Resolved
(1) That the sum of £3.93 million required for the Hotspots project (ref. P16( p)) , that is currently on the p rovisional capital programme, be moved to the approved capital programme. (2) That the sum of £1.033 million required for the Town Centre Approaches project (ref. P14( p)) , that is currently on the p rovisional capital programme, be moved to the approved capital programme. Reasons: · To complete the project in line with the government’s timescales for the third iteration of its growth deal funding. · To enable the continuation and completion of the detailed design and implementation of the works from 2018-19 to 2020-21 Alternative options considered and rejected by the Executive: To return funding to the LEP and not progress with the projects. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None