What was decided
The Committee noted progress on the 3-year works programme first approved on 5th February 2024 and noted the tendered works and management fee totalling £1,485,875 against a budget of £1,381,490, a projected shortfall of £104,385. Report 7.1
The Committee confirmed that work would be deferred to 2027/8 and agreed to re-profile the 3-year budget to facilitate the works in 2025/6 and 2026/7.
The Committee agreed to move the North Chapel refurbishment back so that wider Cemetery repair to the Burial Chapel, funded by Royal Borough of Greenwich, can complete first.
Why
The 3-year works programme was originally approved on 5th February 2024; design work has been done and a contractor appointed after competitive tender. Report 7.1
The budget for 2026/7 has yet to be agreed, so the Committee could either uplift the budget to cover the increase or re-profile works into the next financial year. Report P7
Sequencing the Burial Chapel repair first allows the Crematorium to keep offering services in that chapel while the North Chapel is refurbished, so users see reduced rather than total loss of provision.
What happens next
Officers will re-profile the 3-year budget to move elements of the work to 2027/8. Report P7
The wider Cemetery repair to the Burial Chapel, funded by Royal Borough of Greenwich, will be completed before the North Chapel refurbishment begins.
The 2026/7 budget will be set in February by the Joint Committee, considering any pay increase, fee income and demand. Report P6
The money
- £1,485,875 Tendered works and fee to manage the works
- £1,381,490 Previously agreed budget allocation for the 3-year works
- £104,385 Projected shortfall against the 3-year budget
Options considered
- Rejected: Approve the 2026/27 works and uplift the budget to cover the increase. Committee instead chose to re-profile so elements move to 2027/8 Report P7
- Chosen: Re-profile the works so elements move to the next financial year. Avoids budget uplift and lets Burial Chapel repair go first Report P7
Implications
- Financial: Report notes an overspend against the previously agreed 3-year property works budget; year-end distribution payments to each borough may vary depending on outturn. Report P7, P8
- Risk: Key risks and mitigations have been considered and are being monitored under the Council's risk management Toolkit. Report P11
- Equalities: Decisions have remote or low relevance to the Equality Act and no apparent equality impact on end users. Report P9
- Climate: Works are primarily maintenance of buildings and infrastructure, with very little or no impact on the Greenwich Carbon Neutral Plan. Report P10
- Legal: Crematoria functions are delegated to the Eltham Crematorium Joint Committee; legal issues arise from the decisions being made. Report P5
- Other: The Joint Committee meeting is open to the public and supports engagement with communities of the three boroughs. Report P12
Who and where
- Users of Eltham Crematorium, who will see reduced service rather than total loss while the North Chapel is refurbished
- Communities served by the three member boroughs: Royal Borough of Greenwich, Dartford and Bexley Report P6, P12
Timeline
- 5th February 2024: Joint Committee approved the 3-year works programme Report 7.1
- 2025/6 and 2026/7: Works to be facilitated under the re-profiled budget
- February of each year: Joint Committee sets the budget, considering pay, fee income and demand Report P6
- 2027/8: Work deferred to this financial year
Plain English for the jargon
- Eltham Crematorium Joint Committee: Joint committee made up of Royal Borough of Greenwich, Dartford and Bexley that oversees the Eltham Crematorium, which is managed by Royal Borough of Greenwich on its behalf.
- Re-profile the budget: Move planned spending between financial years so that the cost of the works is spread across a different timetable.