Resolved
Resolved – That the update on the 2023/4 planned maintenance programme be noted That it be noted that the 3-year works programme (2024-2027) is currently out to tender.
Eltham Crematorium Joint Committee noted this item on Wednesday 5 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the update on the 2023/4 planned maintenance programme be noted That it be noted that the 3-year works programme (2024-2027) is currently out to tender.
7.1.1 The 2023/4 works programme has been completed and works are in the defects liability period with expenditure committed to. The Joint Committee approved a 3-year works programme on 5th February 2024. Design works have been undertaken and tenders are being sought for the works.
8. Consultation Results
8.1There is no duty to consult therefore none undertaken.
9. Cross-Cutting Issues and Implications
Issue Implications Sign-off Legal including The Eltham Crematorium Joint Davidaire Human Rights Committee is an executive body which Horsford, Act operates under joint arrangements (see Interim Head of the Constitution; Part 2, Article 11.02 – Legal Services 11.03). 27 January 2025
Crematoria functions are delegated to the Eltham Crematorium Joint Committee as per the Constitution, Part 3, Schedule A.4.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
6.1: Appendix 1: Crem PPM 2023-24 updateAppendix | 44 KB | Download |
PDF |
Report of Programme Manager, Capital Projects & Property MaintenanceReport | 86 KB | DownloadRead as text |
Follow Eltham Crematorium Joint Committee at Greenwich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | Bereavement Services Managers ReportNoted the information provided in the report regarding cremation, memorial sales and operational issues. Noted the do... | Noted | Open |
| 23 Jun 2026 | Report of Programme Manager, Capital Projects & Property MaintenanceNoted the progress of the 3-year works programme included as Appendix 1 of the report. Noted that as agreed at the la... | Noted | Open |
| 23 Jun 2026 | Finance Managers Treasurer ReportNoted the 2025/26 yearend financial position summarised in 4.1 and set out in Appendix A of the report. Noted the pro... | Noted | Open |
| 4 Feb 2026 | Bereavement Services Managers ReportNoted the information provided in this report regarding cremation, memorial sales and operational issues. Noted the i... | Noted | Open |
| 4 Feb 2026 | Report of Programme Manager, Capital Projects & Property MaintenanceNoted the progress of the 3-year works programme included as Appendix 1 of the report. Noted the tendered works and f... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.