That application 24/P/01428 be refused for the following reasons: (1) By virtue of the height, width, mass and cramped nature of the proposed development, it fails to reflect the distinct local character of the immediate neighbouring properties in Send Road and Tannery Lane. (2) The proposed development clearly and demonstratively fails to reinforce and respond to local distinct patterns of development, contrary to policy D1 (4) of the Guildford Borough Local Plan: Strategy and Sites, and by virtue of that, it also fails to meet the requirements of policy D4 of the Guildford Borough Local Plan: Development Management Policies, in that it fails to demonstrate how it will achieve a well-designed place both in terms of (a) enhancing its surroundings - paragraph (a), context, and (b) providing a coherent pattern of development with its neighbours - paragraph (c), built form. (3) The proposed development also fails to meet two of the Send Neighbourhood Development Plan policies, namely: (a) Policy Send 1 - Design, which states that high quality and sustainable design is expected in Send and shall conserve and enhance its heritage and environmental assets, and (b) Paragraph (b) of Policy Send 2 - Housing Development, which states that housing development in Send Parish will be supported, provided ... view the full minutes text for item PL24
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
That delegated authority be granted to the Assistant Director of Planning to approve subject to the completion of a legal agreement securing SANG and SAMM contributions and subject to the following conditions and reasons:
1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51(1) of the Planning and Compulsory Purchase Act 2004.
2. The development hereby permitted shall be carried out in accordance with the following approved plans:
Received 01/10/2024
• 1788/S-01 Existing Site plan • 1788/P-02 Proposed Plans and Elevations Unit 1 and Unit 2 • 1788/P-03 Proposed Plans and Elevations Unit 3 and Unit 4 • 1788/S-02 Existing Plans and Elevations 94 and 95 • 1788/S-03 Existing Plans and Elevations 96 and 97, Shed, Office and Outbuilding • 1788/S-04 Existing Plans and Elevations Garage 1, Garage2 and Summer House • 1788/P-04 Proposed Street Scene and Site Section AA • 1788/S-05 Existing Street Scene and Site Section AA
Received 27/01/2025 • Tree Protection Plan (Sapling, Plan ref: J1535 dated 30/09/2024).
Received 08/05/2025
• 1788-OS-02A Amended Site Location Plan • 1788-P-01C Amended Site Plan with Visibility Splays and Tracking
Reason: To ensure that the development is carried out in accordance with the approved plans and in the interests of proper planning.
3. Prior to any work commencing on site, including site clearance and demolition, a ‘Construction Environmental Management Plan’ (CEMP) shall be submitted to, and approved in writing by, the Local Planning Authority. The CEMP shall include all the following details:
a) An indicative programme for carrying out of the works b) The arrangements for public consultation and liaison during the construction works c) Measures to minimise the noise (including vibration) generated by the construction process to include hours of work, proposed method of piling for foundations, the careful selection of plant and machinery and use of noise mitigation barrier(s) d) Details of any floodlighting, including location, height, type and direction of light sources and intensity of illumination e) the parking of vehicles of site operatives and visitors f) loading and unloading of plant and materials g) storage of plant and materials used in constructing the development h) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate i) wheel washing facilities j) measures to control the emission of dust and dirt during construction k) a scheme for recycling/disposing of waste resulting from construction work l) Details of measures to mitigate the impact of construction activities on protected species specified in Section 5.3 of the Preliminary Ecological Appraisal (PJC, Ref: 5643E/24/01, dated 20/09/2024)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.