and detailed reports to go on TfGM website
Who it affectsTrafford Park areaPassengers, businesses, future rapid transit planning

What was decided

The committee noted the post-implementation evaluation headline findings and broad areas for action for the Metrolink Trafford Park Line.

The committee noted the publication on TfGM's website of the supporting summary and detailed reports.

Why

The evaluation was commissioned as a condition of the Earn Back funding agreement, which required evidence of outcomes from the £350m scheme. Report 1.1, 1.2

Evidence gathered in 2024 and into the first half of 2025 showed reduced car dependency, enhanced public transport connectivity, and positive employment and development trends in the Trafford Park area. Report 1.3, 2.3, 2.4, 2.5

Lessons learnt are being shared with TfGM's rapid transit team to shape future extensions and the Draft GM Rapid Transit Strategy. Report 4.1, 4.2, P28

What happens next

The summary and detailed findings are being published on the TfGM website alongside this report. Report 5.1

A wider plan to grow public transport patronage and revenue across the network is in development and will include the Trafford Park Line. Report 3.4

The issue of extending services through the city centre to Crumpsall on the Bury Line remains under review.

The money

  • £350m Original budget within which the Trafford Park Line was delivered Report P28
  • £1.86 Anticipated benefits in the business case for every £1 of costs incurred Report P31
  • £1 to £1.5 Currently estimated benefits, taking wider impacts into account, for every £1 of costs Report P31

Implications

  • Financial: Earn Back funding requirements for evidence gathering have been met; no specific further financial implications at this stage. Report P3
  • Legal: No specific legal considerations arising from the evaluation. Report P2
  • Other: Surveys indicate a significant modal shift from car, with 33% of users saying they would otherwise have travelled by car or taxi. Report 2.3, P30
  • Other: 80% of businesses surveyed agreed that staff site access has improved; 76% agreed there have been positive productivity impacts. Report P32
  • Other: Future rapid transit extensions are being designed to use mainly segregated alignments, building on the line's success. Report P29, P30

Who and where

  • Passengers travelling to and from the Trafford Park area on Metrolink Report 2.4, P29
  • Businesses located in the Trafford Park area Report 2.5, P32
  • Future users of planned rapid transit extensions in Greater Manchester Report 4.1, 4.2
  • Transport for Greater Manchester's rapid transit planning team Report 4.1, P28
  • Staff and contractors involved in delivering future Metrolink-style extensions Report P28

Timeline

  • 2020: Services began operating on the Metrolink Trafford Park Line. Report 1.1
  • July 2024: Draft GM Rapid Transit Strategy published, drawing on evidence from the Trafford Park Line. Report P29, P30, P32
  • 2024: Concentrated evidence gathering carried out for the post-implementation evaluation. Report 1.3
  • First half of 2025: Analysis and interpretation of evidence continued. Report 1.3
  • 7 months ahead of schedule: The line was delivered ahead of programme and within the £350m budget. Report P28

Plain English for the jargon

  • Earn Back: A fund administered by the Ministry of Housing, Communities and Local Government, focused on supporting local economic growth in Greater Manchester.
  • Metrolink: Greater Manchester's tram network, operated and planned by Transport for Greater Manchester (TfGM).
  • TfGM: Transport for Greater Manchester, the public body responsible for transport strategy and delivery across Greater Manchester.
  • Rapid transit: High-capacity public transport, including trams and similar segregated systems, referenced in the Draft GM Rapid Transit Strategy.
  • Modal shift: A change in the way people travel, in this context from car or taxi to Metrolink.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

T hat the post-implementation evaluation headline findings and broad areas for action be noted. 2. That the publication on TfGM’s website of the supporting summary and detailed reports be noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Risk management

Rather than risks, the report presents a range of opportunities that lead from the evaluation evidence.

Legal Considerations No specific legal considerations.

Financial Consequences Although developing evidence from monitoring & evaluation activity was a funding requirement of Earn Back, whose requirements have been met for the release of future funds, there are no specific further financial implications at this time.

Number of attachments to the report: 0

Comments/recommendations from Overview & Scrutiny Committee Not applicable.

Background Papers No background papers.

Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?

No

Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?

No. 1. Introduction

1.1The Trafford Park Line consists of 5.5km of new Metrolink route westwards from Pomona, with six new stops - Wharfside, Imperial War Museum, Village, Parkway, Trafford Palazzo (formerly Barton Dock Road) and Trafford Centre. Services began operating on the line in 2020. The line was largely funded by means of a fund administered by the Ministry of Housing, Communities and Local Government known as “Earn Back”, with the focus of the fund being on supporting local economic growth in Greater Manchester.

1.2To maximise learning from the Trafford Park Line to inform future investment decisions and to demonstrate a range of achievements and outcomes, as an Earn Back gateway condition, an evidence-gathering programme was commissioned from independent transport consultants.

1.3A wide range of evidence was assembled, with concentrated evidence gathering in 2024, then analysis and interpretation continuing into the first half of 2025. This included analysis of existing data (e.g. on patronage, costs and revenues), in -depth stakeholder interviews, and passenger and business surveys.

1.4A summary report of findings, alongside a more detailed report, is published alongside this report on the TfGM website.

2. Overall findings in relation to scheme objectives 2.1. The findings need to be considered in the context of the performance in the initial years being affected by Covid-19; the scale of engineering works that have limited city centre capacity; and that the planned operating pattern, with services running through the city centre to Crumpsall on the Bury Line, has not been implemented. Running Trafford Centre services through to Crumpsall is an issue that remains under review due to the additional timing pressures this would place on Victoria station that is already a significant network pinch point and the number of trams and drivers required to operate this service pattern .

2.2Three scheme objectives were determined and the evidence in relation to these is set out in the following paragraphs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Metrolink Trafford Park Line EvaluationReport 214 KB DownloadRead as text
PDF
Trafford Park Line impacts: from evidence to action Appendix 1Appendix 7.7 MB Download

At this meeting

Whole meeting

Who was there

0 of 18 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
PB
Councillor Phil BurkeCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
AW
Councillor Aidan WilliamsCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected

All 18 on the meeting page

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies