(1) That the General Fund Capital Estimates, as shown in: (a) Appendices 4 and 5 (current approved and provisional schemes) to the report submitted to the Council, as amended to include the new bids set out in Appendix 1 to that report (b) Appendix 7 to the report (schemes funded from reserves) (c) Appendix 8 to the report (s106 schemes), and (d) Appendix 9 ... view the full minutes text for item CO105
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Council Report Ward(s) affected: All wards Report of the Chief Financial Officer Author: Vicky Worsfold Tel: 01483 444834 Email: [email protected] Lead Councillor responsible: Nigel Manning Tel: 01252 665999 Email: [email protected] Date: 10 February 2016
General Fund Capital Programme (2015-16 to 2020-21) Executive Summary
The report details the position of the current capital programme and the new capital expenditure proposals for the period 2016-17 to 2020-21. Officers have put forward 40 new bids, with a net cost to the Council of £120 million. The Council has a current underlying need to borrow for the general fund capital programme of £144 million, which will increase to £264 million, should these proposals be approved for inclusion in the programme.
The Council has an ambitious Corporate Plan, and in order to achieve the targets within that, we need to invest in capital. Some of the schemes put forward as part of this report supports the corporate plan.
This is a prudent capital programme. Some capital receipts or a revenue stream may arise because of the investment, but in most cases are currently uncertain and it is too early to make assumptions. Some information has been included in the capital vision highlighting the potential income. It is likely there are cash-flow implications of the development schemes, where income will come in after the five-year time horizon and the expenditure will be incurred earlier in the programme.
Capital receipts, grants and contributions, reserves and finally borrowing, will fund all projects. We do not currently know how each scheme will be funded – this budget report shows a high-level position.
Appendices 1 to 3 contain details of the new bids submitted, including the impact of proposed capital expenditure on Council Tax. Appendices 4 to 9 show the position and profiling of the current capital programme (2015-16 to 2019-20). Appendix 10 shows the capital vision schemes. Corporate Management Team (CMT) evaluated each bid (other than a few late bids) using the prioritisation criteria within each bid. Finance Scrutiny Group (FSG) reviewed all the bids.
Officers have requested that a number of bids are approved straight away, without the need for a further Executive report, and these requests were supported by both CMT and the FSG, other than bid PR195 (reference 34) – Woodbridge Road Pavilion Redevelopment, where FSG wanted more information to come to the Executive before the scheme proceeded. The Executive, at its meeting on 19 January 2016, also moved the 2017-18 to 2020-21 element of bid PR304 (reference 19) – Fleet Renewals Programme to the provisional programme.
The key areas of growth included are:
PR303 capital contingency fund PR304 fleet renewals programme PR350 Slyfield Area Regeneration Project PR228 Major Projects Unit
This report also includes the Council’s Minimum Revenue Provision (MRP) policy and some of the Council’s Prudential Indicators. The details are in section 6 and section 7.
At its meeting on 19 January 2016, the Executive endorsed the recommendation below and agreed, subject to the Council approving the budget at this meeting,
(1) That the new capital proposals listed as items 1 to 18 and 20, and the 2016-17 part of item 19 in Appendix 1 be added to the General Fund Capital Programme approved list and the relevant officers be authorised to implement the schemes.
(2) That the new capital proposals listed as items 21 to 30 in Appendix 1 be added to the General Fund Capital Programme approved list, funded by reserves, and the relevant officers be authorised to implement the schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.