Eltham Crematorium Joint Committee, Wednesday 4 February 2026 at 6.30pm

Report of Programme Manager, Capital Projects & Property Maintenance

Noted Committee 2 papers

AI summaryEltham Crematorium Joint Committee noted a £104,385 shortfall on its 3-year works programme and agreed to defer some work to 2027/8, re-profiling the budget so Burial Chapel repairs complete first.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNorth Chapel refurbishment pushed back to let Burial Chapel repairs go first
Money£104,385 shortfallTendered works £1,485,875 vs budget £1,381,490
What happens nextRe-profile 3-year budgetCover works in 2025/6 and 2026/7, defer to 2027/8
Who it affectsCrematorium service usersReduced provision, not total loss, while North Chapel refurbished

What was decided

The Committee noted progress on the 3-year works programme first approved on 5th February 2024 and noted the tendered works and management fee totalling £1,485,875 against a budget of £1,381,490, a projected shortfall of £104,385. Report 7.1

The Committee confirmed that work would be deferred to 2027/8 and agreed to re-profile the 3-year budget to facilitate the works in 2025/6 and 2026/7.

The Committee agreed to move the North Chapel refurbishment back so that wider Cemetery repair to the Burial Chapel, funded by Royal Borough of Greenwich, can complete first.

Why

The 3-year works programme was originally approved on 5th February 2024; design work has been done and a contractor appointed after competitive tender. Report 7.1

The budget for 2026/7 has yet to be agreed, so the Committee could either uplift the budget to cover the increase or re-profile works into the next financial year. Report P7

Sequencing the Burial Chapel repair first allows the Crematorium to keep offering services in that chapel while the North Chapel is refurbished, so users see reduced rather than total loss of provision.

What happens next

Officers will re-profile the 3-year budget to move elements of the work to 2027/8. Report P7

The wider Cemetery repair to the Burial Chapel, funded by Royal Borough of Greenwich, will be completed before the North Chapel refurbishment begins.

The 2026/7 budget will be set in February by the Joint Committee, considering any pay increase, fee income and demand. Report P6

The money

  • £1,485,875 Tendered works and fee to manage the works
  • £1,381,490 Previously agreed budget allocation for the 3-year works
  • £104,385 Projected shortfall against the 3-year budget

Options considered

  • Rejected: Approve the 2026/27 works and uplift the budget to cover the increase. Committee instead chose to re-profile so elements move to 2027/8 Report P7
  • Chosen: Re-profile the works so elements move to the next financial year. Avoids budget uplift and lets Burial Chapel repair go first Report P7

Implications

  • Financial: Report notes an overspend against the previously agreed 3-year property works budget; year-end distribution payments to each borough may vary depending on outturn. Report P7, P8
  • Risk: Key risks and mitigations have been considered and are being monitored under the Council's risk management Toolkit. Report P11
  • Equalities: Decisions have remote or low relevance to the Equality Act and no apparent equality impact on end users. Report P9
  • Climate: Works are primarily maintenance of buildings and infrastructure, with very little or no impact on the Greenwich Carbon Neutral Plan. Report P10
  • Legal: Crematoria functions are delegated to the Eltham Crematorium Joint Committee; legal issues arise from the decisions being made. Report P5
  • Other: The Joint Committee meeting is open to the public and supports engagement with communities of the three boroughs. Report P12

Who and where

  • Users of Eltham Crematorium, who will see reduced service rather than total loss while the North Chapel is refurbished
  • Communities served by the three member boroughs: Royal Borough of Greenwich, Dartford and Bexley Report P6, P12

Timeline

  • 5th February 2024: Joint Committee approved the 3-year works programme Report 7.1
  • 2025/6 and 2026/7: Works to be facilitated under the re-profiled budget
  • February of each year: Joint Committee sets the budget, considering pay, fee income and demand Report P6
  • 2027/8: Work deferred to this financial year

Plain English for the jargon

  • Eltham Crematorium Joint Committee: Joint committee made up of Royal Borough of Greenwich, Dartford and Bexley that oversees the Eltham Crematorium, which is managed by Royal Borough of Greenwich on its behalf.
  • Re-profile the budget: Move planned spending between financial years so that the cost of the works is spread across a different timetable.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Noted the progress of the 3-year works programme included as Appendix 1 of the report. Noted the tendered works and fee to manage the works comes to £1,485,875. The budget allocation (noting budget for 26/7 has yet to be agreed) was £1,381,490 leaving a projected shortfall of £104,385. Confirmed to defer work to 2027/8. Agreed to re-profile the 3-year budget to facilitate the works in 25/6 and 26/7 and to effectively move the North Chapel refurbishment back to enable wider Cemetery repair (funded by Royal Borough of Greenwich) to the Burial Chapel to complete first, this will enable the Crematorium to offer services in the Burial chapel whilst the North Chapel is refurbished thus resulting in reduced service provision, rather than total loss.
Word for word from the decision Greenwich published for this meeting. Source: committees.royalgreenwich.gov.uk

Follow this further

Built from Greenwich's papers

What the report saysPro

Report to Eltham Crematorium Joint Committee

Reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 58 KB Download
PDF
Report of Programme Manager, Capital Projects & Property MaintenanceReport 98 KB DownloadRead as text

At this meeting

Whole meeting
4MinutesOn the agenda 5Bereavement Services Managers ReportNoted
6Report of Programme Manager, Capital Projects & Property MaintenanceThis decision
7Finance Managers Treasurer ReportNoted

Who was there

4 of 9 attended
DL
Councillor David LeafCommittee Member, apologies, sent representative
SB
Councillor Sandra BauerCommittee Member, present
RD
Councillor Richard DimentCommittee Member, present
RW
Councillor Richard WellsCommittee Member, apologies, sent representative
MW
Councillor Miranda WilliamsVice-Chair, in the Chair, in attendance
CT
Councillor Chris TaylorDeputy, in attendance
BS
Bereavement Services ManagerOfficer, in attendance
PM
Programme Manager (Corporate)Officer, in attendance
HO
Head of Accounting and Business ChangeOfficer, in attendance

On this subject at Greenwich

Search all
  1. Report of Programme Manager, Capital Projects & Property MaintenanceThis decision
  2. Report of Programme Manager, Capital Projects & Property MaintenanceNoted
  3. Report of Programme Manager, Capital Projects & Property MaintenanceNoted
  4. Report of Programme Manager, Capital Projects & Property MaintenanceNoted
  5. Report of Programme Manager, Capital Projects & Property MaintenanceNoted

More from Greenwich Eltham Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 Bereavement Services Managers ReportNoted the information provided in the report regarding cremation, memorial sales and operational issues. Noted the do... Noted Open
23 Jun 2026 Report of Programme Manager, Capital Projects & Property MaintenanceNoted the progress of the 3-year works programme included as Appendix 1 of the report. Noted that as agreed at the la... Noted Open
23 Jun 2026 Finance Managers Treasurer ReportNoted the 2025/26 yearend financial position summarised in 4.1 and set out in Appendix A of the report. Noted the pro... Noted Open
4 Feb 2026 Bereavement Services Managers ReportNoted the information provided in this report regarding cremation, memorial sales and operational issues. Noted the i... Noted Open
4 Feb 2026 Finance Managers Treasurer ReportNoted the projected financial position at Period 9 2025/26 summarised in 4.1 and detailed in Appendix A of the report... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies