AI summaryGuildford Planning Committee approved an eight bedroom House in Multiple Occupation at 54 Queen Eleanors Road, subject to conditions and a S106 agreement securing £16,280.98 in SANG and £1,910.20 in SAMM contributions.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedEight bedroom HMO granted with conditions
MoneyS106 contributions requiredSANG £16,280.98 and SAMM £1,910.20
What happens nextS106 agreement requiredUnilateral undertaking to secure payments
Who it affectsOnslow ward neighboursEspecially 52 and 56 Queen Eleanors Road
What was decided
The Planning Committee approved the application, with delegated authority given to the Assistant Director of Planning to grant permission subject to conditions and a S106 agreement. Report P13
The use is limited to a maximum of eight single occupants, with all rooms single occupancy only. Report P32
The change of use is from a C3 dwellinghouse to a sui generis eight bedroom HMO, including conversion of the existing garage and utility area to living accommodation. Report P8, P41
Why
Officers found the change of use would not unbalance family housing and HMOs in the area, would not harm the character of the area, and would not harm neighbouring amenity. Report P12, P72, P78
The site is in a sustainable location close to the town centre, Surrey University and the Royal Surrey Hospital, supporting lower than maximum car parking provision. Report P98, P99
The County Highway Authority and the Head of Environmental Health and Licensing raised no objection, subject to recommended conditions. Report P46, P47
What happens next
The applicant must complete a Unilateral Undertaking under S106 to secure the SANG and SAMM contributions before permission is issued. Report P115, P117
Pre-commencement and pre-occupation conditions must be met, covering material samples, biodiversity enhancements, widened access, parking for three vehicles, cycle facilities, EV charging, and water efficiency of 110 litres per person per day. Report P18, P20, P22, P24, P26, P28, P30
The development must begin within three years of the date of permission. Report P14
The money
£16,280.98 SANG contribution towards Thames Basin Heaths Special Protection Area mitigation, based on occupancy uplift from five bed C3 to eight occupants Report P115
£1,910.20 SAMM contribution for Strategic Access Management and Monitoring, based on occupancy uplift from five bed C3 to eight occupants Report P115
Options considered
Chosen: Approve with conditions and a S106 agreement (officer recommendation). Compliant with policy, no harm to character, amenity, or highway safety, and TBHSPA mitigation secured Report P12, P13, P46, P115
Rejected: Refuse. Officers identified no material harm to character, amenity, or highways that would justify refusal Report P12, P78, P87, P102
Implications
Legal: A S106 agreement (Unilateral Undertaking) is required to secure SANG and SAMM contributions before planning permission can be granted. Report P115, P117
Environment: SANG and SAMM payments mitigate the impact of additional occupants on the Thames Basin Heaths Special Protection Area within the 400 metre to 5 kilometre buffer zone. Report P39, P114, P115
Climate: Conditions require EV charging, secure cycle storage with e-bike charging, permeable parking surface, rainwater harvesting, and a water efficiency of 110 litres per occupant per day. Report P28, P30, P34, P107
Equalities: Officers concluded the decision would not have an impact on protected groups under the Equality Act 2010, and would not breach Articles 1 and 8 of the European Convention on Human Rights. Report P120, P121
Risk: Objectors raised cumulative HMO concentration concerns; officers note that with other approvals, HMOs would still be a small proportion of properties in the area. Report P49, P72
Who and where
Twenty two third party objectors who submitted letters of representation Report P49
Neighbours at 52 and 56 Queen Eleanors Road, closest to the proposal Report P80
Future occupants of the eight bedroom HMO, limited to single occupancy Report P32, P92
Residents of Onslow ward, where the application site is located Report P4, P37
Users of Queen Eleanor's C of E Junior School, situated at the start of Queen Eleanors Road Report P67
Timeline
15 October 2025: Plans 10, 31, 40 and 30 Rev A received by the council Report P16
10 December 2025: Plan BR02 Rev B received by the council Report P16
2026-01-07: Planning Committee resolved to approve the application subject to conditions and a S106 agreement
Plain English for the jargon
HMO: House in Multiple Occupation, a shared rental home where tenants share facilities
C3: Planning use class covering dwellinghouses used by a single household
Sui generis: Planning use class for uses that do not fall within any defined use class, including HMOs of more than six occupants
SANG: Suitable Alternative Natural Green Space, provided to divert visitors away from protected heathland
SAMM: Strategic Access Management and Monitoring, measures to manage visitor pressure on protected heathland
TBHSPA: Thames Basin Heaths Special Protection Area, a European protected site for rare birds
S106: Section 106 legal agreement under the Town and Country Planning Act used to secure planning obligations
NDSS: Nationally Described Space Standards, minimum size standards for new dwellings
LPDMP: Local Plan: Development Management Policies, Guildford's detailed planning policies
EV: Electric Vehicle
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPL86
Resolved
That application 25/P/01398 be approved, with delegated authority granted to the Assistant Director of Planning to grant planning permission subject to conditions and a S106 agreement being entered into to secure the provision of SANG and SAMM ... view the full minutes text for item PL86
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
This application has been referred to the Planning Committee because more than 10 letters of objection have been received, contrary to the Officer's recommendation. The application is also for a House in Multiple Occupation which are referred to the planning committee by the Assistant Director of Planning.
Key information
The application site is located within the ward of Onslow and consists of a detached, two storey dwellinghouse. The site benefits from a large, spacious garden and onsite parking for two vehicles. The surrounding area comprises predominantly detached two storey dwellinghouses of similar designs to the host property.
The topography of the site is generally flat, with some minor undulations within the garden and a step down from the existing patio. The rear boundaries are largely screened by trees and scrubs, with some views of neighbouring properties through gaps in the vegetation.
The site is subject to the following constraints: • 400m - 5km Thames Basin Heaths Special Protection Area buffer zone • Green Newt Impact Zone
Proposal.
Change of use from an existing dwelling house under C3 to an 8 bedroom HMO under Sui Generis. With the conversion of the existing garage and utility area to living accommodation. Change of internal layout to existing dwelling, with removal of existing garage door an opening infilled with new window and brickwork infill below. 1no new double door set to side facing elevation. 6no additional opaque glazed windows serving en suites to ground and first floor elevations opening area at 1.7m above FFL.
The application is supported by the following technical documents: • Climate Change Questionnaire • Highway Statement • Design and Access Statement
The scheme also includes an extension to the car parking area at the front of the site, to be finished with a permeable surface and the construction of a cycle store to the rear.
Summary of considerations and constraints
The proposed change of use from a C3 dwellinghouse to a sui generis HMO for up to eight occupants would not create an unbalance between family housing and HMOs, nor would it result in an unacceptable impact on the character of the area or on neighbouring amenity. The dwelling would provide acceptable living conditions to the occupants, including a spacious garden area and largely private bathroom facilities. Through the imposition of conditions the proposal would not result in a material adverse impact on highway safety and would achieve an adequate level of sustainability. Subject to the completion of a legal agreement to secure the mitigation on the TBHSPA, the proposed development is recommended for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.