New contract for Aids & Adaptations to Guildford Borough Council Properties
ApprovedExecutive1 paper
AI summaryGuildford Borough Council's Executive has approved awarding £2.5 million of aids and adaptations contracts to four contractors for up to five years, ensuring continuity of disability housing adaptations.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor aids and adaptations works to council properties
Money£2.5 millionTotal estimated value over the full five year term
What happens nextEnter into contractsThree years initial, extendable by two years
Who it affectsCouncil tenants needing adaptationsResidents with disabilities and mobility needs
What was decided
Awarded contracts for Aids and Adaptations Works to DAAS Group Limited, Southern Counties Building Solutions Ltd, Milestone South East Limited and Topcoat Construction Ltd, at a total estimated combined value of £2.5 million for an initial three years with the option to extend for up to two further periods of twelve months each. Report P5, P6, P14
The contracts will be funded by Central Government Grants, with annual expenditure of approximately £500,000 drawn from Disabled Facility Grants and related funding streams. Report P44, P45, P51
Works will be allocated to the four contractors on a rotational basis to ensure capacity, resilience and value for money. Report 6.4, 10.3
Why
The Council has a statutory responsibility under the Care Act 2014 and housing legislation to provide aids and adaptations that help eligible residents live independently and safely in their homes. Report 6.1, 1.2, 3.3
The procurement, run as a two stage Competitive Flexible Procedure under the Procurement Act 2023, attracted 75 expressions of interest and 15 tender responses, with four Most Advantageous Tenders identified. Report 6.2, 6.5, 3.2
Using a panel of four contractors provides resilience and continuity of service delivery, and is needed before the transfer of functions to West Surrey Council on 1 April 2027. Report 10.3, 8.1, 8.3
What happens next
Enter into contracts with each of the four named contractors for the supply of Aids and Adaptations to Guildford Borough Council properties. Report 4.1, P14
Allocate works on a rotational basis, monitor service quality, and ensure contractual flexibility so contracts can be transferred, novated, varied or terminated after vesting day if needed. Report 6.4, 8.3
Report the decision taken under the General Consent to the West Surrey Shadow Council, since the contracts will become its responsibility. Report P51, 12.2
The money
£2.5 million Total estimated combined contract value over the full five year term, split across four suppliers Report 1.1, P5, P44
approximately £500,000 Estimated annual expenditure, funded by Central Government Grants and demand led Report P45
Options considered
Chosen: Award the contracts to the four highest ranked bidders. Ensures continued delivery of adaptations, value for money, resilience and service quality Report 11.2
Rejected: Do nothing. Would significantly impact delivery, increase waiting times, cause resident dissatisfaction and risk non compliance with statutory obligations Report 11.1, 1.3
Implications
Legal: Procurement was run as an above threshold, two stage Competitive Flexible Procedure under the Procurement Act 2023 and the Council's Contract Procedure Rules; legal are instructed to finalise the contracts. Report 6.2, P52, P53, P54
Financial: Funded from Disabled Facility Grants, Disabled Facility top up Grant and Home Improvement Grant via Central Government; spend will only be incurred up to the value of the annual grant. Report P45, P51
Risk: Failure to award would risk harm to vulnerable residents, waiting time increases, and legal challenge or reputational damage under the Care Act 2014 and housing legislation. Report 10.1, 10.2, P36
Equalities: Supports residents with protected characteristics, especially disability, by enabling safe, independent living; officers concluded there are no direct equality and diversity implications from the report itself. Report 7.1, P58, P61
Climate: Adaptations refurbish or alter existing stock rather than replace it, extending asset life and reducing environmental impact; contractors will be expected to minimise waste and use local suppliers where possible. Report P63, P64, P67, P68
Staffing: No direct HR impacts; contracts help maintain stable workloads for relevant operational teams. Report P57
Who and where
Council tenants needing aids, adaptations or accessibility works in Guildford Borough Council properties Report 1.2, 6.1, 6.3
Eligible residents assessed under the Care Act 2014, including people with disabilities and mobility issues Report 3.1, 7.1
Guildford Borough Council operational teams delivering adaptations Report P57
West Surrey Council as the successor authority from 1 April 2027 Report 8.1, 8.3
Timeline
10 March 2026: Surrey (Structural Changes) Order 2026 came into effect, placing duties on the Council up to vesting day Report 8.1
9 June: West Surrey Shadow Executive granted General Consents covering capital contracts funded by Disabled Facility Grants, Disabled Facility top up Grant or Home Improvement Grant Report 12.2, P51
23 July 2026: Guildford Borough Council Executive approved the contract awards
Three years initial term: Initial contract period for the four Aids and Adaptations Works contracts Report P5, 4.1
