Resolved
That the performance of the Waste and Resource Management contracts be noted.
AI summaryGM Waste and Recycling Committee noted Suez contract performance for April to December 2025, with overall recycling down to 46% and total waste arisings of 776,216 tonnes.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the performance of the Waste and Resource Management contracts be noted.
Greater Manchester Combined Authority
Waste and Resources Committee Date: 11 March 2026
Subject: Contracts Update
Report of: Justin Lomax, Head of Contract Services, Waste and Resources Team
Purpose Of Report To update the Committee on performance of the Waste and Resource Management Services and Household Waste Recycling Centre Management Services Contracts that commenced on 1 June 2019.
Recommendations: The Committee is requested to:
1. Note and comment on performance of the Waste and Resource Management contracts set out in the report.
Contact Officers
Justin Lomax, Head of Contract Services, Waste and Resources Team [email protected] Equalities Impact, Carbon and Sustainability Assessment: There are no equalities impacts arising from the matters set out in this report. A fundamental principle of the WRMS and HWRCMS contracts is the sustainable management of waste in order to reduce carbon emissions from landfill disposal. The carbon impacts of the contracts are monitored and provided annually by the contractor.
Risk Management Performance of the contracts and associated risks are captured in the GMCA corporate risk register.
Legal Considerations Activities set out in this report are in accordance with the terms of the WRMS and HWRCMS contracts.
Financial Consequences – Revenue Activities set out in this report are in accordance with the Waste revenue budget.
Financial Consequences – Capital Activities set out in this report are in accordance with the Waste capital budget.
Number of attachments to the report: None
Comments/recommendations from Overview & Scrutiny Committee N/A
Background Papers 19/1/2019 - Waste Procurement, Corporate Issues and Reform Committee
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution
Yes
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? N/A Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction
This report provides the Waste and Recycling Committee with an overview of performance of the Waste and Resources Management Services (WRMS) and the Household Waste Recycling Centre Management Services (HWRCMS) Contracts, with updates on key issues currently affecting the waste management services during this period.
2. Contract Performance
This report uses cumulative data for Contract year 7 (2025/26), Quarter 3 (April 2025 to December 2025), combined for the two Contracts held by Suez. This is the latest verified data available at the time of writing of the report.
2.1Cumulative Data
Data is provided for Quarter 3 of Contract year 7, alongside a comparison for the same period of the previous year, 2024/25:
OVERALL Combined Performance (WCA + HWRC) 2025 / 2026 2024 / 2025 Cumulative data (Year to date figures) Qtr 3 Qtr 3 Total arisings (t) 776,216 783,747 Combined Recycling Rate* 46% 48% Diversion Rate 99% 99% HWRC Combined Performance Recycling Rate (Household Waste)* 62% 63% Diversion (Household Waste) 99% 99% WCA Recycling Collections Rejected Kerbside Recycling Collections (t) 171 219 MRF Contamination Rate (Commingled) 18% 17%
*This Recycling Rate relates only to tonnage handled through the Suez contracts, f rom both WCA collections and delivered to HWRCs. It is not the same as the nationally reported Waste Data Flow recycling rate which includes other WCA waste and recycling streams that do not f low through Suez contracts. 2.2. Total Waste Arisings
Total waste arising for Contract year 7, up to Quarter 3 (2025/26) was over 776k tonnes(t), which is slightly lower (-1%) than the levels in the same period of the previous year (c.7.5kt lower).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contracts UpdateReport | 281 KB | DownloadRead as text |
Follow Greater Manchester Waste & Recycling Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | ApologiesTo note the apologies for absence received from Councillor Sue Maitland (Trafford) Subs: Gina Reynolds (Salford) Apol... | Noted | Open |
| 11 Mar 2026 | Chairs Announcements and Urgent BusinessThat the Committee notes the sad loss of Councillor David Lancaster MBE and acknowledges the significant contribution... | Decided | Open |
| 11 Mar 2026 | Declarations of InterestThere were no declarations of interest reported. | Decided | Open |
| 11 Mar 2026 | Greater Manchester Waste & Recycling Committee Minutes 21 January 2026That the minutes of the meeting held on 21 January 2026 be approved as a correct record. | Approved | Open |
| 11 Mar 2026 | Update on Delivery of the Communications and Behavioural Change PlanThat the contents of the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.