AI summaryGreater Manchester's Bee Network Committee approved funding drawdowns including £59.1m for zero emission buses, £16.158m for EV charging, and approved the Tyldesley Travel Hub Full Business Case.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDrawdowns and Full Business Cases across several schemes
MoneyMultiple£59.1m ZEB, £16.158m LEVI, £5.7m Metrolink, more
What happens nextSchemes progressConstruction starts Jan 2026 for Tyldesley, A6, Wigan
Who it affectsGreater ManchesterBus, tram, EV and active travel users across GM
What was decided
Noted the current position, recent progress and key milestones on the transport infrastructure pipeline, and approved the listed funding drawdowns and business case decisions. Report P6, 1.1, 1.3
Approved £59.1m Integrated Settlement funding for around 220 zero emission buses, plus £16.158m Local Electric Vehicle Infrastructure funding and £1.751m CRSTS for EV charging. Report 2.15, 3.1, 3.2
Approved the Full Business Cases and remaining funding for the Tyldesley Travel Hub and the Wigan Atherton and Tyldesley Strategic Links North Phase 1, and the A6 Wellington Road North drawdown. Report 2.14, 2.23, 2.25, 4.7
Why
To continue delivery of the Bee Network, Greater Manchester's plan for an integrated public transport and active travel system. Report P4, 1.1, 1.2
Zero emission buses and EV charging are expected to support Greater Manchester's target of becoming carbon neutral by 2038 and to improve air quality. Report P10, 2.17
Independent TfGM officer review panels found the relevant schemes demonstrated the strategic case, value for money and deliverability required. Report 2.13, 4.6
What happens next
Tyldesley Travel Hub, A6 Wellington Road North Phase 1 and the Wigan active travel scheme are planned to start on site in January 2026. Report 2.14, 2.26, 4.7
The Oldham, Rochdale, Heywood and Bury Tram-Train Pathfinder Outline Business Case is expected to complete in late 2026 and be submitted to Government in early 2027, with a target construction start in 2028. Report 2.8
The Local Electric Vehicle Infrastructure contract is expected to be awarded in Spring 2026. Report 3.1
The money
£5.7m Metrolink Next Generation Vehicles and Oldham, Rochdale, Heywood and Bury Tram-Train Pathfinder development Report 2.8
£3.84m Tyldesley Travel Hub and Park and Ride Full Business Case drawdown Report 2.14
£59.1m Next Phase of Zero Emission Bus Investment, around 220 buses Report 2.15, 2.16
£1.305m Rapid Transit Extensions Package, Metrolink Airport Western Leg Strategic Outline Case Report 2.22
£2.312m City Centre Radials, A6 Wellington Road North, phased Full Business Cases Report 2.23, 2.25
£16.158m Local Electric Vehicle Infrastructure funding from Office for Zero Emission Vehicles Report 3.1, 3.2
£1.751m Integrated Settlement CRSTS for Electric Vehicle Charging Infrastructure Report 3.1, 3.2
£0.93m Wigan: Atherton and Tyldesley Strategic Links North Phase 1, Active Travel Report 4.5, 4.7
£0.3m Reallocation of Mayor's Challenge Funding from Leigh St Helen's Road to the Wigan scheme Report 4.6, 4.7
Options considered
Chosen: Approve all listed drawdowns and business case decisions as set out in the report. Schemes met required strategic, value for money and deliverability tests in independent officer reviews. Report 2.13, 2.15, 4.6
Implications
Financial: Multiple capital funding drawdowns are approved, drawing on the Integrated Settlement, CRSTS, LEVI and Active Travel allocations. Report P6, 1.3, 3.1, 4.5
Carbon: Zero emission buses, EV charging and active travel schemes are expected to support Greater Manchester's carbon neutral 2038 target. Report P10, 2.17, 2.18
Legal: Legal and funding agreements are required for allocation of Mayor's Challenge Fund, Active Travel and CRSTS funding. Report P16
Risk: A programme risk register is maintained, with scheme risks including resource constraints, project dependencies, funding uncertainties and governance delays for the A6 scheme. Report P15, 2.25
Equalities: The impacts questionnaire rates Equality and Inclusion, Health, and other areas as positive, with carbon assessment scoring 0.9375. Report P9, P12
Who and where
Bus passengers, especially in the Oldham and Hyde Road Large Franchises where around 220 zero emission buses will be deployed Report 2.15, 2.18
Tram passengers using current and new Metrolink services in the Oldham, Rochdale, Heywood and Bury area Report 2.3, 2.4
Tyldesley and Leigh area residents using the guided busway and new Travel Hub Report 2.9, 2.11
Wigan borough residents using active travel routes between Atherton, Tyldesley and Leigh Report 4.2, 4.3
Greater Manchester electric vehicle drivers who will use new on street public chargers Report 3.1
Stockport to Manchester City Centre commuters using the A6 corridor Report 2.23
Timeline
January 2026: Planned start on site for Tyldesley Travel Hub Report 2.14
January 2026: Planned construction start for the first A6 Wellington Road North works package Report 2.26
January 2026: Wigan Atherton and Tyldesley Strategic Links North Phase 1 works planned to start on site Report 4.7
Spring 2026: Local Electric Vehicle Infrastructure contract award expected Report 3.1
Summer 2026: Wigan active travel scheme scheduled for completion Report 4.7
Late Summer 2026: Further A6 Wellington Road North Full Business Case work package expected for Committee approval Report 2.26
Late 2026: Tram-Train Pathfinder Outline Business Case completion expected Report 2.8
Early 2027: Tram-Train Pathfinder Outline Business Case submission to Government expected Report 2.8
2028: Target start for Tram-Train Pathfinder construction Report 2.8
Late 2030s: Existing M5000 Metrolink trams expected to start requiring replacement Report 2.5
Plain English for the jargon
Bee Network: Greater Manchester's planned integrated public transport and active travel system
CRSTS: City Region Sustainable Transport Settlement, a central government transport fund
ZEB: Zero Emission Bus
LEVI: Local Electric Vehicle Infrastructure, an Office for Zero Emission Vehicles programme
MCF: Mayor's Challenge Fund, an active travel funding stream
OBC and FBC: Outline Business Case and Full Business Case, stages in the Department for Transport business case process
SOC: Strategic Outline Case, the first stage in the Department for Transport business case process
TfGM: Transport for Greater Manchester
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
T hat the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression be approved as follows: · Metrolink Next Generation Vehicles and Oldham–Rochdale–Heywood–Bury Tram-Train ‘Pathfinder’: £5.7m; · Tyldesley Travel Hub / Park & Ride: Full Business Case and £3.84m; · Next Phase of Zero Emission Bus (ZEB) Investment: £59.1m; · Rapid Transit Extensions Package: £1.305m; and · City Centre Radials – A6 Wellington Road North: £2.312m. 3. That the drawdown of funding for Electric Vehicle Charging Infrastructure be approved as follows: · Local Electric Vehicle Infrastructure: £16.158m; and · Integrated Settlement (CRSTS): £1.751m. 4. That the drawdown of Active Travel funding and associated scheme progression be approved as follows: · Wigan: Atherton & Tyldesley Strategic Links North Phase 1: Full Business Case and £0.93m; and · To note the reallocation of £0.3m Mayor’s Challenge Funding (MCF) from the Wigan: Leigh St Helen’s Road scheme to the Wigan: Atherton & Tyldesley Strategic Links North scheme.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Bee Network Committee Date: Thursday 27th November 2025
Subject: Transport Infrastructure Pipeline
Report of: Chris Barnes, Network Director Infrastructure, TfGM
Purpose of Report To provide an update on delivery of a pipeline of transport infrastructure improvements to support the Bee Network: a high -quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.
Recommendation: The Committee is requested to:
1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline. 2. Approve the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression as follows: • Metrolink Next Generation Vehicles and Oldham–Rochdale–Heywood–Bury Tram-Train ‘Pathfinder’: £5.7m; • Tyldesley Travel Hub / Park & Ride: Full Business Case and £3.84m; • Next Phase of Zero Emission Bus (ZEB) Investment: £59.1m; • Rapid Transit Extensions Package: £1.305m; and • City Centre Radials – A6 Wellington Road North: £2.312m. 3. Approve the drawdown of funding for Electric Vehicle Charging Infrastructure as follows: • Local Electric Vehicle Infrastructure: £16.158m; and • Integrated Settlement (CRSTS): £1.751m. 4. Approve the drawdown of Active Travel funding and associated scheme progression as follows: • Wigan: Atherton & Tyldesley Strategic Links North Phase 1: Full Business Case and £0.93m; and • To note the reallocation of £0.3m Mayor’s Challenge Funding (MCF) from the Wigan: Leigh St Helen’s Road scheme to the Wigan: Atherton & Tyldesley Strategic Links North scheme.
Contact Officers Chris Barnes, Network Director Infrastructure, TfGM [email removed]
Richard Nickson, Network Director Active Travel, TfGM [email removed] Equalities Impact, Carbon, and Sustainability Assessment: Recommendation - Key points for decision-makers Insert text
Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production
Contribution to achieving the GM Carbon Neutral 2038 target
Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.
Carbon Assessment Overall Score 0.9375
Buildings Result Justification/Mitigation New Build residential N/A Residential building(s) N/A renovation/maintenance New build non- residential (including N/A public) buildings Transport Active travel and public 1 transport Roads, Parking and N/A Vehicle Access Access to amenities 1 Vehicle procurement 1.5 Land Use Land use 0.5
High standard in Mostly best practice Partially meets best Not best practice No associated terms of practice with a good level of practice/ awareness, and/ or insufficient carbon impacts and awareness on awareness on significant room to awareness of carbon expected. carbon. carbon. improve. impacts.
Risk Management The recommendations of this report will enable the continued development and delivery of the Bee Network infrastructure pipeline and prioritised infrastructure expenditure. A programme risk register is maintained, updated and reviewed regularly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.