That consideration of this matter be deferred to the next meeting of the Executive to be held on 24 August 2021. Reason for Recommendation: To enable the matter to be considered by the Strategy and Resources EAB on 9 August 2021. Other options considered and rejected by the Executive: To consider the matter at this meeting. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: All Wards Report of Director of Strategic Services Author: Martin Knowles Email: [email protected] Lead Councillor responsible: John Rigg Tel: [phone removed] Email: [email protected] Date: 20 July 2021
Priority List of Highway and Transport Schemes Critical to Local Plan Delivery Executive Summary
Corporate Programmes Team has highlighted five highway and transport schemes that are likely to be critical priorities to the Local Plan maintaining its housing trajectory and continuing to be up to date. They have been named ‘priority schemes’ and are in no particular order in this report.
On 11 March 2020 the government published the Road Investment Strategy 2 (RIS2). These are prepared every five years and the latest strategy deals with funding for the period 2020- 2025 but also mandates Highways England to investigate schemes that could be funded in the period 2025-2030 (RIS3).
The RIS2 does not now include an A3 Guildford scheme but does include a requirement to develop a scheme for the RIS3 pipeline known as A3/A247 Ripley south. The details of this improvement have not been formulated by Highways England and officers assume that this scheme relates in part to potential new north facing slips at the A3/A247 junction at Burnt Common.
As the A3 through Guildford scheme no longer forms part of the Government’s Road Strategy Local Plan Policy ID2(2) requires the Council to review its transport evidence base to investigate the consequent cumulative impacts of approved developments and Local Plan growth including site allocations on the safe operation and the performance of the Local Road Networks and the Strategic Road Network. The final sentence of the Policy is important in that it states that “The outcome of this review will determine whether development can continue to be completed in accordance with the Local Plan trajectory or will determine whether there needs to be a review of the Local Plan.”
The highway and transport Schemes that are likely to be critical to the Local Plan (in no particular order) are as follows:
• SRN2 – M25 Junction 10/A3 Wisley Interchange ‘Road Investment Strategy’ scheme • NR2 and NR3 New rail stations at Guildford West (Park Barn) and Guildford East (Merrow) • SMC 1-6 - Sustainable Movement Corridor • SRN7 and SRN8 - A3 northbound on and off slip roads at A247 Clandon Road (Burnt Common) • LRN19 – New road bridge and footbridge scheme to enable level crossing closure on A323 Guildford Road adjacent to Ash railway station
The Report sets out a commentary as to why we consider these schemes to be important. We have also highlighted some of the difficulties that the schemes may create in terms of wider issues that would need resolving as part of their future delivery. Some of the schemes have funding from various sources whilst other schemes have no funding.
We have also provided commentary on the highway and transport schemes that are likely to be delivered by the developers of the Strategic Sites.
We have had a meeting with Surrey County Council to discuss the priorities which they were very receptive to and supportive of and they are looking to align them with their own priorities moving forward.
We have not gone into any detail regarding the Guildford Economic Regeneration Project (GERP) in this report, but we note that there may be significant infrastructure requirements to achieve the transformational change that that Project is proposing.
The Executive is asked to approve the highway and transport infrastructure schemes set out in the Report that are considered to be priorities and therefore critical to Local Plan delivery as currently envisaged. Should the Local Plan be reviewed or amended, the list of schemes may also require amendment accordingly.
Recommendation to Executive
That the Executive approves the priority list of highway and transport schemes likely to be critical to Local Plan delivery as described in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.