Resolved
That the 2024/25 actual outturn capital expenditure of £598.0m compared to the forecast position presented to GMCA on 7 February 2025 of £631.6m be noted. That the great work being undertaken in the region by Project Skyline be noted.
Greater Manchester Combined Authority noted this item on Friday 27 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the 2024/25 actual outturn capital expenditure of £598.0m compared to the forecast position presented to GMCA on 7 February 2025 of £631.6m be noted. That the great work being undertaken in the region by Project Skyline be noted.
Date: 27 June 2025
Subject: GMCA Capital Outturn 2024/25
Report of: Councillor David Molyneux, Portfolio Lead for Resources and Steve Wilson, GMCA Group Chief Finance Officer
Purpose of Report This report is to inform members of the Greater Manchester Combined Authority of the capital outturn for 2024/2025.
Recommendations: The GMCA is requested to:
Note the 2024/25 actual outturn capital expenditure of £598.0m compared to the forecast position presented to GMCA on 7 February 2025 of £631.6m.
Contact Officers Name: Steve Wilson, Group Chief Finance Officer, GMCA
E-Mail: [email protected]
Name: Matt Bull, Director of Finance, Commercial and Corporate Services, Transport for Greater Manchester
E-mail: [email removed]
Equalities Impact, Carbon and Sustainability Assessment There are no specific equalities impact, carbon and sustainability issues contained within this report.
Risk Management An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary. Legal Considerations There are no specific legal implications contained within the report.
Financial Consequences – Revenue There are no specific revenue considerations contained within the report.
Financial Consequences – Capital The report details the actual capital expenditure for 2024/25.
Number of attachments to the report: None
Background Papers GMCA Capital Programme 2023/24 – 2026/27 – 9 February 2024
GMCA 2024/25 Capital Update – Quarter 1 – 27 September 2024
GMCA 2024/25 Capital Update – Quarter 2 – 29 November 2024
GMCA 2024/25 Capital Programme 2024/25 – 2027/28 – 7 February 2024
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution?
No
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction/Background 1.1 The Greater Manchester Combined Authority approved the 2024/25 capital programme at its meeting on 9 February 2024. Updated forecast outturns were provided on a quarterly basis during 2024/25 with the latest forecast being presented on 7 February 2025.
1.2The Authority’s capital programme, funded from a number of sources and grants, includes Greater Manchester Fire and Rescue Services (GMFRS), Economic Development & Regeneration programmes, Waste & Resources Service and the continuation of the programme of activity currently being delivered by the Authority, Transport for Greater Manchester (TfGM) and GM Local Authorities (LA) including the following elements:
a) Metrolink schemes.
b) Rapid Transit schemes.
c) Rail schemes.
d) Interchange schemes.
e) Clean Air schemes.
f) Active Travel schemes.
g) Bus Infrastructure schemes.
h) Bus Franchising Schemes.
i) Local Authority highways schemes.
j) Other capital projects and programmes.
k) Capital Highways Maintenance, Traffic Signals and Full Fibre.
1.3The actual expenditure for 2024/25 was £598.0m compared to a forecast for 2024/25 presented to GMCA on 7 February 2025 of £631.6m. This is summarised in Appendix A and the major variances are described in this report. The financing of capital expenditure in 2024/25 is provided in section 6.
1.4It should be noted that this report is a draft of the expected outcome of the 2024/25 capital outturn position, ahead of the audit of the Statement of Accounts, however it is not anticipated that there will be any material changes to the position presented in this report. 2. Transport Schemes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
GMCA Capital Outturn 2024/25Report | 325 KB | DownloadRead as text |
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Sep 2026 | ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... | Decided | Open |
| 25 Sep 2026 | Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... | Decided | Open |
| 25 Sep 2026 | Declarations of InterestThat it be noted that no declarations of interest were received. | Noted | Open |
| 25 Sep 2026 | GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. | Approved | Open |
| 25 Sep 2026 | Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.