Procurement of contract for provision of Servicing Domestic Boilers (West Area)

Refused Executive 1 paper

Executive refused this item on Thursday 28 November 2024. Below is the council's own wording, with the papers it was decided on.

ItemEX70

Resolved

Authorise the entering into of a new contract with K&T Heating Services Limited under Fusion 21 Framework (Fusion21 Heating, Renewables, and Electrical Framework- Lot 1 Domestic Heating [Combustibles]) for the servicing of domestic boilers with a financial cap of £1.3 million pounds for a term of 1 year. Reason(s): 1. The Council is preparing a tender for a longer-term contract which is envisaged to be awarded in 12 months period. It is imperative that whilst the council is preparing for a long-term contract, the regulatory service of Domestic Boiler Servicing is provided continuously. Any new contractor will need a 3-month mobilisation period and considering that new long-term contract will be ready for execution in 12 months’ time, continuity of the incumbent supplier becomes imperative. 2. Additionally, the costs for demobilisation of current contractor and cost of system integration and mobilisation of new contract for a short period would outweigh any benefit from bringing in any potential new supplier. 3. Value for money is demonstrated by continuity of the service noting that we have continuity of service, and K&T are the no.1 ranked supplier on the Fusion 21 framework. There is an approximate saving of 10% on existing fees by using this framework. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Background

6.1The council is in the process of preparing tender to award a long- term contract for Domestic Boiler Servicing. The long term contract will take about 12 months to conclude whilst the current regulatory service Domestic Boiler Servicing still needs to be undertaken. SS / J-SCS-065 / 00945327 / Version : Page 2 6.2 Currently the Borough is geographically split into East region managed by supplier TSG and West region managed by K&T. The current contract for East region of the council is with TSG and is coming to an end on 4th November 2024, and was recently approved for extension.

6.3The contractors are also contracted to carry out any repairs for loss of heating and hot water and as such they are paid per property an all-inclusive annual rate for the gas service and 1 x repair per property. Should a property have more than 1 repair visit per year it is at the cost of the contractor which ensures a steady incentive to maintain the system well and deliver a best possible first-time fix.

Options

7.1If we do not enter into a contract, the Council will fail in providing its statutory Gas and Boiler Servicing requirements. This presents a significant risk to the Council given the risk involved in not servicing a boiler to Health and Safety duties of the council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of contract for provision of Servicing Domestic Boilers (West Area)Report 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, apologies
GP
Councillor George PotterCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
JW
Councillor James WalshGuest, in attendance, virtual
VK
Councillor Vanessa KingGuest, in attendance, virtual
TD
The Deputy Mayor, Councillor Howard SmithGuest, in attendance

All 13 on the meeting page

On this subject at Guildford

Search all
  1. Procurement of contract for provision of Servicing Domestic Boilers (West Area)This decision
  2. Procurement Pipeline and Delegation of Authority to award contractsApproved
  3. Procurement Pipeline and Delegation of Authority to award contractsApproved
  4. Procurement of contract for provision of Servicing Domestic Boilers (East Area)Refused

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies