That the Executive: (1) endorses the findings of the previously-completed GRIP 2 (Feasibility) study; (2) approves progression of the project to GRIP 3 (Option Selection); (3) authorises the Director of Planning and Regeneration: (a) to take all necessary steps in accordance with the Council’s Procurement Procedure Rules to procure services and enter into a contract with the preferred supplier, in order to deliver GRIP 3; and (b) to establish a new Project Board (4) approves the transfer of £500,000 from the provisional capital budget of £5.2 million for this project to the approved programme, ready to commence works on GRIP 4 once the GRIP 3 work has been formally signed-off. Reason: To progress works necessary for the future delivery of the Guildford West Rail Station at Park Barn. Alternative options considered and rejected by the Executive: · To do nothing (‘Option 0’) · Low cost bus service enhancement (‘Option 3’) Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: Onslow Report of Director of Planning and Regeneration Author: Elizabeth Fleming Tel: 01483 444038 Email: [email protected] Lead Councillor responsible: Caroline Reeves Tel: [phone removed] Email: [email protected] Date: 16 July 2019
Guildford West Rail Station Executive Summary
The Guildford West Rail Station is a proposed new station located in the west of Guildford that will help relieve congestion and parking to the west of the town by providing a genuine alternative to the private motor car. It will encourage modal shift and support the proposed expansion of the area, which includes the Royal Surrey County Hospital, University of Surrey and Guildford Research Park, in addition to a large residential population. Other benefits include an interface with, and complementing, Phase 1 of the Council’s Sustainable Movement Corridor (SMC), helping to sustain important local institutions and further support their expansion by increasing the catchment area from which the staff and students attending and resourcing these institutions are drawn. This station would also enable increased economic development without the associated traffic congestion and high demand for parking and would also improve productivity and support inward investment helping to retain key employers in the area.
The viability of a new railway station on the national network, its size, location, accessibility, impact on existing services and initial views on constructability, was investigated under Stage 2 (Feasibility) of Network Rail’s Governance for Railway Investment Projects (GRIP) Process. GRIP is an eight-stage process that sees the concept of a major investment project – in this case a new two-platform railway station - from feasibility, option identification, option selection and subsequent single option development through to detailed design, construction and commissioning of a completed station.
While the GRIP process helps to eliminate non-viable options and provides costs for preferred option construction and commissioning, it does not identify how a project would be funded. Those invested in the process would undertake this in parallel.
In this case, as the Council has identified the requirement for a new station based on many factors including the envisaged local benefits it will deliver, it is the Council’s responsibility to source funding by exploring potential contributions from developers and other stakeholders such as Network Rail, the University of Surrey, Surrey County Council, the EM3 LEP, etc. The extent of funding required will become clearer as the Council moves through the necessary GRIP stages. The next stage (GRIP 3 – Option Selection) will allow the Council to review the options put forward in the GRIP 2 Feasibility Report in more detail. It will identify any unforeseen issues e.g. topography, bearing capacity etc. that could eliminate a GRIP 2 option from coming forward.
An allocation had been identified in the Local Plan for the proposed new station - it is one of the two options put forward under GRIP 2 for consideration. It is anticipated that the work undertaken under GRIP 3 will confirm its viability and identification as the preferred location, but this cannot be assumed at the current time until the full option appraisal has been completed.
There will be some land requirements for the options to be considered in GRIP 3 and this may influence the final option selection. Discussions have already been initiated with Network Rail, Great Western Railway (GWR), South Western Railway (SWR) Royal Surrey County Hospital and University of Surrey in this respect.
Matters such as station design, access, and the necessary amount, type and location of car parking required to support a new station here will be considered in more detail at the appropriate time under GRIP Stages 3 and 4.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.