GMCA Capital Programme 2025/26 - 2028/29

Noted Committee 1 paper

AI summaryGreater Manchester Combined Authority approves a £1.107bn capital programme for 2026/27 and reallocates £5.3m of Oldham transport funding to two new active travel schemes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIncludes reallocations and new grant additions
Money£1,107m approved for 2026/27Plus £5.3m reallocation and new grants
What happens nextBee Network Committee in February 2026Will consider further drawdown details
Who it affects10 GM local authorities and GM-wideTransport, housing, retrofit and skills projects

What was decided

The 2025/26 capital forecast of £585.9m, down from a previous £620.4m, was noted. Report P7, P205

The 2026/27 capital programme of £1,107m and forward plan were approved. Report P8, P205

Approval was given to reallocate £5.3m from Oldham's Beal Valley scheme to Park Road/Kings Road and Broadway Canal Link projects, and to use the full capital to revenue switch and add £1.4m to the Mayor's Renewable Fund. Report P10, P11, P12, 2.13

Why

The 2026/27 capital programme needs to be set so that the Authority can deliver its transport, regeneration, housing, retrofit and skills commitments. Report P5, P6, 1.3

Oldham Council withdrew the Beal Valley scheme in February 2025, requiring the remaining £5.3m of CRSTS1 Streets for All funding to be redirected to alternative Oldham schemes. Report 2.13, P11

What happens next

Further drawdown requests for the Oldham reallocation schemes will be presented to the February 2026 Bee Network Committee meeting. Report 2.13

Updates on the £1.839m Pavement Channels Grant will be included in the next capital update report.

The GM Transport Strategy 2050 and Delivery Plan are planned to be adopted by late summer or autumn 2026, with subsequent capital forecasts updated to quarter 3 of 2026/27.

The money

  • £585.9m 2025/26 capital forecast Report P7, P205
  • £620.4m Previous 2025/26 capital forecast Report P7, P205
  • £1,107m 2026/27 capital programme budget Report P8, P205
  • £1.839m Department for Transport Pavement Channels Grant addition Report P8
  • £15.6m Additional 2026/27 funding for local highways maintenance Report P9
  • £7.8m Highways maintenance share to GM local authorities Report P9
  • £7.8m Highways maintenance incentive element retained by DfT Report P9
  • £5.3m Reallocated CRSTS1 funding from Beal Valley to Park Road/Kings Road and Broadway Canal Link Report P11, 2.13
  • £1.4m Mayor's Renewable Fund 2026/27 addition Report P12
  • £526m 2026/27 borrowing requirement Report P183
  • £739m Good Growth Fund available over next three years

Options considered

  • Chosen: Approve 2026/27 capital programme of £1,107m and forward plan. Needed to continue delivery of transport, regeneration, housing, retrofit and skills programmes Report P8
  • Chosen: Reallocate £5.3m of CRSTS1 Streets for All funding from Beal Valley. Oldham Council withdrew the Beal Valley scheme in February 2025, requiring alternative uses for the funding Report 2.13
  • Chosen: Use the full capital to revenue 'switch' under integrated settlement flexibilities. Enabled by CRSTS1 being included in the Integrated Settlement from April 2025, to fund services that would otherwise need non-recurrent sources
  • Chosen: Add £1.839m of DfT Pavement Channels Grant. To deliver cross-pavement channels for residents without off-street parking
  • Chosen: Add £1.4m to Mayor's Renewable Fund. To develop renewable energy projects as part of Great British Energy Local Power Plan

Implications

  • Financial: A significant proportion of the capital budget is funded through grant; claw-back risk is mitigated through monitoring against grant conditions. Report P20
  • Financial: Borrowing requirement for 2026/27 is £526m, with £25.793m for transport and £419.222m for Economic Development and Regeneration. Report P183
  • Legal: There are no specific legal implications contained within the report. Report P21
  • Equalities: There are no specific equalities impact issues contained within this report. Report P19
  • Climate: There are no specific carbon and sustainability issues contained within this report, though multiple programmes target decarbonisation and retrofit. Report P19, 6.1, 6.2, 6.3, 6.5
  • Risk: Major budget risks are assessed quarterly; monitoring against grant conditions is used to mitigate monetary claw back risk. Report P20
  • Other: Government accepted in January 2025 that an investment-led, non-charging Greater Manchester Clean Air Plan will achieve nitrogen dioxide compliance by 2026 at the latest.

Who and where

  • 10 Greater Manchester local authorities Report 1.2, P193, P101
  • Transport for Greater Manchester (TfGM) Report 1.2, P16
  • Greater Manchester Fire and Rescue Service (GMFRS) Report 1.2, 11.1
  • Greater Manchester Waste and Resources Service Report 1.2, 12.1
  • Residents without off-street parking who will benefit from cross-pavement channels
  • Oldham Council (Beal Valley scheme withdrawn, two new active travel schemes added) Report 2.13, P11

Timeline

  • February 2025: Oldham Council withdrew the Beal Valley scheme from the CRSTS Streets for All Programme
  • 7 February 2025: GMCA approved the 2025/26 capital programme Report 1.3, P25
  • June 2025: Spending Review confirmed GM's Transport for City Regions funding allocation of £2.47bn for April 2027 to March 2032
  • August 2025: Department for Transport announced £25m capital grant for cross-pavement channels
  • November 2025: Good Growth Fund launched with £400m committed to 18 housing and employment site projects
  • 12 December 2025: Latest 2025/26 capital reforecast at quarter 2 was noted by the Authority Report 1.3, P25
  • February 2026: Bee Network Committee meeting will consider further drawdown requests for Oldham reallocation schemes
  • 13 February 2026: GMCA approved the 2026/27 capital programme and forward plan Report P1
  • March 2026: Further Good Growth Fund allocations to be made
  • Late summer or autumn 2026: GM Transport Strategy 2050 and Delivery Plan planned to be adopted
  • Quarter 3 of 2026/27: Subsequent capital forecasts to be updated to include new funding allocations

Plain English for the jargon

  • CRSTS1: City Region Sustainable Transport Settlement, the first round of this funding stream, now part of GM's Integrated Settlement from April 2025
  • Integrated Settlement: A consolidated funding arrangement from government that includes transport and other funds, allowing flexibility between areas
  • Bee Network: Greater Manchester's plan for a high-quality, affordable and fully integrated public transport and active travel system
  • Streets for All: A CRSTS/Integrated Settlement-funded programme led by GM local authorities covering local highways and active travel schemes
  • MCF: Mayor's Cycling and Walking Challenge Fund
  • TCR: Transport for City Regions, government funding stream for city region transport
  • MRF: Mayoral Renewables Fund, a grant scheme for Mayoral Strategic Authorities to develop renewable energy projects
  • Good Growth Fund: A new GM investment approach combining Integrated Settlement monies, borrowing, and Pension Fund investment to deliver growth across the region
  • HILF: Housing Investment Loan Fund, designed to accelerate and unlock housing schemes in Greater Manchester
  • GBE: Great British Energy, a government body supporting clean power initiatives
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5F

Resolved

That the current 202 5 /2 6 forecast of £ 585.9m compared to the previous forecast of £ 620.4m , be noted . 2. That the 2026/27 capital programme budget of £1,107m, and the forward plan , set out in the report and Appendix A, be approved. 3. That the addition of £1.839m of the Department for Transport Pavement Channels Grant to deliver cross-pavement channels for residents without access to off-street parking, as outlined in section 2.6.6 of the report, be approved. 4. That the addition of £15.6m to the 2026/27 capital programme for local highways maintenance (£7.8 m to be paid to local authorities and £7.8m retained by Department for Transport (DfT) as a new incentive element), as outlined in sections 2.10.8 and 2.10.9 of the report, be noted. 5. That the utilisation of full capital to revenue ‘switch’ permitted under the integrated settlement flexibilities , be approved. 6. That the reallocation of £5.3m of CRSTS1 / Integrated Settlement Streets for All funding from Oldham Council’s Beal Valley scheme to support two new council-led projects: Park Road / Kings Road and Broadway Canal Link, as outlined in section 2.13 of the report, be approved. 7. That the addition of £1.4m to the 2026/27 Capital Programme for the Mayor’s Renewable Fund to develop renewable projects, as outlined in section 6.4.1 of the report, be approved.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Greater Manchester Combined Authority Date: 13th February 2026

Subject: GMCA Capital Programme 2025/26 – 2028/29

(Budget Paper F)

Report of: Councillor David Molyneux, Portfolio Lead for Resources & Investment and Steve Wilson, GMCA Group Chief Financial Officer

Purpose of Report To present an update in relation to the Greater Manchester Combined Authority’s 2025/26 capital expenditure programme and the 2026/27 capital budget and forward plan for approval.

Recommendations: The GMCA is requested to:

1. Note the current 2025/26 forecast of £585.9m compared to the previous forecast of £620.4m; and

2. Approve the 2026/27 capital programme budget of £1,107m and the forward plan set out in this report and Appendix A; 3. Approve the addition of £1.839m of the Department for Transport Pavement Channels Grant to deliver cross-pavement channels for residents without access to off-street parking, as outlined in section 2.6.6;

4. Note the addition of £15.6m to the 2026/27 capital programme for local highways maintenance (£7.8m to be paid to Local Authorities and £7.8m retained by Department for Transport (DfT) as a new incentive element), as outlined in sections 2.10.8 and 2.10.9;

5. Approve utilisation of full capital to revenue ‘switch’ permitted under the integrated settlement flexibilities; and

6. Approve the reallocation of £5.3m of CRSTS1 / Integrated Settlement Streets for All funding from Oldham Council’s Beal Valley scheme to support two new council-led projects: Park Road / Kings Road and Broadway Canal Link, as outlined in section 2.13; and

7. Approve the addition of £1.4m to the 20267/27 Capital Programme for the Mayors Renewable Fund to develop renewable energy projects, as outlined in section 6.4.1.

Contact Officers Name: Steve Wilson, Group Chief Financial Officer

Telephone: 0161 778 7004

E-Mail: [email protected]

Name: Matt Bull, Director of Finance, Commercial and Corporate Services, Transport for Greater Manchester

Telephone: [phone removed]

E-mail: [email removed]

Equalities Impact, Carbon and Sustainability Assessment: There are no specific equalities impact, carbon and sustainability issues contained within this report.

Risk Management An assessment of major budget risks faced by the Authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. To mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.

Legal Considerations There are no specific legal implications contained within the report.

Financial Consequences – Revenue The report sets out the detail behind the CRSTS1 Capital to Revenue ‘switch’ in section 2.12.

Financial Consequences – Capital The report sets out the forecast capital expenditure for 2025/26 and the budget for 2026/27 and future years. Number of attachments to the report: 1 GMCA Greater Manchester Good Growth Fund Report

Comments/recommendations from Overview & Scrutiny Committee None

Background Papers • 07 February 2025 GMCA Capital Programme 2024/25 – 2027/28 • 27 June 2025 GMCA CRSTS Reprioritisation • 19 August 2025 BNC Transport Infrastructure Pipeline • 22 August 2025 GMCA Active Travel Funding • 26 September 2025 GMCA Capital Budget Update – Quarter 1 • 30 October 2025 BNC Transport Infrastructure Pipeline • 26 November 2025 GMCA Greater Manchester Good Growth Fund • 12 December 2025 GMCA Capital Budget Update – Quarter 2 • GM Transport Strategy 2050 Greater and Delivery Plan Consultation - https://www.gmconsult.org/transport/transport2050/

Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution

No

Exemption from call in

Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?

No

Bee Network Committee

N/A

Overview and Scrutiny Committee

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GMCA Capital Programme 2025/26: 2028/29Report 450 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 14 attended
RR
Rachael RobinsonCouncil Staff, expected
SK
Shelley KiplingCouncil Staff, expected
EW
Councillor Eleanor WillsCommittee Member, expected
SH
Suzanne HeslingCouncil Staff, expected
GM
GM Mayor Andy BurnhamChair, expected
TR
Councillor Tom RossCommittee Member, expected
AS
Councillor Arooj ShahCommittee Member, expected
NE
Councillor Neil EmmottCommittee Member, expected
NP
Councillor Nicholas PeelCommittee Member, expected
EO
Councillor Eamonn O'BrienCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
DM
Councillor David MolyneuxCommittee Member, expected

All 14 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. GMCA Capital Programme 2025/26 - 2028/29This decision
  2. 2026/27 GMCA Capital StrategyApproved
  3. GMCA Revenue and Capital Budgets 2026/27 OverviewNoted
  4. GMCA Capital Outturn 2024/25Noted
  5. 2025/26 GMCA Capital StrategyApproved
  6. GMCA Revenue and Capital Budgets 2025/26 OverviewNoted

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies