Greater Manchester Combined Authority
Greater Manchester Combined Authority, Friday 27 March 2026 at 10.30am

Economy, Business & International Programmes & Projects 2026/7

Approved Committee 1 paper

AI summaryGMCA approved provisional 2026/27 budget allocations for 11 economy, business and international programmes, including £19,929,200 for local authority ED&R grants and £16,200,00 for the Business Growth Hub.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProvisional 2026/27 budget allocations for 11 programmes and projects
MoneyNot stated
What happens nextDelivery in 2026/27Managed through existing delegations in the Constitution
Who it affectsAll 10 GM local authoritiesPlus businesses, entrepreneurs, social economy, foreign investors

What was decided

The combined authority approved the proposed economic and business programmes and projects and their provisional budget allocations for the 2026/27 financial year. Report 1.5

It noted that programmes and projects will be managed through existing delegations, as contained within the Constitution.

Why

The allocations are needed to deliver the Greater Manchester Strategy Delivery Plan, in particular the 'a great place to do business' workstream, following high-level budget approval on 13 February 2026. Report 1.1, 1.3, 1.5

They are intended to meet specific end states, including raising productivity above the national average, increasing R&D investment by £750m per annum, growing the visitor economy to £15 billion by 2030, and supporting a thriving social economy. Report P28, P29, P31, P33

What happens next

Each programme or project will be delivered by the EICI Directorate's dedicated Programmes Team, with risk management systems in place for each one. Report P1

Local Authority ED&R Flexible Grants will be allocated using the existing methodology based on UK Shared Prosperity Fund formulas, to support business continuity. Report P75, 2.1

Some existing contracts, including Innovation Navigator and the Support for the Social Economy programme, are intended to be extended for continued delivery. Report 2.5, 2.7

The money

  • £19,929,200 Local Authority ED&R Flexible Grant Funding total (£11,190,200 revenue + £8,739,000 capital) Report 2.1, P60, P61, P62
  • £16,200,00 Business Growth Hub revenue allocation Report 2.11, P74
  • £6,350,000 International Promotion and Inward Investment revenue Report 2.10, P73
  • £4,500,000 Innovation Navigator revenue Report 2.5, P66
  • £1,500,000 Access to Innovation Capital (£500,000 revenue + £1,000,000 capital) Report 2.9, P70, P71, P72
  • £1,000,000 GM Colleges Innovation Connector Network revenue Report 2.6, P67
  • £948,059 Made Smarter Adoption North West revenue Report 2.3, P64
  • £907,500 Support for the Social Economy revenue Report 2.7, P68
  • £850,255 Build A Business in GM Libraries revenue Report 2.2, P63
  • £800,993 GM Good Employment Charter revenue Report 2.8, P69
  • £512,500 Care Smarter Pilot revenue Report 2.4, P65

Options considered

  • Chosen: Approve the proposed programmes and projects with their provisional budget allocations for 2026/27. Required to deliver the GMS Delivery Plan and meet Integrated Settlement outcomes following high-level budget approval on 13 February 2026. Report 1.5

Implications

  • Financial: Approval commits GMCA to the proposed revenue and capital allocations for 2026/27, with budget approval set out in the background papers. Report P4, P5, P6, P7
  • Legal: No specific legal considerations are set out in the report; any legal implications will be considered at programme or project level prior to award. Report P2, P3
  • Risk: Risk will be managed by the EICI Directorate's dedicated Programmes Team, using risk management systems for each programme or project and within the directorate's wider risk management process. Report P1
  • Staffing: Programmes are delivered through a range of roles, including Enterprise Officers in libraries, Innovation Advisors and Connectors in each local authority, and Strategic Account Managers and Enterprise Advisors in the Business Growth Hub. Report P58, 3.1
  • Other: In 2026/27, the Business Growth Hub is expected to respond to 15,000 enquiries, engage with more than 9,000 businesses and provide in-depth support to 2,000; the Innovation Connector Network plans to engage 1,500 businesses, refer 830 into wider support and integrate 400 employers into college skills provision. Report 2.6, 2.11

Who and where

  • All 10 Greater Manchester local authorities Report 3.1, P58
  • Start-ups, early-stage businesses and entrepreneurs across the city region Report 2.2, P58
  • Greater Manchester-based manufacturers eligible for Made Smarter support Report 2.3, P58
  • Adult social care providers in Greater Manchester, through the Care Smarter Pilot Report 2.4, P58
  • Social enterprises, co-operatives and community businesses, including the Our Business platform and 10GM support Report 2.7, P58
  • Employers participating in or joining the GM Good Employment Charter Report 2.8, P58
  • Foreign-owned companies targeted by inward investment activity Report 2.10, P58
  • FE colleges and their local innovation hubs Report 2.6, P58

Timeline

  • 13 February 2026: GMCA approved high-level budget allocations to resource implementation of the GMS Delivery Plan for 2026/27. Report 1.5, P9, P10, P11, P12, P13
  • 2025/26: Build A Business in GM Libraries supported more than 700 potential entrepreneurs and businesses; Made Smarter supported over 100 businesses and match-funded 19 investment projects; Innovation Navigator has supported more than 500 businesses since inception; international promotion activity on track to attract more than 50 conferences with a total economic impact of £75m; inward investment on track to secure more than 50 FDI projects creating more than 2,500 jobs. Report 2.2, 2.3, 2.5, 2.10
  • 2026/27 financial year: Proposed programmes and projects to be delivered using approved allocations, subject to existing delegations. Report 1.5

Plain English for the jargon

  • ED&R: Economic Development and Regeneration, a pillar of GMCA's Integrated Settlement covering business productivity, jobs, floorspace, regeneration and cultural activities.
  • GMS: Greater Manchester Strategy, the city region's overarching strategy with a ten-year delivery plan.
  • RDEL / CDEL: Revenue Departmental Expenditure Limit and Capital Departmental Expenditure Limit, the two categories of budget covered by the allocations.
  • FDI: Foreign Direct Investment, the focus of GMCA's inward investment activity.
  • VCSE: Voluntary, Community and Social Enterprise organisations, including those supported by 10GM and the Our Business platform.
  • Integrated Settlement: Greater Manchester's funding arrangement combining multiple funding streams to support the GMS Delivery Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10A

Resolved

That the proposed economic and business programmes and projects and their respective provisional budget allocations as set out in the report for the 2026/27 Financial Year, be approved. 2. That it be noted that programmes and projects will be managed through existing delegations, as contained within the Constitution.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Risk management

Risk will be managed by the EICI Directorate’s dedicated Programmes Team, with risk management systems in place for each programme/project, as well as forming part of the directorate’s risk management process.

Legal Considerations

There are no specific legal considerations set out in this report. Any legal implications will be considered at programme/project level, prior to award.

Financial Consequences – Revenue

The report sets out the revenue implications for each programme/project, summarised in Section 4 - Economy, Business and International Programmes and Projects 2026/27 – Proposed Allocations Summary. The approval of budgets to meet these costs is set out in the background papers.

Financial Consequences – Capital

The report sets out the capital implications for each programme/project, summarised in Section 4 - Economy, Business and International Programmes and Projects 2026/27 – Proposed Allocations Summary. The approval of budgets to meet these costs is set out in the background papers.

Number of attachments to the report: 3

Background papers

GMCA Revenue and Capital Budgets 2026/27 Overview

(GMCA, 13th February 2026)

GMCA General Revenue Budget 2026/27: Delivering the Greater Manchester Strategy (GMCA, 13th February 2026)

GMCA Capital Programme 2025/26 – 2028/29

(GMCA, 13th February 2026) Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution

No

Exemption from call in

Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?

No

Bee Network Committee

No

Overview and Scrutiny Committee

N/A 1. Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Economy, Business & International Programmes & Projects 2026/7Report 406 KB DownloadRead as text

At this meeting

Whole meeting
1ApologiesDecided 2Chairs AnnouncementsNoted 3Urgent BusinessDecided 4Declarations of InterestDecided 5AGMCA Minutes - 13 February 2026Approved 5BGMCA Overview & Scrutiny Committee: 11 & 25 February 2026Noted 5CGMCA Audit Committee - 23 February & 9 March 2026Noted 5DGMCA Waste & Recycling Committee - 11 March 2026Noted 6GMCA Constitution: Update on Procedural Rules to Clarify and Reflect current PracticeApproved 7AGreater Manchester Good Growth Fund :March AllocationsNoted 7BGood Growth Fund Investment decisions through the Implementation of a Greater Manchester Social Value ContractNoted 8AGMCA Revenue Update Quarter 3 2025/26Noted 8B2026/27 GMCA Capital StrategyApproved 8CTreasury Management Strategy Statement, Minimum Revenue Provision Policy Statement and Annual Investment Strategy 2026/27Approved 8DGreater Manchester's Support for Local Government FinanceNoted 9AApproval of the VCFSE Accord RefreshNoted
10AEconomy, Business & International Programmes & Projects 2026/7This decision
10BYear One Prioritisation of Creative Places Growth Funding to support delivery of the Greater Manchester Creative Industries Sector Development PlanApproved 10CGreater Manchester Culture Fund Awards 2026 - 29Approved 10DProposed Oldham Town Centre Mayoral Development Corporation (MDC) : Approval to ConsultNoted 10EProposed Ashton and Stalybridge Mayoral Development Corporation (MDC): Approval to ConsultNoted 10FMiddleton Mayoral Development Corporation: Approval to ConsultNoted 10GIn Principle Approval of the Establishment of a Leigh Mayoral Development ZoneApproved 11AApproval of Proposed Allocation and Administration Arrangements for GMCA's Homelessness and Migration budget for 2026-2029Approved 12AKey Findings of the 2025 #Bee Well 2025 Survey ResultsNoted 13AProgress update on the Ambition to position Greater Manchester as an AI Demonstrator City Region and the Establishment a GM Data UnitNoted 14Exclusion of the Press and PublicDecided 14AGreater Manchester Good Growth Fund March AllocationsPrivate 14BGMCA Culture Fund Awards 2026 - 29Private

Who was there

0 of 14 attended
RR
Rachael RobinsonCouncil Staff, expected
SK
Shelley KiplingCouncil Staff, expected
EW
Councillor Eleanor WillsCommittee Member, expected
SH
Suzanne HeslingCouncil Staff, expected
GM
GM Mayor Andy BurnhamChair, expected
TR
Councillor Tom RossCommittee Member, expected
AS
Councillor Arooj ShahCommittee Member, expected
NE
Councillor Neil EmmottCommittee Member, expected
NP
Councillor Nicholas PeelCommittee Member, expected
EO
Councillor Eamonn O'BrienCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
DM
Councillor David MolyneuxCommittee Member, expected

All 14 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Economy, Business & International Programmes & Projects 2026/7This decision
  2. GMCA Economy, Business Growth & Skills Overview & Scrutiny CommitteeApproved

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open