Guildford Borough Council
Planning Committee, Wednesday 8 October 2025 at 7.00pm

25/P/00753 - Land to the rear of Manor House Flats, The Street, Tongham, Farnham, GU10 1DP

Approved Planning 1 paper

AI summaryGuildford Planning Committee approves six new council-built flats on land behind Manor House Flats in Tongham, subject to conditions and a planning obligations agreement covering Thames Basin Heaths mitigation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFinal conditions and S106 wording delegated to Assistant Director of Planning
MoneyNo sums stated in papersSPA mitigation via adopted tariff, amount unspecified
What happens nextS106 legal agreement to be completedBefore planning permission is granted
Who it affectsTongham residents and new occupantsSix flats in two blocks on a backland plot

What was decided

Application 25/P/00753 was approved, with the Assistant Director of Planning given delegated authority to agree final conditions and grant permission once a Statement of Intent securing planning obligations, including SPA mitigation, is completed. Report P17

The development will deliver six new flats, three one-bed and three two-bed, in two blocks on a backland site accessed from The Street, with six unallocated parking spaces. Report P10, P11, P12, P13, P70, P71, P72, P73

Conditions must cover, among other matters, protection of trees and ecology and a Construction Traffic Management Plan covering traffic, hours and site logistics.

Why

The site is within the urban area and allocated housing site A31, where 1,485 of 1,750 allocated units are already permitted or built, and the council cannot currently demonstrate a five-year housing land supply, triggering the NPPF's tilted balance in favour of sustainable development. Report P99, P102, P103, P106

Officers found the scale, design and massing acceptable, with no unacceptable harm to character, neighbouring amenity, locally listed buildings, flood risk, or highway safety, subject to recommended conditions and a legal agreement for SPA mitigation. Report P16, P117, P129, P134, P143, P153, P156, P160

Seven letters of objection were received on issues including loss of green space, trees, privacy, highway safety, parking and construction disturbance, but officers judged these not to outweigh the benefits of the proposal. Report P85

What happens next

A Section 106 agreement must be completed to secure SANG and SAMM contributions under the Thames Basin Heaths SPA Avoidance Strategy tariff before permission is granted. Report P17

Pre-commencement conditions require a Biodiversity Gain Plan, reptile mitigation strategy, sensitive lighting management plan, site waste management plan, tree protection, and a detailed drainage strategy to be submitted and approved. Report P22, P29, P30, P33, P50

Development must begin within three years of the permission date and proceed in accordance with the approved plans and technical documents listed in the decision. Report P19, P20

Options considered

  • Chosen: Approve the application with delegated authority and conditions, including SPA mitigation. Site is allocated, within urban area, no unacceptable harm identified, council lacks five-year housing supply triggering tilted balance Report P17, P99, P102, P103, P106
  • Rejected: Refuse the application. Officers found no material harm that would warrant refusal; design concerns, amenity issues and third-party objections were not sufficient to outweigh benefits Report P85, P114, P117

Implications

  • Legal: Planning permission is conditional on completion of a Section 106 agreement securing SPA mitigation contributions and a Statement of Intent covering equivalent planning obligations. Report P17
  • Environment and climate: Conditions require a Biodiversity Gain Plan delivering at least 20% net gain for 30 years, a reptile mitigation strategy, sensitive lighting for bats, and an Energy and Sustainability Statement and Overheating Assessment. Report P27, P33, P44, P50
  • Risk: Conditions require a Construction Traffic Management Plan, a Site Waste Management Plan, a detailed reptile strategy, and continued badger sett monitoring to manage ecological and amenity risks during construction. Report P30, P33, P177, P178
  • Other: Conditions require a Sensitive Lighting Management Plan, water efficiency of 110 litres per occupant per day, and adherence to the approved Flood Risk Assessment and drainage strategy. Report P39, P48, P50

Who and where

  • Future occupants of the six new flats Report P10, P11
  • Residents of 13-21 Scarlet Road, whose rear boundaries adjoin the site Report P147, P148, P149
  • Residents of 1-16 Manor House Flats, adjoining the site to the east Report P151, P155, P158
  • Tongham residents and the wider local community Report P85
  • Tongham Parish Council, which raised no objection Report P83

Timeline

  • 20 May 2025: Application and most plans received Report P20
  • 5 June 2025: Plan 19-186_005 REV-P03 received Report P20
  • 22 September 2025: Plan 19-186_006 REV-P04 received Report P20
  • 8 October 2025: Planning Committee considers application 25/P/00753
  • Within three years of permission: Development must begin Report P19

Plain English for the jargon

  • SPA mitigation contributions: Payments to the Thames Basin Heaths Special Protection Area Avoidance Strategy, used to provide Suitable Alternative Natural Greenspace (SANG) and Strategic Access Management and Monitoring (SAMM) to protect protected bird species.
  • Tilted balance: The NPPF presumption in favour of sustainable development, applied where a council cannot show a five-year housing land supply, weighing benefits against any adverse impacts but starting from a position favouring approval.
  • Biodiversity Net Gain (BNG): A requirement that development delivers a measurable improvement in habitat value, with a national minimum of 10% rising to 20% in some local policies, maintained for at least 30 years.
  • CTMP: Construction Traffic Management Plan, a document setting out how construction vehicles will access the site, manage deliveries, and minimise disruption to the highway.
  • Site Allocation A31: A strategic location in Guildford's Local Plan allocated for around 1,750 homes across Ash and Tongham, of which 1,485 are already permitted or completed.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPL58a

Resolved

That application 25/P/00753 be approved, with delegated authority to the Assistant Director of Planning to agree the final wording of conditions and grant planning permission, subject to completion of a Statement of Intent securing the equivalent planning obligations, including SPA mitigation contributions in accordance with the adopted tariff. Conditions to include (inter alia) protection of trees and ecology and a CTMP to manage construction traffic, hours and site logistics.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Planning Committee

Executive summary

Reason for referral

This application has been referred to the Planning Committee because Guildford Borough Council is the applicant.

Key information

The application site is located within the urban area of Ash and Tongham and consists of an undeveloped plot with a large group of trees as well as a number of other semi-mature individual trees. Access to the site is via The Street, over the existing access that serve Manor House Flats.

The site is bordered by residential development on the western, southern and eastern boundaries. To the north is a small, grassed area, with residential development beyond that.

The site is relatively flat in topography with small undulations around the site. The site is bordered by a close boarded timber fence which separates the application site from the newer development to the south.

The site is subject to the following planning constraints:

• Urban Area • Site Allocation A31 • Locally listed building (wall) • 400m - 5km Thames Basin Heaths Special Protection Area buffer zone

The surrounding area is residential in character with a mixture of housing types and designs evident. This includes the new housing development to the south as well as older, more linear development along The Street. Proposal

The application is for the redevelopment to provide six new homes (2 blocks of flats) with associated amenity space, landscaping, car and cycle parking.

The proposal would consist of the following housing mix: • three one bed, two person dwellings. • three two bed, four person dwellings.

The dwellings would consist of two blocks of flats, each with three dwellings (units 1 - 3 and units 4 - 6).

Six unallocated parking spaces, along with an extended access from The Street.

The application site is subject to the following constraints: • Urban Area • Site Allocation A31 • Locally listed building (wall) • 400m - 5km Thames Basin Heaths Special Protection Area buffer zone

Summary of considerations and constraints

The proposed development would deliver six additional residential units of an acceptable scale, design and massing, and would therefore not result in unacceptable harm to the character of the area. The site and building layout would ensure that acceptable living conditions would be provided to the occupants, and the amenity of neighbouring properties would not be impacted to an unacceptable level. Conditions are recommended to ensure impacts on highway safety, ecology, flooding, drainage and trees are acceptable, that the development delivers a high level of energy efficiency and sustainability and that the mandatory biodiversity net gain is achieved. Subject to the recommended conditions and the completion of a legal agreement to secure appropriate mitigation for the Thames Basin Heaths Special Protection Area, the development is recommended for approval.

RECOMMENDATION: That delegated authority be granted to the Assistant Director of Planning to agree the final wording of the planning conditions and to grant planning permission subject to a S106 agreement being entered into to secure the provision of SANG and SAMM Contributions in accordance with the adopted tariff of the SPA Avoidance Strategy to mitigate against the impact on the Thames Basin Heath Special Protection Area.

Approve - subject to the following condition(s) and reason(s) :-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/P/00753: Land to the rear of Manor House Flats, The Street, Tongham, Farnham, GU10 1DPReport 1.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 20 attended
VK
Councillor Vanessa KingChair, present
JJ
Councillor James JonesVice-Chair, present
BA
Councillor Bilal AkhtarCommittee Member, present
JB
Councillor Joss BigmoreCommittee Member, apologies
DB
Councillor David BilbeCommittee Member, present
YD
Councillor Yves de ContadesCommittee Member, apologies
LG
Councillor Lizzie GriffithsCommittee Member, apologies
SH
Councillor Stephen HivesCommittee Member, present
MM
Councillor Masuk MiahCommittee Member, present
RM
Councillor Richard Mills OBECommittee Member, present
PO
Councillor Patrick OvenCommittee Member, present
MR
Councillor Maddy RedpathCommittee Member, present

All 20 on the meeting page

On this subject at Guildford

Search all
  1. 25/P/00753 - Land to the rear of Manor House Flats, The Street, Tongham, Farnham, GU10 1DPThis decision
  2. 25P00613 - Land to the rear of the Harrow InnDecided
  3. 24/P/01428 - Land to the rear of 94 to 97 Send Road, Send, GU23 7HNRefused
  4. 24/P/01428 - Land to the rear of 94 to 97 Send Road, Send, GU23 7HNDeferred
  5. Freehold disposal of land known as Land to the rear of 4 Middle Farm Close, EffinghamApproved
  6. 19/P/00634 - Land rear of Chicance and Quintons, Ockham Road North, East Horsley, KT24 6PUApproved

More from Guildford Planning Committee

All decisions
MeetingDecisionOutcome
26 Aug 2026 26P00194 - 9 North StreetThat application 26/P/00194, be APPROVED, subject to the conditions and reasons as set out in the Officer’s report. Approved Open
26 Aug 2026 26P00630 - 98 Yew Tree DriveThat application 26/P/00630 be APPROVED, subject to the conditions and reasons set out in the Officer’s report. Approved Open
26 Aug 2026 26P00492 - 1, 3, 5 York RoadThat application 26/P/00492 be APPROVED, subject to the conditions and reasons set out in the Officer’s report. Approved Open
26 Aug 2026 26P00662 - Foxenden Quarry PlaygroundThat application 26/P/00662 be APPROVED, subject to the conditions and reasons set out in the Officer’s report. Approved Open
22 Jul 2026 Local code of conduct - disclosure of interestsIt was agreed Cllr Smith would observe the presentation, address the meeting as Ward Councillor, then absent himself ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies