Walnut Tree Bridge Replacement Project: Request for financial and procurement authority for the design and construction work

Approved Executive 2 papers

Executive approved this item on Tuesday 24 November 2015. Below is the council's own wording, with the papers it was decided on.

ItemEX59

Resolved

(1) That the decision taken by the Managing Director, in consultation with the Acting Leader and the Monitoring Officer, under her delegated powers ( Para. 2 of the powers delegated to the Head of Paid Service (Part 3 of the Council’s Constitution)) to transfer a budget of £47,000 from the provisional capital programme to the approved programme for the feasibility study stage of the project, be endorsed. (2) That the Director of Development be authorised to proceed to tender to appoint consultants to undertake the design and construction supervision work required by the project through a recognised procurement framework, to be approved by the Director of Development, in consultation with both the Lead Councillor for Infrastructure and Environment, and the Council’s Procurement Officer. (3) That the transfer of £13,000 from the provisional to the approved capital programme to enable the tendering process to proceed, be approved. (4) That the Director of Development be authorised, in consultation with the Lead Councillor for Infrastructure and Environment, to approve the preferred bridge design as an outcome of the feasibility report and to prepare and submit a business case to the LEP for grant funding. Reasons for In order to deliver a key component of the Guildford Town Centre Transport Package, and ensure that the project is delivered in a timescale that is in-line with the bidding documents approved by the LEP. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the acting Leader or lead councillors and any dispensation granted: None In order to deliver a key component of the Guildford Town Centre Transport Package, and ensure that the project is delivered in a timescale that is in-line with the bidding documents approved by the LEP.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Purpose of report

1.1This report asks for approval to transfer £13,000 from the general fund provisional programme to the approved capital programme. It also requests delegations to the Director of Development, in consultation with the Lead Councillor for Infrastructure and Environment, to enter into a procurement framework to enable to scheme to progress efficiently.

2. Strategic Priorities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 16 (1): Walnut Bridge: App 1: Financial and Procurement AuthorityAppendix 310 KB Download
PDF
Walnut Tree Bridge Replacement Project: Request for financial and procurement authority for the design and construction workReport 418 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
NM
Councillor Nigel ManningVice-Chairperson, present
RB
Councillor Richard BillingtonCommittee Member, present
GD
Councillor Geoff DavisCommittee Member, present
GE
Councillor Graham EllwoodCommittee Member, present
MF
Councillor Matt FurnissCommittee Member, present
MG
Councillor Murray Grubb JnrCommittee Member, absent
IR
Councillor Iseult RocheCommittee Member, present
TR
Councillor Tony RoothCommittee Member, present
PS
Councillor Paul SpoonerCommittee Member, present
DB
Councillor David BilbéCommittee Member, in attendance
AG
Councillor Angela GunningCommittee Member, in attendance
JM
Councillor Julia McShaneCommittee Member, in attendance

All 15 on the meeting page

On this subject at Guildford

Search all
  1. Walnut Tree Bridge Replacement Project: Request for financial and procurement authority for the design and construction workThis decision
  2. 18/P/02226 - Bishops Nissan of Guildford, Walnut Tree Close, Guildford, GU1 1TXApproved
  3. 16/P/00752 - Wey Corner, Walnut Tree Close, Guildford, GU1 4TTAgreed
  4. Acquisition of land at Walnut Tree CloseApproved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies