Resolved
(1) T hat the Director of Planning and Regeneration, in consultation with the Lead Councillor for Infrastructure and Governance, be authorised to progress the Bedford Wharf – Plaza Landscaping scheme to design and consultation. (2) That the sum of £500,000 be vired from scheme PF7(p) Transport Scheme to a new Capital Scheme on the provisional programme. (3) That the sum of £150,000 be transferred from the provisional to the approved capital programme Bedford Wharf – Plaza Landscaping Project for the purpose of carrying out the design and consultation. Reason: To complete the Plaza Landscaping design and consultation in relation to the delivery of the Walnut Bridge replacement project and to enhance the wider Bedford Wharf area. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None