AI summaryGreenwich Planning Board grants full planning permission for redevelopment of two council owned garage sites in Abbey Wood to provide up to 21 homes, subject to a Section 111 legal agreement and 34 planning conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFull planning permission for up to 21 homes
MoneyNot stated
What happens nextSection 111 legal agreementMust be satisfactorily completed first
Who it affectsAbbey Wood ward, two sitesGarage sites on Sewell Road
What was decided
Full planning permission was granted for the redevelopment of two sites for residential dwellings (Use Class C3) with associated landscaping, parking and storage, because the Council is the landowner of both sites.
The number of dwellings is capped at no more than 21 across the two sites, with each building limited to three storeys and a maximum height of 10 metres (east) or 10.1 metres (west). Report P18, P21, P22
Permission is subject to satisfactory completion of a Section 111 Legal Agreement and the 34 conditions set out in Appendix 2, including energy, contamination, ecology, drainage, transport, and design requirements. Report P9, P33
Why
The application is reported to the Planning Board because the Council is the landowner of both sites, and the development is recommended for approval.
Officers considered the scheme against the National Planning Policy Framework, the London Plan (2021) and the Royal Greenwich Local Plan: Core Strategy with Detailed Policies (2014), as set out in Appendix 3. Report P165, P166, P176
Positive and proactive pre-application discussions took place, which resulted in further information being submitted by the applicant. Report P158
What happens next
A Section 111 Legal Agreement must be completed to the Council's satisfaction before the permission takes effect, with Section 106 confirmatory deeds required for any non-Council freehold, leasehold or financial charge interests. Report P25, P27, P28
The development must begin within three years of the date permission is granted, otherwise it expires, and a range of pre-commencement conditions (contamination, UXO, ecology, energy, construction management) must be discharged first. Report P10, P36, P58, P72, P77, P81, P83, P88, P93
Post-construction, the developer must submit verification reports on contamination and remediation, a 'be seen' energy monitoring submission for five years, and EPCs, with floor levels set no lower than 1.14mAOD for flood mitigation. Report P46, P107, P111, P129
Options considered
Chosen: Grant full planning permission subject to a Section 111 Legal Agreement and conditions. The application is recommended for approval as the Council is the landowner and the scheme meets planning policy requirements Report P158
Implications
Climate: The development must achieve an overall sitewide reduction in regulated CO2 emissions of at least 80% (TBC), equating to 23.7 tonnes of CO2 per year beyond Building Regulations Part L 2021, using a Lean, Clean, Green energy hierarchy including Air Source Heat Pumps and approximately 63 kWp of photovoltaic panels. Report P93, P94
Risk: Contamination remediation, unexploded ordnance risk assessment and mitigation, piling restrictions, and finished floor levels of at least 1.14mAOD are required to address ground, groundwater, flood and UXO risks. Report P36, P45, P56, P58, P129
Equalities: All dwellings must comply with Building Regulation M4(2) 'accessible and adaptable dwellings', with Greenwich Housing Occupational Therapist approval required before occupation, and units retained as such thereafter. Report P142, P144
Legal: The Section 111 Legal Agreement and any Section 106 confirmatory deeds bind the development to planning obligations covering affordable housing and other matters; non-Council interests must be bound before development commences or is occupied. Report P25, P27, P29, P30, P33
Other: An Air Quality Neutral scheme or, where not possible, mitigation measures must be approved, and a 'be seen' energy monitoring plan submitted to the GLA for five years after occupation, alongside a Secured by Design inspection and certificate prior to occupation. Report P70, P81, P107, P111
Who and where
Future residents of the up to 21 new dwellings across the two sites Report P18
Royal Borough of Greenwich as landowner of both sites
Residents and highway users on Sewell Road and Ampleforth Road, Abbey Wood ward Report P115
Protected species, specifically bats, requiring a European Protected Species Mitigation Licence from Natural England Report P77, P78
Timeline
2026-07-21: Planning Board meeting date and decision to grant full planning permission
Three (3) years beginning with the date on which the permission is granted: Development must be begun, otherwise permission expires under Section 91 of the Town and Country Planning Act 1990 Report P10, P11
Prior to the commencement of the development: Pre-commencement conditions must be discharged, including contamination, UXO, landscape and ecological management plan, bat licence, air quality, construction management plan, NRMM, plant noise, tree protection, and the Section 111/Section 106 legal agreement Report P25, P36, P58, P72, P77, P81, P83, P88, P90, P146
Prior to first occupation: Conditions requiring car parking, cycle parking, refuse and recycling, landscape strategy, overheating renters manual, fire strategy, energy monitoring, and finished floor levels must be in place Report P125, P129, P132, P134, P136, P151, P153
Within 2 months of the completion of remediation works: Verification report on contamination remediation must be submitted to the Local Planning Authority Report P46
Within 3 months of occupation or first use: Two-page summary report comparing 'as built' TER to BER/DER figures and relevant EPCs must be submitted to the Council Report P105
Five years following the end of the defects liability period: Annual 'be seen' in-use energy performance data must be reported to the GLA's monitoring portal Report P111
Plain English for the jargon
Use Class C3: Planning use class for dwelling houses, as defined in planning regulations
Section 111 Legal Agreement: An agreement under Section 111 of the Local Government Act 1972 used by local authorities to secure planning-related obligations
Section 106 agreement: A planning obligation under Section 106 of the Town and Country Planning Act 1990, used to bind land to planning obligations
M4(2): Building Regulation requirement for 'accessible and adaptable dwellings'
UXO: Unexploded Ordnance, addressed through risk assessment and mitigation
LEMP: Landscape and Ecological Management Plan
UGF: Urban Greening Factor, a score for the quantity and quality of urban greening provided
NRMM: Non-Road Mobile Machinery, subject to emissions controls on construction sites
Air Quality Neutral: A benchmark from the Mayor of London for development emissions
CLP and CMP: Construction Logistics Plan and Construction Management Plan, covering site operations, traffic, dust and noise
DSP: Delivery and Servicing Plan, setting out how deliveries and servicing are managed
PV: Photovoltaic, meaning solar panels
SCOP: Seasonal Coefficient of Performance, a measure of heat pump efficiency across a year
SAP 10.2: The Government's Standard Assessment Procedure for calculating dwelling energy performance
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Resolved that full planning permission be GRANTED for the redevelopment of 2 sites, comprising residential dwellings (Use Class C3), associated landscaping, parking and storage. Subject to: i The satisfactory completion of a Section 111 (S111) Legal Agreement (obligations set out in Section 26); and ii Conditions set out in Appendix 2 and any addendums.
Word for word from the decision Greenwich published for this meeting.Source: committees.royalgreenwich.gov.uk
The following drawings and associated documentation have been submitted by the applicant in support of application reference 26/0565/F:
Drawings Site location Plan as Existing - SWRD-RMA-ZZ-00-DR-A-0080 P00 East Site Existing Roof Plan - SWRD-RMA-ZZ-00-DR-A-0081 P00 West Site Existing Roof Plan - SWRD-RMA-ZZ-00-DR-A-0082 P00 Site location Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0099 P03 East Site Ground Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0110 P01 East Site First Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0111 P01 East Site Second Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0112 P01 East Site Roof Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0113 P01 West Site Ground Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0114 P01 West Site First Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0115 P01 West Site Second Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0116 P01 West Site Roof Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0117 P01 End of Terrace Floor Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0170 P01 End of Terrace House Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0170 P01 Mid Terrace House Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0171 P01 East Site Elevations as Proposed - SWRD-RMA-A-EZ-DR-A-0200 P03 West Site Elevations as Proposed - SWRD-RMA-A-EZ-DR-A-0201 P03 Sections as Proposed - SWRD-RMA-EW-ZZ-DR-A-0250 P03
Documents Covering Letter Design and Access Statement Accommodation Schedule Affordable Housing Statement Air Quality Assessment Preliminary Ecological Assessment
APPENDICES PAGE NO: 1 APPENDICES
Daylight & Sunlight Assessment Transport Assessment Draft Construction Management Plan Draft Delivering & Servicing Plan Draft Travel Plan Parking Assessment Planning Statement Energy Statement Fire Statement Flood Risk Assessment & Drainage Strategy Report Health Impact Assessment Land Contamination Assessment Noise Impact Assessment Statement of Community Consultation Sustainable Design & Construction Statement Tree Survey Foul Sewage & Utilities Assessment Urban Greening Calculator
APPENDICES PAGE NO: 2 APPENDICES
Appendix 2 – Conditions and Informative(s)
Conditions and Reasons for Application Reference 26/0565/F:
Condition 1 Expiration of Planning Permission The development to which this permission relates must be begun not later than the expiration of three (3) years beginning with the date on which the permission is granted.
Reason: As required by Section 91 of the Town and Country Planning Act 1990.
Condition 2 Approved Drawings The development hereby permitted shall be carried out in accordance with the following approved plans:
Site location Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0099 P03 East Site Ground Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0110 P01 East Site First Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0111 P01 East Site Second Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0112 P01 East Site Roof Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0113 P01 West Site Ground Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0114 P01 West Site First Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0115 P01 West Site Second Floor Site Plan as Proposed - SWRD-RMA-ZZ-00-DR-A- 0116 P01 West Site Roof Plan as Proposed - SWRD-RMA-ZZ-00-DR-A-0117 P01 End of Terrace Floor Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0170 P01 End of Terrace House Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0170 P01 Mid Terrace House Plans as Proposed - SWRD-RMA-ZZ-ZZ-DR-A-0171 P01 East Site Elevations as Proposed - SWRD-RMA-A-EZ-DR-A-0200 P03
APPENDICES PAGE NO: 3 APPENDICES
West Site Elevations as Proposed - SWRD-RMA-A-EZ-DR-A-0201 P03 Sections as Proposed - SWRD-RMA-EW-ZZ-DR-A-0250 P03
Reason: For the avoidance of doubt and in the interests of proper planning.
Condition 3 Quantum of development:
a) Residential Development - The total amount of residential development within Use Class C3 (Dwelling Houses) shall be no more than 21 dwellings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.