AI summaryGMCA approved provisional 2026/27 budget allocations for 11 economy, business and international programmes, including £19,929,200 for local authority ED&R grants and £16,200,00 for the Business Growth Hub.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProvisional 2026/27 budget allocations for 11 programmes and projects
MoneyNot stated
What happens nextDelivery in 2026/27Managed through existing delegations in the Constitution
Who it affectsAll 10 GM local authoritiesPlus businesses, entrepreneurs, social economy, foreign investors
What was decided
The combined authority approved the proposed economic and business programmes and projects and their provisional budget allocations for the 2026/27 financial year. Report 1.5
It noted that programmes and projects will be managed through existing delegations, as contained within the Constitution.
Why
The allocations are needed to deliver the Greater Manchester Strategy Delivery Plan, in particular the 'a great place to do business' workstream, following high-level budget approval on 13 February 2026. Report 1.1, 1.3, 1.5
They are intended to meet specific end states, including raising productivity above the national average, increasing R&D investment by £750m per annum, growing the visitor economy to £15 billion by 2030, and supporting a thriving social economy. Report P28, P29, P31, P33
What happens next
Each programme or project will be delivered by the EICI Directorate's dedicated Programmes Team, with risk management systems in place for each one. Report P1
Local Authority ED&R Flexible Grants will be allocated using the existing methodology based on UK Shared Prosperity Fund formulas, to support business continuity. Report P75, 2.1
Some existing contracts, including Innovation Navigator and the Support for the Social Economy programme, are intended to be extended for continued delivery. Report 2.5, 2.7
The money
£19,929,200 Local Authority ED&R Flexible Grant Funding total (£11,190,200 revenue + £8,739,000 capital) Report 2.1, P60, P61, P62
£16,200,00 Business Growth Hub revenue allocation Report 2.11, P74
£6,350,000 International Promotion and Inward Investment revenue Report 2.10, P73
£948,059 Made Smarter Adoption North West revenue Report 2.3, P64
£907,500 Support for the Social Economy revenue Report 2.7, P68
£850,255 Build A Business in GM Libraries revenue Report 2.2, P63
£800,993 GM Good Employment Charter revenue Report 2.8, P69
£512,500 Care Smarter Pilot revenue Report 2.4, P65
Options considered
Chosen: Approve the proposed programmes and projects with their provisional budget allocations for 2026/27. Required to deliver the GMS Delivery Plan and meet Integrated Settlement outcomes following high-level budget approval on 13 February 2026. Report 1.5
Implications
Financial: Approval commits GMCA to the proposed revenue and capital allocations for 2026/27, with budget approval set out in the background papers. Report P4, P5, P6, P7
Legal: No specific legal considerations are set out in the report; any legal implications will be considered at programme or project level prior to award. Report P2, P3
Risk: Risk will be managed by the EICI Directorate's dedicated Programmes Team, using risk management systems for each programme or project and within the directorate's wider risk management process. Report P1
Staffing: Programmes are delivered through a range of roles, including Enterprise Officers in libraries, Innovation Advisors and Connectors in each local authority, and Strategic Account Managers and Enterprise Advisors in the Business Growth Hub. Report P58, 3.1
Other: In 2026/27, the Business Growth Hub is expected to respond to 15,000 enquiries, engage with more than 9,000 businesses and provide in-depth support to 2,000; the Innovation Connector Network plans to engage 1,500 businesses, refer 830 into wider support and integrate 400 employers into college skills provision. Report 2.6, 2.11
Who and where
All 10 Greater Manchester local authorities Report 3.1, P58
Start-ups, early-stage businesses and entrepreneurs across the city region Report 2.2, P58
Greater Manchester-based manufacturers eligible for Made Smarter support Report 2.3, P58
Adult social care providers in Greater Manchester, through the Care Smarter Pilot Report 2.4, P58
Social enterprises, co-operatives and community businesses, including the Our Business platform and 10GM support Report 2.7, P58
Employers participating in or joining the GM Good Employment Charter Report 2.8, P58
Foreign-owned companies targeted by inward investment activity Report 2.10, P58
FE colleges and their local innovation hubs Report 2.6, P58
Timeline
13 February 2026: GMCA approved high-level budget allocations to resource implementation of the GMS Delivery Plan for 2026/27. Report 1.5, P9, P10, P11, P12, P13
2025/26: Build A Business in GM Libraries supported more than 700 potential entrepreneurs and businesses; Made Smarter supported over 100 businesses and match-funded 19 investment projects; Innovation Navigator has supported more than 500 businesses since inception; international promotion activity on track to attract more than 50 conferences with a total economic impact of £75m; inward investment on track to secure more than 50 FDI projects creating more than 2,500 jobs. Report 2.2, 2.3, 2.5, 2.10
2026/27 financial year: Proposed programmes and projects to be delivered using approved allocations, subject to existing delegations. Report 1.5
Plain English for the jargon
ED&R: Economic Development and Regeneration, a pillar of GMCA's Integrated Settlement covering business productivity, jobs, floorspace, regeneration and cultural activities.
GMS: Greater Manchester Strategy, the city region's overarching strategy with a ten-year delivery plan.
RDEL / CDEL: Revenue Departmental Expenditure Limit and Capital Departmental Expenditure Limit, the two categories of budget covered by the allocations.
FDI: Foreign Direct Investment, the focus of GMCA's inward investment activity.
VCSE: Voluntary, Community and Social Enterprise organisations, including those supported by 10GM and the Our Business platform.
Integrated Settlement: Greater Manchester's funding arrangement combining multiple funding streams to support the GMS Delivery Plan.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10A
Resolved
That the proposed economic and business programmes and projects and their respective provisional budget allocations as set out in the report for the 2026/27 Financial Year, be approved. 2. That it be noted that programmes and projects will be managed through existing delegations, as contained within the Constitution.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Risk will be managed by the EICI Directorate’s dedicated Programmes Team, with risk management systems in place for each programme/project, as well as forming part of the directorate’s risk management process.
Legal Considerations
There are no specific legal considerations set out in this report. Any legal implications will be considered at programme/project level, prior to award.
Financial Consequences – Revenue
The report sets out the revenue implications for each programme/project, summarised in Section 4 - Economy, Business and International Programmes and Projects 2026/27 – Proposed Allocations Summary. The approval of budgets to meet these costs is set out in the background papers.
Financial Consequences – Capital
The report sets out the capital implications for each programme/project, summarised in Section 4 - Economy, Business and International Programmes and Projects 2026/27 – Proposed Allocations Summary. The approval of budgets to meet these costs is set out in the background papers.
Number of attachments to the report: 3
Background papers
GMCA Revenue and Capital Budgets 2026/27 Overview
(GMCA, 13th February 2026)
GMCA General Revenue Budget 2026/27: Delivering the Greater Manchester Strategy (GMCA, 13th February 2026)
GMCA Capital Programme 2025/26 – 2028/29
(GMCA, 13th February 2026) Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution
No
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
Bee Network Committee
No
Overview and Scrutiny Committee
N/A 1. Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.