Executive, Tuesday 19 June 2018 at 7.00pm

Clay Lane Link Road Phase 1 - Internal Estate Road

Approved Executive 1 paper

Executive approved this item on Tuesday 19 June 2018. Below is the council's own wording, with the papers it was decided on.

ItemEX16

Resolved

(1) That the sum of £10.439 million be transferred from the Provisional to the Approved Capital Programme to enable the continuation and completion of the detailed design and construction of phase 1 of the Clay Lane Link Road: the Internal Estate Road in 2018-19 and 2019-20, as detailed in the report submitted to the Executive. (2) That the Lead Councillor for Infrastructure and Governance be authorised to determine which of the construction options described in paragraph 3.15 of the report should be implemented for the Internal Estate Road once discussions with Surrey County Council have progressed and resolved. Reason: To complete the construction of the Internal Estate Road . Alternative options considered and rejected by the Executive: ‘Do nothing’ in which case the project would cease and the internal estate road would not be constructed. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The purpose of this report is to provide the Executive with an update of the work carried out so far in delivering Phase 1 of the Clay Lane Link Road, hereafter known as the Internal Estate Road, and to seek approval of the recommendations within this report. 2. Strategic Priorities

2.1The recommendations support the delivery of the following priorities from the Corporate Plan 2015-2020:

 Work effectively with partners to drive development and business growth that will expand our economy.

 To grow a sustainable economy that will support all aspects of life in our borough.

 Work with partners to bring forward a delivery plan for Clay Lane Link Road and other important infrastructure necessary to unlock the wider Slyfield.

Background

3.1The proposed scheme is phase 1 of the two phase Clay Lane Link Road project. It will provide a new estate road needed to develop expansion sites within the Slyfield industrial Estate and facilitate the delivery of the Slyfield Area Regeneration Programme (SARP) which are allocated within the Guildford Borough Council saved Local Plan (2003) and the Surrey County Council Waste Plan (2008).

3.2The proposed new road will be located within the eastern confines of the Slyfield Industrial Estate, which lies 2.5km north of Guildford Town Centre. Slyfield is the town’s largest industrial and commercial park. Access to the estate is via Woking Road, which connects Guildford to Woking.

3.3The current scheme will extend Westfield Road and Moorfield Road to the east, provide significant improvements and realignment to the existing mini roundabout at Moorfield Road, together with the construction of two new roundabouts.

3.4The land on which majority of the road will be constructed is part of a former landfill site. A small section of the road goes through the edge of the old sludge lagoons, which are on land owned by Thames Water. Thames Water have agreed to transfer the land to Guildford Borough Council at a peppercorn rate to facilitate the building of the road.

3.5Surrey County Council have agreed a pavement design in principle. Detailed design and the construction estimate will be based on this design with the intent that Surrey County Council formally adopts the road after construction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Clay Lane Link Road Phase 1: Internal Estate RoadReport 328 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
PS
Councillor Paul SpoonerChairperson, present
MF
Councillor Matt FurnissVice-Chairperson, present
DB
Councillor David BilbéCommittee Member, present
PB
Councillor Philip BrookerCommittee Member, present
GD
Councillor Geoff DavisCommittee Member, apologies
GE
Councillor Graham EllwoodCommittee Member, apologies
GJ
Councillor Gordon JacksonCommittee Member, present
NM
Councillor Nigel ManningCommittee Member, present
NN
Councillor Nikki Nelson-SmithCommittee Member, present
IR
Councillor Iseult RocheCommittee Member, present
AC
Councillor Adrian ChandlerGuest, in attendance
JR
Councillor Jo RandallDeputy Leader of the Council, in attendance

All 14 on the meeting page

On this subject at Guildford

Search all
  1. Clay Lane Link Road Phase 1 - Internal Estate RoadThis decision
  2. 17/P/02593 - Chambers House, Clay Lane, Jacobs Well, Guildford, GU4 7NAApproved
  3. 17/P/01613 - Burpham Court Farm, Clay Lane, Jacobs Well, Guildford, GU4 7NAApproved
  4. 16/P/00064 - Tynley, Clay Lane, Jacobs Well, Guildford, GU4 7PFApproved
  5. Clay Lane Link Road - Planning ApplicationRefused

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies