(1) That capital expenditure of £1,133,500 be approved from existing development contributions to improve SANG capacity and improvement of the SANG access infrastructure at Riverside Nature Reserve and Parsonage Water Meadows. (2) That an additional staff resource of one Project Manager Post for project delivery be approved. Reasons: · Officers consider the project proposal the most efficient option to maintain SANG capacity to mitigate the recreational pressure resulting from the developments the SANG contributions have been collected from. · The project will deliver necessary works to achieve health and safety compliance under the Occupiers Liability Act 1957. · The delivery of the project will provide added benefits to the Council by demonstrating compliance with the ... view the full minutes text for item CO35
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Guildford Borough Council Report to: Council Date: 23 July 2024 Ward(s) affected: Bellfields and Slyfield, Burpham Report of Director: Julian Higson, Interim Strategic Director Housing & Environment Author: Hendryk Jurk, Parks Development Lead Tel: 01483 444768 Email: [email protected] Lead Councillor responsible: George Potter, Lead Councillor for Environment and Climate Change Tel: [phone removed] Email: [email protected] Report Status: Open
Riverside - Nature Reserve SANG improvement 1. Executive Summary 1.1 This report seeks approval to carry out a capital project for replacement and improvement of the access infrastructure at Riverside Nature Reserve and Parsonage Water Meadows, and to create additional staff resource of one Project Manager Post for project delivery.
1.2Riverside Nature Reserve is a designated Suitable Alternative Natural Greenspace (SANG) to avoid increased recreational pressure on the Thames Basin Heaths Special Protection Area (SPA) resulting from new housing development. 1.3 This mitigation is required for the Council to comply with the Conservation of Habitats and Species Regulations 2010 by providing alternative recreation areas that provide a similar experience to the SPA.
1.4The estimated project cost of £1,133,500 will be funded from financial contributions from developers that are collected to deliver new SANG sites, improve existing SANG land, provide infrastructure and site maintenance and cover staff costs associated with management. The project will include access and site improvement to the SANG to enable additional use of the site.
1.5The report outlines the need for the project to improve existing infrastructure and facilitate increased visitor numbers. These pressures provide a challenge managing visitor conflicts, safe access to natural green space, naturally occurring changes, whilst retaining the site’s natural character in line with SANG guidelines, GBC Countryside Vision, and the Environment Act 2021.
1.6The existing boardwalk on Riverside Nature Reserve is a key piece of SANG infrastructure that requires replacement as a matter of urgency. Parts of the existing boardwalk are currently closed for Health & Safety reasons.
1.7Officers also seek to improve access for firefighting equipment to mitigate increased wildfire risks.
1.8Proposed works comprise of re-designing and replacing the existing boardwalk and improving pathways, signage, and seating, following recommendations from an access audit commissioned in 2020. Officers propose to include public consultation during the project.
1.9The project aims to ensure that the Council fulfils its duties under the Occupiers Liability Act 1957, the Equality Act 2010, and the Environment Act 2021.
1.10Officers recommend that the Council approves the capital expenditure and to create additional staff resource for project delivery. 1.11 This matter was also considered by the Executive at its meeting on 12 June 2024. The Executive endorsed the recommendation below.
2. Recommendation to Council 2.1. That capital expenditure of £1,133,500 be approved from existing development contributions to improve SANG capacity and improvement of the SANG access infrastructure at Riverside Nature Reserve and Parsonage Water Meadows.
2.2That an additional staff resource of one Project Manager Post for project delivery be approved.
3. Reasons for Recommendation: 3.1. Officers consider the project proposal the most efficient option to maintain SANG capacity to mitigate the recreational pressure resulting from the developments the SANG contributions have been collected from.
3.2The project will deliver necessary works to achieve health and safety compliance under the Occupiers Liability Act 1957.
3.3The delivery of the project will provide added benefits to the Council by demonstrating compliance with the public duties for biodiversity under the Environment Act 2021 and the duties under the Equality Act 2010.
4. Exemption from publication 4.1. No
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.