What was decided
The Combined Authority approved the proposed funding allocations and administration arrangements for 12 named programmes covering temporary accommodation, homelessness prevention, refugee support, rough sleeping, and inclusion health for 2026 to 2029. Report 1.10, 3.5
Members noted the current position on the Community Accommodation Service Tier 3 programme, with year 3 spend estimated and subject to Ministry of Justice decisions after December 2027. Report 7.1, 7.2, 7.3, 7.4
Why
From April 2026 GMCA's homelessness funding from MHCLG moves into the Integrated Settlement, giving three-year funding stability and flexibility to adapt to local need. Report 1.8, 1.9, 3.0, 3.1
The Greater Manchester Strategy commits to a healthy home for all by 2038, a sustainable reduction in temporary accommodation, and rough sleeping as a rare, brief and non-recurring experience, and the programmes are designed to deliver these aims. Report 1.1, 1.2, 1.3, P73, P89, P113
Homelessness pressures have grown sharply: households in temporary accommodation are up 103 percent and children in temporary accommodation up 127 percent since 2019, alongside higher rough sleeping counts and rising temporary accommodation costs of £77.5million to GM local authorities. Report P40, P41, 2.4, P84
What happens next
Onward commissioning and grant funding agreements will be put in place with appropriate legal, procurement and information governance advice, and the £24,131,599 Empty Homes Programme will continue subject to satisfactory deployment and evaluation in 2026/27. Report 3.8, P2, P86
GMCA is reviewing whether long-term commissioning of Housing First, RSAP and WISH properties sits best at regional or local authority level, which may change future funding requirements. Report 6.8
The GM Homelessness Prevention Strategy will be reviewed from 2026, working with the GM Homelessness Action Network and the ten local authorities. Report 5.7
The money
- £124m Total proposed investment in homelessness and migration infrastructure over 2026 to 2029 Report 3.4
- £25,877,158 Total MHCLG homelessness funding included in the Integrated Settlement for 2026 to 2029 Report P59, 3.2
- £113,379,600 Total programme spend across the 12 programmes for 2026 to 2029 Report P72
- £83,019,713.77 Amount passported to GM local authorities, about 73 percent of the total Report P72, 3.6
- £24,131,599 Continuation of the Empty Homes Programme into a three-year programme Report P86, 4.2
- £4,000,000 Family Homelessness Prevention Programme, via grant and commissioning Report P87, 4.2, P77
- £23,389,199 Continuation of the A Bed Every Night programme to 31 March 2029 Report P165, P124
- £10,595,320 Continuation of the Housing First programme to 31 March 2029 Report P161
- £1,608,203 Continuation of Rough Sleeping Accommodation Programme schemes, subject to commissioning review Report P162
- £6,539,222 Continuation of the GM Youth Homelessness Prevention Service to 31 March 2029 Report P109
- £5,299,120 Continuation of the Refugee Welcome Programme Work and Skills provision to 31 March 2029 Report P110
- £641,167 Continuation of the Refugee Welcome Programme Homelessness Prevention Service to 31 March 2029 Report P111, P163
- £1,461,528 Restricted Eligibility Support Service (RESS) to 31 March 2029 Report P164
- £2,562,245 Continuation and development of the Homelessness Inclusion Health Service Report P166
- £771,792 Rough Sleeping Test and Learn Pilots to 31 March 2029 Report P167
- £3,163,215 Rough Sleeping Infrastructure including outreach roles, data and commissioning capacity Report P168
- £77.5million Spend by GM local authorities on renting temporary accommodation Report P84
Options considered
- Chosen: Approve the proposed funding allocations and administration arrangements for the 12 named programmes for 2026 to 2029. Delivers the Greater Manchester Strategy housing aims and provides three-year funding certainty under the new Integrated Settlement Report 1.1, 1.8, 1.9
- Rejected: Continue GMCA regional commissioning of Housing First, RSAP and WISH properties. Under review to determine whether local authority commissioning is more efficient in the long term, so future funding may be reduced or removed Report 6.8
- Rejected: Take a decision on the supported housing element of the Integrated Settlement allocation. Requires further iteration with local authorities and no decision is sought at this time Report 3.2
Implications
- Financial: Around 73 percent of the £113.4m programme total flows to GM local authorities via grant, with the remainder funding regional commissioning and core regional capabilities, primarily to VCFSE and non-profit providers. Report 3.6, P64, P72
- Financial: Revenue and capital spend will be managed within the grant allocation through ongoing contract and grant assurance processes. Report P3, P4, P5, P6
- Legal: Legal advice will be taken on onward grant agreements, procurement and information governance, with further commissioning and grant funding agreements to follow. Report P2, 3.8
- Equalities: Programmes target groups at higher risk of homelessness, including young people aged 18 to 25, care leavers, LGBTQ+ young people, refugees and people seeking asylum, prison leavers, people with no recourse to public funds, and people with multiple disadvantage including mental health and substance misuse needs. Report 5.2, P94, P95, P98, 6.15, 6.16, 6.17
- Other: Rough sleeping and homelessness work sits within Live Well and the broader Greater Manchester Strategy, with governance through the Housing First Board, the Housing First Planning and Infrastructure Commission, and the Greater Manchester Housing Needs Group. Report 1.12, 5.4
- Risk: Year 3 Community Accommodation Service Tier 3 spend is an estimate and is subject to Ministry of Justice decision-making after December 2027. Report 7.3, P70
Who and where
- Households owed a prevention or relief duty, which rose 23 percent and 9 percent respectively since 2019 Report P40
- Households and children in temporary accommodation, which have roughly doubled since 2019, with B&B placements up 69 percent and 84 percent for households with children Report P40
- People sleeping rough in Greater Manchester, with 126 individuals recorded in the latest annual snapshot Report P41
- Young people aged 18 to 25 at risk of homelessness, including LGBTQ+ young people and those with poor mental health Report P94
- Refugees and people seeking asylum, including those leaving Home Office accommodation and at risk of street homelessness Report P45, P52, 5.2, P95
- People leaving prison at risk of rough sleeping, supported through the Community Accommodation Service Tier 3 pathway Report P153, 7.1
- People with no recourse to public funds and those experiencing multiple disadvantage, supported through RESS and the Inclusion Health Service Report 6.15, 6.16, 6.17
- VCFSE and non-profit organisations that deliver the majority of regionally commissioned services Report 3.6, P64
Timeline
- From April 2026: Homelessness funding from MHCLG moves into GMCA's Integrated Settlement as the first devolved funding pot under Health, Wellbeing and Public Service Reform Report 1.8, 1.9, 3.1
- April 2026: Empty Homes Programme launches, with 400 ringfenced properties for families who would otherwise be in B&B accommodation Report 4.3
- 2026/27 to 2028/29: Three-year delivery of the 12 approved programmes, with the majority of the £113.4m total spend Report P69, P72
- Up to December 2027: Current Community Accommodation Service Tier 3 budget runs; year 3 allocations subject to Ministry of Justice decision-making Report 7.2, 7.3
- 31 March 2029: End date for the approved continuation of the Housing First, RSAP, Youth Homelessness Prevention, RWP Work and Skills, RWP Homelessness Prevention, RESS, ABEN and Test and Learn programmes Report P109, P110, P111, P161, P162, P163, P164, P165, P167
- By 2035: Greater Manchester Strategy target for a sustainable reduction in the number of families and vulnerable adults in unsuitable temporary accommodation Report P73
- By 2038: Greater Manchester Strategy target of a healthy home for all Report 1.1
Plain English for the jargon
- Integrated Settlement: The funding mechanism from which MHCLG homelessness funding for Combined Authorities is distributed from 2026/27 onwards, the first devolved pot under the Health, Wellbeing and Public Service Reform pillar
- A Bed Every Night (ABEN): GMCA's off-the-streets emergency accommodation programme operating above 600 bedspaces across all ten local authorities
- Housing First: An approach that provides permanent housing with intensive support for people experiencing chronic homelessness with high, multiple and complex needs, without preconditions
- RSAP: Rough Sleeping Accommodation Programme, providing longer-term move-on housing for people who have experienced street homelessness
- RESS: Restricted Eligibility Support Service, providing advice and support to people without recourse to public funds
- CAS3: Community Accommodation Service Tier 3, providing accommodation for people leaving prison who are at risk of rough sleeping
- Live Well: Greater Manchester's approach to prevention and early support, delivered through Live Well Centres, Spaces and Offers
- MHCLG: Ministry of Housing, Communities and Local Government, the government department providing the homelessness funding allocation
- GMHAN: Greater Manchester Homelessness Action Network, the partnership working with GMCA on homelessness prevention
- VCFSE: Voluntary, Community, Faith and Social Enterprise sector, which delivers the majority of regionally commissioned homelessness services