To note that the Managing Director, in consultation with the Leader and the Monitoring Officer, used his urgent decision powers on 26 March 2021 to approve the grant of a 99 year lease at a peppercorn to UKPN in respect of a small plot of land at the Midleton Industrial Estate, Guildford. Reason(s): The approval of the new lease to UKPN provided a power supply and allowed the development to continue on schedule ensuring that there were no increased development costs caused by the delayed installation of the sub-station. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the lead or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
RECORD OF EXECUTIVE DECISION TAKEN BY AN OFFICER UNDER DELEGATED AUTHORITY SUBJECT: Urgent decision on the Grant of Protected Lease of Land at Midleton Industrial Estate to UKPN for a sub-station.
KEY DECISION* Yes/No No
Ward(s) affected: Onslow
NAME AND DESIGNATION OF James Whiteman OFFICER TAKING DECISION: Managing Director
SOURCE OF AUTHORITY TO TAKE Council’s 05/01/2021 Constitution Part 3, Page 3-44, Para DECISION: 2, the Managing Director Either: Executive Decision (please include date of meeting) “In consultation with the Leader where practicable and the Or: Scheme of Delegation to Monitoring Officer, to act in an emergency or in relation to Officers matters of urgency in relation to any functions of the Council, subject to the use of this power being reported to the next meeting of the Council, Executive or committee concerned”.
CONSULTATIONS: (a) Relevant Lead Councillor(s): (a) Leader – Joss Bigmore – Email 25/03/2021 at Comments: 15:37 agrees with proposal with no further comments being made. (b) Local Ward Councillor(s): (b) Cllrs Jon Askew, David Goodwin and Will Salmon Comments**: – informed of decision on 25/03/2021.
(c) Officers (state names): (c) Monitoring Officer – Diane Owens – Email 25/03/2021 at 14:57 agrees with proposal with no Comments: further comments being made.
To accept terms for the grant of a new lease of land at DETAILS OF DECISION: Midleton Industrial Estate for UKPN to install an electricity (attach additional sheets if required) sub-station at the request of the Council (i.e. not the utility company).
A new lease of land at the Midleton Industrial Estate is to be granted to UKPN to allow them to install and maintain a substation on behalf of the Council, which is required for the Council’s new redevelopment. The substation has been requested and its’ installation paid for by the Council at a cost of £132,000 and the supply will be only for the benefit of the Council’s development and the industrial units that are being constructed. Lease terms: - Lease length = 99 years - Rent = Peppercorn - Right of access from the substation site to the nearest public highway. - UKPN shall provide reasonable prior notice of its intentions to carry out works, except in case of emergency, and shall cause no unnecessary damage or disturbance in exercise of the rights and make good any damage that may be caused to your reasonable satisfaction.
The whole redevelopment hinges on having the additional power supply from the substation
Urgent approval is sought for this decision for two major reasons:
1) By virtue of s123 of the Local Government Act 1972, the Council is empowered to dispose of land provided it obtains the best consideration reasonably obtainable. In this case, UKPN will not enter into a lease for a rental or premium. The Council as landlord is installing the substation for its own use and the terms of the lease will restrict the use only as a substation. It could be argued that this agreement has nil value. However, by virtue of the fact that UKPN is renting the land, it does stand to reason that the 99 year lease has some value. Therefore, the lease is considered to fall within the requirement for approval by the Executive to be granted at less than best consideration and falls outside of any delegated powers to officers.
2) However, there is an immediate need to agree terms for the substation asap as UKPN has a 34 week lead in time for and will only progress the installation once the lease has been signed. Every week that we delay the signing of the lease this has a knock-on effect on the development programme and in turn will lead to rising development costs
Therefore, to expedite the matter, the Managing Director is requested to approve this using his powers to act in an emergency or in relation to matters of urgency, with his decision being reported to the next meeting of the Executive (20 April 2021).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.