Approved the membership and terms of reference for the Executive working groups recommended to continue as set out in the appendices to the report; 2. Agreed to dissolve the Financial Recovery Executive Working Group and the HRA Housing Management HRA Board; and, 3. Established the Housing Operations Board and approve its terms of reference and membership. Reason(s): To assist the Executive to select or set up appropriate, properly resourced groups to provide support or undertake work on its behalf. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Strategic Programmes & Projects Delivery Boards Terms of Reference
Purpose The purpose of the four Delivery Boards, listed below, is to provide a robust governance and scrutiny model for the relevant Executive Councillors, and invited Board Members, to provide direction, comment, check and challenge on issues that require Member input with a focus on emerging risks, issues and problems relating the Council’s major projects. The Boards will report into the Executive Strategic Programmes and Projects Board (SPPB).
The four Delivery Boards are: • Capital, Transport and Infrastructure Delivery Board • Housing Delivery Board • Shaping Guildford’s Future Delivery Board • Weyside Urban Village Delivery Board
Membership Boards will be chaired by the Lead Member for Regeneration who will report to the SPPB quarterly.
• Other relevant Lead Members will be invited onto relevant Deliver Boards – eg: Housing. • Finance Lead Member will be invited onto all Delivery Boards. • Membership will be cross party and involve wider group of Members beyond Executive. • Up to four other Councillors as selected by the Lead Member for Regeneration. • Where appropriate, invitations can be extended to other Councillors, officers or external parties.
Supporting officers:
1 v.1 July 2023
• Strategic Director – Place. • Executive Head of Regeneration and Planning Policy. • Relevant programme/project officers and consultants.
Role • The Delivery Board meetings will be held three times a year. • Key business will be: o To review last four months and status of risk/issues/problems/progress raised. o Look forward four months with focus on emerging risks/issues/progress milestones/constraints and interdependencies. o Agendas to focus on the above and budget issues that require direction/input rather than general project updates. • The Boards will escalate risks/issues to SPPB where appropriate. • Reporting will be by exception on an action log. • Deep dives will be conducted into individual projects periodically. • Change management governance will be in place. • Frequency three times per annum but with additional meetings where an urgent issue requires Member consultation. • Councillors will be expected to give their expert opinions to guide key decisions. • Councillors are also expected to convey information back from the meetings to their groups. • Executive Lead Members will be asked to comment on any key interfaces and dependencies that may exist between their service areas and the projects, work streams or capital programmes. Officers will:
• Administer the meetings. • Provide written updates on the programme and projects to the Boards, including a dashboard covering programme, risks and budget.
2 v.1 July 2023
• Maintain an action log.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.