The Self-build and Custom Housebuilding Act 2015: Proposed delegated powers

Approved Executive 1 paper

Executive approved this item on Tuesday 3 January 2017. Below is the council's own wording, with the papers it was decided on.

ItemEX60

Resolved

(1) That the Director of Planning and Regeneration be authorised to carry out the obligations set out in Appendix 1 to this report to keep and publicise a register of individuals and associations who are seeking to acquire serviced plots of land in the Council’s administrative area to build houses for those individuals to occupy as homes and to determine applications for entry on to the register and removal therefrom. (2) That the steps taken by officers to set up and publicise a register and arrangements for the determination of applications seeking entry on to the Register which have already been carried out by Planning Policy Officers since 1 April 2016 be approved. (3) That, subject to paragraph (4) below, the introduction of a set of additional eligibility criteria for entry on the Register which shall consist of the ‘long and substantial’ local connections test and financial viability assessment be approved. (4) That the Director of Planning and Regeneration be authorised to review and amend such criteria periodically, and to carry out an immediate review to clarify the definition of ‘long and substantial local connection’. (5) That the setting of fees for entry on to, and remaining on the register, as outlined in this report be approved and that such fees be reviewed annually by Council as part of the budget setting process. Reasons for · Officers have been determining applications for entry on to the Council’s Self-build and Custom Housebuilding Register since its initiation in April 2016. Due to the simplicity of determining applications, frequency at which they are received and requirement to respond to applicants within 28 days, it is considered more appropriate for applications to be determined at officer level. · The introduction of a local connections test and financial viability assessment as additional eligibility criteria will enable the Council to identify applicants who have a long-standing and substantial connection to the area and are able to purchase land for a self-build project. The Council will only be required to provide suitable development permission to such applicants. · Charging an initial entry fee and an annual fee to remain on the register will enable the Council to recover the costs incurred from maintaining the register, processing applications and handling disputes. Alternative options considered and rejected by the Executive: The Executive to retain responsibility for determining all future applications under the Act. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None · Officers have been determining applications for entry on to the Council’s ... view the full minutes text for item EX60
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

The Self-build and Custom Housebuilding Act 2015 (‘the 2015 Act’) requires Relevant Authorities (which as currently defined includes Guildford Borough Council):

 to establish and publicise a register of persons seeking to acquire land to build or commission their own home,  to determine applications for entry onto and removal from the register, and  to have regard to that register when carrying out their planning, regeneration, housing and land disposal functions.

To meet these requirements, Planning Policy Officers set up a Self-build and Custom Housebuilding Register on behalf of the Council in April 2016 and have been determining applications for entry onto the register since.

The Self-build and Custom Housebuilding (Register) Regulations 2016 (‘the 2016 Regulations’), which were introduced on 1 April 2016, detailed the eligibility criteria for applicants in terms of their required nationality, age and interest in acquiring a self-build plot. However, these regulations were updated in October 2016 and now enable Relevant Authorities

 to introduce additional eligibility criteria in the form of a local connections test and financial viability assessment, and  to charge applicants for entry on to, and for remaining on, the Register.

The obligations placed upon the Council under the 2015 Act and the 2016 Regulations made thereunder are Executive functions. However, given the simplicity of determining applications under current and proposed eligibility criteria, the frequency at which applications have been received and the requirement to respond to applicants within 28 days of receipt of an application, it is proposed that the Executive functions described above are delegated to officers.

Recommendations to Executive

(1) That the Director of Planning and Regeneration be authorised to carry out the obligations set out in Appendix 1 to this report to keep and publicise a register of individuals and associations who are seeking to acquire serviced plots of land in the Council’s administrative area to build houses for those individuals to occupy as homes and to determine applications for entry on to the register and removal therefrom.

(2) That the steps taken by officers to set up and publicise a register and arrangements for the determination of applications seeking entry on to the Register which have already been carried out by Planning Policy Officers since 1 April 2016 be approved.

(3) That the introduction of a set of additional eligibility criteria for entry on the Register which shall consist of the ‘long and substantial’ local connections test and financial viability assessment be approved and that the Director of Planning and Regeneration be authorised to review and amend such criteria periodically.

(4) That the setting of fees for entry on to, and remaining on the register, as outlined in this report be approved and that such fees be reviewed annually by Council as part of the budget setting process.

Reasons for Recommendation:  Officers have been determining applications for entry on to the Council’s Self-build and Custom Housebuilding Register since its initiation in April 2016. Due to the simplicity of determining applications, frequency at which they are received and requirement to respond to applicants within 28 days, it is considered more appropriate for applications to be determined at officer level.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Self-build and Custom Housebuilding Act 2015: Proposed delegated powersReport 188 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 28 attended
PS
Councillor Paul SpoonerChairperson, present
MF
Councillor Matt FurnissVice-Chairperson, present
DB
Councillor David BilbéCommittee Member, present
RB
Councillor Richard BillingtonCommittee Member, present
GD
Councillor Geoff DavisCommittee Member, present
GE
Councillor Graham EllwoodCommittee Member, present
MI
Councillor Michael IllmanCommittee Member, present
NN
Councillor Nikki Nelson-SmithCommittee Member, present
IR
Councillor Iseult RocheCommittee Member, present
TR
Councillor Tony RoothCommittee Member, present
JA
John ArmstrongSecretary, expected
SB
Sophie ButcherSecretary, expected

All 28 on the meeting page

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open