Up to two further periods of twelve months each: Optional extensions to the initial three year term, giving a potential total of five years Report P5, 4.1
1 April 2027: Vesting day when functions transfer to West Surrey Council Report 8.1
Plain English for the jargon
Aids and Adaptations: Works such as level access showers, ramps, grab rails and property alterations that help residents live independently
Most Advantageous Tender: The winning bid under the Procurement Act 2023, selected on quality and price
Disabled Facilities Grant (DFG): Central Government funding used to pay for essential adaptations to eligible residents' homes
Competitive Flexible Procedure: A two stage procurement route under the Procurement Act 2023
s24 Direction: A direction under section 24 of the Local Government and Public Involvement in Health Act 2007 requiring consent from the West Surrey Shadow Executive for certain contracts
Vesting day: The date on which the new West Surrey Council takes on its functions, 1 April 2027
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX37
Resolved
To approve the award of the contracts for Aids and Adaptations Works to the following contractors for an initial period of three years, with the option to extend for up to two further periods of twelve months each, at a total estimated combined contract value of £2.5 million: · DAAS Group Limited · Southern Counties Building Solutions Ltd · Milestone South East Limited · Topcoat Construction Ltd Reason(s): 1. The Council requires suitably qualified and experienced contractors to undertake aids and adaptations works that enable residents to live independently and safely within their homes. 2. The procurement process identified four Most Advantageous Tenders capable of delivering high-quality services and providing sufficient capacity and resilience to meet demand. 3. Awarding the contracts supports the Council’s statutory responsibilities and ensures continuity of service delivery while achieving value for money through a compliant procurement process. Other options considered and rejected by the Executive: Do nothing - Failure to award the contracts would significantly impact the Council’s ability to deliver adaptations works, potentially leading to increased waiting times, resident dissatisfaction and non-compliance with statutory obligations. This option is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
1.1The purpose of this report is to seek approval, in accordance with Guildford Borough Council’s Contract Procedure Rules, to award contracts for the provision of Aids and Adaptations Works to four contractors for an initial period of three years, with options to extend for up to two further years (1 + 1) at a total estimated contract value of £2.5 million (for the full 5 year period), split across 4 suppliers.
1.2The contract will support the Council in meeting its obligations under the Care Act 2014 and Housing legislation by providing essential adaptations to Council owned properties that enable residents to live safely and independently in their homes. The procurement has established a panel of four suitably qualified contractors who will undertake adaptation works on a rotational basis, ensuring resilience, capacity and value for money.
1.3Approval of the recommendation will enable the Council to continue delivering timely aids and adaptations works, improving resident wellbeing, reducing risks associated with unsuitable housing, and supporting the Council’s strategic priorities. Failure to award the contracts would significantly impact service delivery and the Council’s ability to meet its statutory obligations.
Recommendations
2.1That the Executive resolves to:
2.1.1 Approve the award of the contracts for Aids and Adaptations Works to the following contractors for an initial period of three years, with the option to extend for up to two further periods of twelve months each, at a total estimated combined contract value of £2.5 million:
DAAS Group Limited Southern Counties Building Solutions Ltd Milestone South East Limited Topcoat Construction Ltd
3 Reason(s) for recommendation:
2 The award of new contract for Aids and Adaptations
3.1The Council requires suitably qualified and experienced contractors to undertake aids and adaptations works that enable residents to live independently and safely within their homes.
3.2The procurement process identified four Most Advantageous Tenders capable of delivering high-quality services and providing sufficient capacity and resilience to meet demand.
3.3Awarding the contracts supports the Council’s statutory responsibilities and ensures continuity of service delivery while achieving value for money through a compliant procurement process.
4 Next steps
4.1To enter into contracts with each of the contractors listed below for the supply of Aids and Adaptations to GBC Properties for a period of three (3) years, with the provision to extend for a further two further periods of twelve months each:
DAAS Group Limited Southern Counties Building Solutions Ltd Milestone South East Limited Topcoat Construction Ltd
5 Exemption from publication
5.1The Appendix to this report is exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972.
6 Background and Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.