(1) That the findings of the two SOLACE reports, attached as Appendices 1 and 2 to the report submitted to the Council be noted and endorsed. (2) That the Improvement Plan, including the Housing sub-plan, attached at Appendices 3 and 4 to the report submitted to the Council be endorsed and adopted. (3) That the Council notes that the Improvement Plan (Appendix 3), along with the Housing sub-plan (Appendix 4), has addressed each and every recommendation and finding from the two SOLACE reports and, in some areas, has gone further. (4) That the Council agrees that the intention of the delivery of the Plan is to enable Councillors to have confidence that we are delivering best value for Guildford’s residents and businesses. (5) That the Council notes that the Chief Executive and Corporate Management Board will be accountable for the delivery of the plan. (6) That updates be received by full Council on the delivery of the Improvement Plan, and progress on addressing the recommendations, every six months for three years. (7) That, in line with the recommendations from SOLACE, an Independent Assurance Panel be appointed ... view the full minutes text for item CO27
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Guildford Borough Council Report to: Full Council Date: 23 July 2024 Ward(s) affected: All Report of: Chief Executive Author: Pedro Wrobel, Chief Executive Email: [email protected] Lead Councillor responsible: Julia McShane Tel: 01483 837736 Email: [email protected] Report Status: Open
Corporate Improvement Plan 1. Executive Summary 1.1 On 3 January 2024, SOLACE was commissioned by the former Chief Executive and other statutory officers to undertake an Independent Governance Review of Guildford Borough Council (GBC). The scope of the review was deliberately wide, to encompass the entirety of the Council’s business, structure, processes, systems and culture.
1.2Alongside this report, SOLACE was also commissioned to look specifically at Guildford’s housing landlord function.
1.3The main finding of the reports is that the Council is at serious risk of failing in its statutory duty to deliver Best Value. The recommendations of both reports are designed to assist the Council to avoid such a failure, and to address the issues identified.
1.4The reports recognise the efforts that are already underway to improve the Council’s operation, and recommends the Council develops a comprehensive Improvement Plan encompassing all of the recommendations within the reports.
1.5The SOLACE reviews recommend that the progress of the Improvement Plan should be reported to the Council at six monthly intervals for three years.
1.6The Corporate Governance and Standards Committee also considered this report at its special meeting held on 15 May 2024. A copy of the relevant minute of that meeting, including the many comments made by councillors is attached as Appendix 5. We have provided updates to the Improvement Plan and Housing Improvement sub-plan (Appendices 3 and 4) that have happened since May.
2. Recommendation to Council The Council is asked to:
2.1Note and endorse the findings of the two SOLACE reports, attached as Appendices 1 and 2 to this report.
2.2Endorse and adopt the Improvement Plan, including the Housing sub- plan, attached at Appendices 3 and 4.
2.3Note that the Improvement Plan (Appendix 3), along with the Housing sub-plan (Appendix 4), addresses each and every recommendation and finding from the two SOLACE reports and, in some areas, goes further.
2.4Agree that the intention of the delivery of the Plan is to enable Councillors to have confidence that we are delivering best value for Guildford’s residents and businesses.
2.5Note that the Chief Executive and Corporate Management Board will be accountable for the delivery of the plan.
2.6Agree to receive updates on the delivery of the Improvement Plan, and progress on addressing the recommendations, every six months for three years. 2.7 Agree, in line with the recommendations from SOLACE, to the appointment of an Independent Assurance Panel to provide an independent “critical friend” challenge to the Council.
2.8Agree to that panel being appointed by the Chief Executive, noting that it will include two lead members of the SOLACE review team (Andrew Flockhart and Chris Buss) and that having carried out the review, these experts have a detailed understanding of the issues facing GBC, and are well-placed to advise the Council on whether the actions being taken address the concerns identified.
2.9Note that the panel itself will also provide an independent view to the Council, on a six-monthly basis, about the progress of improvements, and that these reports will be made public.
3. Reasons for Recommendations and purpose of report 3.1 To ensure the Council is aware of, and has had the opportunity to endorse, the findings and recommendations of both SOLACE reviews.
3.2To advise the Council of the steps that have already been taken by the Chief Executive, Corporate Management Board and other colleagues to respond to those findings and recommendations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.