What was decided
Full planning permission was granted for the erection of industrial warehouse buildings for flexible uses within Use Classes E(g)(iii), B2 and B8, with ancillary offices, vehicle and cycle parking, landscaping, roof mounted photovoltaic array, fencing, substation, bin stores and associated works.
The permission is subject to 29 conditions set out in Appendix 2, covering construction management, remediation, UXO, drainage, energy, biodiversity, BREEAM Excellent, materials, security, lighting, landscaping, cycle parking, waste, and travel planning. Report P11, P13, P23, P29, P34, P38, P44, P49, P54, P57, P61, P65, P70, P74, P81, P84, P90, P96, P102, P107, P111, P117, P120, P123, P130, P135, P139, P144, P146
The Assistant Director (Planning and Building Control) was authorised to make minor wording changes, finalise the Section 106 agreement, and refuse the application if the S106 is not completed within 3 months.
Why
The application was approved subject to conditions and planning obligations to mitigate transport, highways, employment, training, carbon offset, and low-carbon energy monitoring impacts, in line with London Plan policies SI 2, SI 3 and SI 4, and Royal Greenwich Local Plan policies E1, EA1, EA(c), IM1, IM4 and IM(c).
Conditions require a minimum 100% reduction in regulated CO2 emissions beyond Building Regulations Part L 2021, BREEAM Excellent rating, at least 10% Biodiversity Net Gain, green roofs, and ecological enhancements, addressing climate and ecological policy requirements. Report P74, P83, P90, P120
What happens next
A Section 106 agreement must be completed within 3 months of the resolution (by late December 2026), or the Assistant Director may refuse the application on grounds that the proposals are unacceptable without the planning obligations.
Pre-commencement conditions require submission and approval of documents including a Construction Environmental Management Plan, Construction Logistics and Travel Plan, Site Waste Management Plan, Remediation Strategy, UXO Survey, drainage design, archaeology Written Scheme of Investigation, and a Biodiversity Gain Plan before development begins. Report P23, P29, P34, P38, P44, P57, P61, P65, P81
The development must begin within three years of the date of the permission, in line with Section 91 of the Town and Country Planning Act 1990. Report P11, P12
Options considered
- Chosen: Grant full planning permission subject to conditions and S106 agreement. The application complies with relevant London Plan and Royal Greenwich Local Plan policies, subject to conditions and planning obligations to mitigate impacts.
- Rejected: Refuse the application if the Section 106 agreement is not completed within 3 months. This is a fallback delegated to the Assistant Director, not the Board's primary decision.
Implications
- Climate: The development must achieve at least 100% reduction in regulated CO2 emissions beyond Building Regulations Part L 2021, deliver approximately 311 kWp of PV panels and VRF Air Source Heat Pumps, and achieve a BREEAM Excellent rating. Report P74, P90
- Equalities: Six accessible Blue Badge parking spaces must be provided, with at least one per commercial unit, and reserved exclusively for valid Blue Badge holders. Report P70
- Risk: A detailed UXO risk assessment and intrusive survey is required prior to commencement due to potential WWII bomb risk, and any underground storage tanks discovered must be safely decommissioned. Report P44, P49
- Other: A minimum 10% Biodiversity Net Gain must be delivered and maintained for 30 years, with bird, bat, bee and invertebrate boxes integrated into the buildings and green roofs on entrance canopies. Report P83, P84, P117, P120
- Other: External lighting must be strictly controlled (less than 2700 Kelvin, zero upward light ratio) to avoid light spill onto The Ridgeway SINC and upward reflectance toward HM Prison Thamesmead. Report P107
Who and where
- Future commercial tenants of the warehouse buildings
- Residents and businesses in Thamesmead Moorings ward
- Users of the adjacent local highway network and Boughton Road bus operations Report P29, P31
- The Ridgeway SINC and protected bat corridors (ecological receptors) Report P107, P110
- HM Prison Thamesmead (lighting constraint) Report P107
Timeline
- 2026-09-24: Planning Board resolves to grant full planning permission
- Within 3 months of the resolution: Section 106 agreement must be completed, or the application may be refused
- Within 3 years of the permission: Development must begin (Section 91 Town and Country Planning Act 1990) Report P11, P12
- Within 2 months of completing UXO remediation works: UXO Verification Report must be submitted to the Local Planning Authority Report P46
- Years 1, 3 and 5 following first occupation: Commercial Travel Plan monitoring reports must be submitted Report P141
- 30 years from completion of development: Created and enhanced habitat must be managed and maintained under the Habitat Management and Monitoring Plan Report P88
Plain English for the jargon
- BREEAM Excellent: A sustainability rating for buildings, with 'Excellent' being a high achievement level under the Building Research Establishment Environmental Assessment Method.
- Biodiversity Net Gain: A planning requirement that development delivers a measurable improvement in biodiversity, with a minimum 10% gain here, maintained for 30 years.
- Section 106 agreement: A legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations, such as financial contributions or works, from a developer.
- Use Classes E(g)(iii), B2 and B8: Town planning use classes covering industrial processes (B2), storage and distribution (B8), and light industrial uses (E(g)(iii)).
- SINC: Site of Importance for Nature Conservation, a locally designated wildlife site.
- UXO: Unexploded Ordnance, such as WWII bombs, which can pose a risk during groundworks.