(1) That the budget for Concurrent Functions Grant Aid for 2017-18 be set at £106,000, subject to final confirmation at the budget Council meeting in February 2017. (2) That the estimated overspend of £1,073 be funded from the Parish Councils Urgent Schemes reserve. (3) That the parish council requests for grant aid for 2017-18, as set out in Appendix 3 to the report submitted to the Executive, be approved . (4) That the scheme be amended for 2018-19 onwards to require an estimate to be provided for allapplications, rather than just those over £2,000, and that a total scheme limit of £50,000 be set for any individual parish council. (5) That the budget for 2018-19 onwards be reduced to £100,000. Reasons for · To assist parish councils with expenditure on concurrent function schemes in 2017-18. · To enable parish councils to take account of financial assistance from Guildford Borough Council when calculating their precept requirements for 2017-18. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None · To assist parish councils with expenditure on concurrent function schemes in 2017-18. · To enable parish councils to take account of financial assistance from Guildford Borough Council when calculating their precept requirements for 2017-18.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
The Council’s concurrent functions grant aid scheme provides financial assistance to parish councils. Concurrent functions are services which both the Borough Council and the parish councils are empowered to undertake.
The Executive is asked to approve the budget for 2017-18 at this time because the parish councils need to be aware of the level of grant aid available to them so that they can build the sums into their budget calculations for the coming year. They will fix their budgets and precept requirements for 2017-18 in December and early January, enabling this information to be included in the Guildford Borough Council’s final budget approval process in February 2017.
Parishes were asked to complete a detailed application form for each project, provide written estimates for projects costing over £2,000 and identify how the project meets at least one of the five fundamental themes within the Council’s corporate plan. We originally received 53 requests from 18 of the 23 active parish councils. A panel of officers have evaluated the bids. The panel referred any queries raised back to the parish council concerned and obtained satisfactory responses in all cases. Officers suggest that three schemes be rejected, as they do not meet the scheme criteria. After an initial review, a further bid has been rejected, and another four have been either deferred, or alternatively funded. The remaining bids total £107,073, which is £1,073 over the base budget of £106,000.
Recommendation to Executive
(1) That the budget for Concurrent Functions Grant Aid for 2017-18 be set at £106,000, subject to final confirmation at the budget Council meeting in February 2017. (2) That the estimated overspend of £1,073 be funded from the Parish Councils Urgent Schemes reserve.
(3) That the parish council requests for grant aid for 2017-18, as set out in Appendix 3 to this report, be approved.
(4) That the scheme be amended for 2018-19 onwards to require an estimate to be provided for all applications, rather than just those over £2,000, and that a total scheme limit of £50,000 be set for any individual parish council.
(5) That the budget for 2018-19 onwards be reduced to £100,000.
Reasons for Recommendation: To assist parish councils with expenditure on concurrent function schemes in 2017-18. To enable parish councils to take account of financial assistance from Guildford Borough Council when calculating their precept requirements for 2017-18.
Purpose of report
1.1This report gives details of the applications from parish councils for financial assistance through the concurrent functions grant aid scheme in 2017-18. The parish councils will include all grants recommended for approval in their precept calculations for the 2017-18 financial year.
2. Strategic Priorities
2.1As part of the bidding process, we asked parishes to indicate how their project(s) meet one of the five fundamental themes within the Council’s corporate plan. In all cases, the projects meet at least one of the five themes.
Background
3.1The Council’s concurrent functions grant aid scheme provides financial assistance to parish councils. Concurrent functions are services which both the Borough Council and the parish councils are empowered to undertake. The policy relating to the operation of the scheme was last updated in 2016-17 and is summarised in Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.