Capital Programme and Asset Management Update

Noted Committee 1 paper

AI summaryGreater Manchester Waste and Recycling Committee noted updates on the Reliance Street HWRC rebuild and Over Hulton MRF procurement, and asked officers to push for stronger fly tipping laws.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport noted; officers to write on fly tipping
MoneyNot stated
What happens nextWaste Crime ConferenceGMCA Waste Crime Conference on Friday 20 th March
Who it affectsGreater Manchester waste servicesHWRC users, recycling capacity, planning in Bolton

What was decided

The Committee noted the report's contents and that contract awards will follow the Constitution and Contract Procedure Rules. Report P3

Officers were asked to write to the government seeking changes to fly tipping legislation to strengthen local authority powers.

Members were reminded the GMCA Waste Crime Conference takes place on Friday 20 th March.

Why

The report provided Q4 2025-26 updates on the GMCA waste asset portfolio, covering Category A operational facilities, Category B buildings and land, and Category C closed landfill sites. Report P1, P22, P23

Reliance Street redevelopment has faced delays from unforeseen ground conditions, including legacy piles from a former anaerobic digestion plant, service diversions, and slope stability risks. Report P27, P28

The Over Hulton MRF is being procured under the Procurement Act 2023 through a 3-stage process, with two bidders now in Stage 2 and a planning application submitted to Bolton Council in December. Report P34, P35, P36, P37, P38

What happens next

Reliance Street work over the next 6 months: conclude piling and ground remediation, structural form work, slabs, container bays, access road, and a new Renew shop and welfare building. Report P29

Over Hulton MRF: conclude procurement stages 2 and 3, obtain planning permission from Bolton Council, submit an Environmental Permit application to the Environment Agency, and confirm enabling and supporting works. Report P39

Officers will write to the government seeking changes to fly tipping legislation to enhance local authority powers.

Options considered

  • Chosen: Note the report and matters set out within it. Standard committee process for capital update Report P2, P3
  • Chosen: Note that contract awards will be in accordance with the Constitution and Contract Procedure Rules
  • Chosen: Officers to write to government on fly tipping legislation changes
  • Not in decision text: Approve delegation of contract award for the Over Hulton MRF to GMCA's Chief Finance Officer. Requested in the report but not included in the formal decision Report P41

Implications

  • Legal: Activities in the report are in accordance with the terms of the WRMS and HWRCMS contracts. Report P9
  • Financial: Revenue activities are in accordance with the Waste revenue budget; capital activities are in accordance with the Waste capital budget. Report P10, P11
  • Risk: Contract performance and associated risks are captured in the GMCA corporate risk register. Report P8
  • Other: Equalities Impact, Carbon and Sustainability Assessment: not applicable. Report P7

Who and where

  • Users of the Reliance Street HWRC in Newton Heath Report 2.1, P26
  • Greater Manchester residents using waste and recycling services Report P22, P23
  • Bolton Council as planning authority for the Over Hulton MRF Report P38
  • Environment Agency for the Environmental Permit application Report P38

Timeline

  • 30th June: Reliance Street HWRC closed to the public Report P26
  • Monday 8th September 2025: Reliance Street redevelopment commenced Report P26
  • late November: Stage 1 of Over Hulton MRF procurement completed Report P35
  • December: Planning application for the Over Hulton MRF submitted to Bolton Council Report P38
  • January: Stage 2 of Over Hulton MRF procurement began Report P37
  • Friday 20 th March: GMCA Waste Crime Conference
  • 2nd of April: Stage 2 of MRF procurement expected to conclude Report P37
  • April: Planning application determination expected Report P38
  • June: Appointment of preferred bidder and contract award for the MRF expected Report P37
  • autumn 2027: Over Hulton MRF completion anticipated, subject to several unknown requirements Report P38

Plain English for the jargon

  • HWRC: Household Waste Recycling Centre
  • MRF: Materials Recovery Facility
  • DMR: Dry Mixed Recyclables
  • PTT: Pots, Tubs, Trays
  • IVC: In-Vessel Composter
  • RaWS: National Resources and Waste Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That the matters set out within the report be noted. 2. That it be noted that award of contracts will be in accordance with the Constitution and Contract Procedure Rules. 3. That the Committee requests that officers write to the government on their behalf seeking changes to fly tipping legislation to enhance local authority powers. 4. That members be reminded that the GMCA Waste Crime Conference would be taking place on Friday 20 th March.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Waste & Recycling Committee

Purpose of report

To provide the Committee with updates on key capital projects and lifecycle projects during quarter 4 of 2025-26.

Recommendations: The Committee is recommended to:

1. Note and comment on matters set out within the report; and 2. Note the award of contracts will be in accordance with the Constitution and Contract Procedure Rules.

Contact Officers Michael Kelly

Head of Engineering and Asset Management,

Waste and Resources

[email protected] Equalities Impact, Carbon and Sustainability Assessment: Not applicable

Risk Management Performance of the contracts and associated risks are captured in the GMCA corporate risk register.

Legal Considerations Activities set out in this report are in accordance with the terms of the WRMS and HWRCMS contracts.

Financial Consequences – Revenue Activities set out in this report are in accordance with the Waste revenue budget.

Financial Consequences – Capital Activities set out in this report are in accordance with the Waste capital budget.

Number of attachments to the report: None

Comments/recommendations from Overview & Scrutiny Committee Not applicable

Background Papers Not applicable

Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution ?

No

Exemption from call in

Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?

No

Bee Network Committee

Not applicable Overview and Scrutiny Committee

Not applicable 1. Introduction This report provides members with updates concerning the Waste and Resources asset portfolio. It includes progress summaries for significant projects conducted during the fourth quarter of 2025-26. The Engineering Team oversees the waste estate, which consists of three primary asset categories.

Category A WRMS Contract Facilities (Lot 1) Lot 1 includes 28 separate waste reception facilities located at 11 different sites. HWRMS Contract Facilities (Lot 2) Lot 2 includes 11 separate Household Waste Recycling Centres. Category B Buildings and Land Category B includes all other Land and building premises separate to the WRMS and HWRMS estate. Category C Closed Landfill Sites Category C includes 4 previously operated dilute and disperse landfill sites that have since been closed and are subject to ongoing management requirements.

2. Category (A) Updates – Operational Waste Facilities

2.1Reliance Street (HWRC) 1. Background – Redevelopment of the existing HWRC at Reliance Street in Newton Heath, is required, due to the current facility being beyond its economic life span and the restricted layout which does not encourage high-levels of recycling. A new improved HWRC will provide a larger facility giving more capacity to receive, manage and recycle commodities by providing 16 individual bulk containers to segregate materials like many of our other HWRC’s across the region.

2. Current Position – Redevelopment activities commenced on Monday 8th September 2025, the HWRC was closed to the public on 30th June to facilitate a full site clearance and handover to our appointed contractor. During the past 6 months the main focus has been on the following activities: • Site clearance and demolition of existing structures; • Ground works and remediation to stabilise conditions for the new HWRC layout; • Drainage and service installation s; and • Piling installation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Asset Management UpdateReport 206 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 15 attended
AQ
Councillor Alan QuinnChair, expected
SA
Councillor Stephen AdsheadVice-Chair, expected
RS
Councillor Richard SilvesterCommittee Member, expected
GS
Councillor Gareth Staples-JonesCommittee Member, expected
SA
Councillor Shaukat AliCommittee Member, expected
LI
Councillor Lee-Ann IgbonCommittee Member, expected
KR
Councillor Ken RustidgeCommittee Member, expected
AR
Councillor Aasim RashidCommittee Member, expected
BB
Councillor Barbara BenthamCommittee Member, expected
PH
Councillor Paul HeilbronCommittee Member, expected
JA
Councillor Jake AustinCommittee Member, expected
LB
Councillor Liam BillingtonCommittee Member, expected

All 15 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Capital Programme and Asset Management UpdateThis decision
  2. Capital Programme Outturn 2025/26Noted
  3. GMCA Capital Programme 2025/26 - 2028/29Noted
  4. GMCA Capital Programme -2024/25 - 2027/28Noted
  5. 2024-25 Capital Programme and Asset Management UpdateNoted
  6. Transport Capital ProgrammeNoted

More from Greater Manchester Combined Authority Greater Manchester Waste & Recycling Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 ApologiesTo note the apologies for absence received from Councillor Sue Maitland (Trafford) Subs: Gina Reynolds (Salford) Apol... Noted Open
11 Mar 2026 Chairs Announcements and Urgent BusinessThat the Committee notes the sad loss of Councillor David Lancaster MBE and acknowledges the significant contribution... Decided Open
11 Mar 2026 Declarations of InterestThere were no declarations of interest reported. Decided Open
11 Mar 2026 Greater Manchester Waste & Recycling Committee Minutes 21 January 2026That the minutes of the meeting held on 21 January 2026 be approved as a correct record. Approved Open
11 Mar 2026 Contracts UpdateThat the performance of the Waste and Resource Management contracts be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies