Albert Road (North) Pedestrianisation Scheme

Approved Executive 2 papers

AI summaryHalton Executive Board approves pedestrianisation of Albert Road (north) in Widnes, funded by Active Travel Fund 5 and a roll-forward of ATF4, to be built within six months before March 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyATF5 grant plus ATF4 roll-forwardFunded via Liverpool City Region Combined Authority, no council match required
What happens nextBuild phase around six monthsGrant must be spent by March 2027
Who it affectsNot stated

What was decided

The Board approved the Albert Road (north) pedestrianisation scheme for delivery, as set out in the report and shown on the plan in Appendix A. Report P3

The Board delegated authority to the Director of Planning and Transport, in consultation with the Portfolio Holder for Environment and Urban Renewal, to handle matters related to delivering the scheme. Report P4

Why

The scheme is intended to improve safety and amenity, encourage pedestrian movement, support town centre trade, and reduce noise and improve local air quality on this section of Albert Road. Report 3.1, 3.12

Officers judged the scheme's advantages to outweigh its disadvantages, noting loss of on-street parking, relocation of the existing bus stop, and a short traffic diversion along Robert Street. Report 3.13, 3.14

The scheme fits council policies on active travel, town centre vitality, modal shift to lower carbon transport, and reducing congestion, and aligns with the Local Cycling and Walking Infrastructure Plan. Report 4.1, 4.2, 4.3

What happens next

The Director of Planning and Transport, with the relevant Portfolio Holder, will handle delivery matters under the delegated authority. Report P4

The construction phase is expected to last about six months and must be completed by March 2027 to avoid losing the grant. Report 5.3, 7.1, 7.2

The Pedestrianisation Order finished advertising in December 2025 with no objections, and consultation with bus and taxi operators has resolved earlier concerns. Report 3.9, 3.10

The money

  • Active Travel Fund 5 Grant funding for the north Albert Road pedestrian improvements Report 5.2, 5.3
  • Active Travel Fund 4 Roll-forward of earlier active travel funding used on this scheme Report 5.2, 3.4

Options considered

  • Chosen: Full pedestrianisation by filling in the carriageway to create a level surface across the width of the street with no kerbs. Preferred option identified through site meetings with local ward councillors, supported by consultation Report 3.7, 3.8, 3.11

Implications

  • Financial: The scheme relies entirely on external grant funding; if delivery slips past March 2027 the grant is lost, with no alternative funding identified. Report 5.3, 7.1, 7.2
  • Legal: A Pedestrianisation Order was advertised and closed in December 2025 with no objections, clearing the legal route to restrict traffic. Report 3.10
  • Equalities: The scheme aims to provide a safer, more navigable environment for people using mobility aids or who are partially sighted, by removing dropped kerbs and motorised traffic. Report 8.1
  • Climate: The scheme supports low carbon and low cost travel choices and aims to use lower carbon materials such as warm mix asphalt where possible. Report 9.0, 9.2, 4.2
  • Risk: Loss of grant is the key risk if the six-month build does not complete before the March 2027 deadline. Report 7.1, 7.2
  • Other: Parking directly outside businesses on this section of Albert Road will be removed, and the existing bus stop will be relocated just beyond the junction. Report 3.13

Who and where

  • Businesses and residents on the affected section of Albert Road in Widnes Report 3.8, 3.12, 3.13
  • Bus passengers, with services rerouted via Robert Street to a new bus stop Report 3.2, 3.9
  • Taxi users, with the Wetherspoons taxi rank made permanent on a 24 hour basis Report 3.9
  • Pedestrians, including shoppers, people with mobility issues, children and young people Report 3.1, 3.12, 6.3
  • Local ward councillors who led early engagement Report 3.3, 3.7, 3.8

Timeline

  • early 2023: Initial discussions held with Members and local ward councillors following early engagement with affected businesses Report 3.3
  • June 2023: Scheme highlighted in a transport projects update to the EUR PPB under Active Travel Fund 4 Report 3.4
  • July 2023: Transport projects update considered at Executive Board Report 3.4
  • September 2025: Further consultation letter sent to affected properties, with no negative feedback received Report 3.8
  • December 2025: Pedestrianisation Order advertising period ended with no objections Report 3.10
  • 15 January 2026: ATF5 funding reported to the last Executive Board Report 3.5
  • 12 February 2026: Executive Board approves scheme for delivery Report P3
  • by March 2027: Grant funding must be spent; build phase expected to take around six months Report 5.3, 7.1, 7.2

Plain English for the jargon

  • Active Travel Fund (ATF): Government funding from Active Travel England and the Department for Transport that supports local authorities in developing and constructing walking and cycling facilities.
  • ATF4 / ATF5: The fourth and fifth tranches of the Active Travel Fund awarded since Covid.
  • EUR PPB: Environment and Urban Renewal Policy and Performance Board, a Halton scrutiny committee.
  • Pedestrianisation Order: The legal mechanism used to restrict or prohibit motor traffic on a street, subject to a public advertising period for objections.
  • LCWIP: Local Cycling and Walking Infrastructure Plan, setting out the borough's active travel network.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item101

Resolved

That the Board 1) approves the Albert Road (north) pedestrianisation scheme for delivery, as set out in the report and shown on the Plan in Appendix A; and 2) the Director Planning and Transport, in consultation with the Portfolio Holder Environment and Urban Renewal be delegated to deal with any matters relating to the delivery of this scheme.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 5 pages

Purpose of the report

1.1Approval is sought to commence the pedestrianisation scheme along a section of Albert Road (north) between Deacon Road / Bradley Way and Robert Street in Widnes.

2.0RECOMMENDED: That the Board

1. approves the Albert Road (north) pedestrianisation scheme for delivery, as set out in this report and shown on the plan in Appendix A; and

2. delegates the requisite powers to the Director Planning and Transport, in consultation with the Portfolio Holder Environment and Urban Renewal, to deal with any matters relating to the delivery of this scheme

3.0SUPPORTING INFORMATION

3.1The Scheme By providing more space through environmental improvements, and excluding traffic through pedestrianisation, this scheme will improve safety and amenity and encourage pedestrian movements along Albert Road between Deacon Road / Bradley Way and Robert Street.

3.2All traffic, including buses, is to be diverted by using Robert Street instead of this section of Albert Road.

3.3Approvals Initial discussion of this scheme was undertaken with Members in early 2023 as local ward councillors were keen to see the area pedestrianised, having spoken to the local businesses affected.

3.4This scheme was then highlighted (under ATF4 which stands for Active Travel Fund 4) in an update on transport projects (within Appendix 2 of that report under ‘sustainable travel schemes’ considered by both the EUR PPB in June 2023, and at Executive Board in July 2023.

3.5The Council has recently received additional funding (ATF5) which will allow the full pedestrianisation of this section of Albert Road to be achieved. ATF5 funding was reported to the last Executive Board (15 January 2026).

3.6Now this scheme is fully worked up and has funding allocated, it is presented to Executive Board to approve the delivery phase.

3.7Consultations Site meetings have been held with local ward councillors to determine the appropriate options for this section of Albert Road between Deacon Rd / Bradley Way and Robert Street. The preferred option is to create a pedestrian only space by filling in the carriageway to make a level surface across the width of the street with no kerbs.

3.8Local Councillors canvassed early views from businesses and residents and there was positive public support for the scheme. A further round of consultation was done via letter to the affected properties in September 2025. No negative feedback was received.

3.9Consultation was undertaken with bus and taxi operators, and all the early objections to the scheme have been overcome by adapting the scheme. Specifically, these scheme refinements ensure that buses can utilise Robert Street to access a new bus stop, and the taxi rank outside Wetherspoons will be made permanent to provide a 24hr location for the taxis.

3.10A Pedestrianisation Order has also come to the end of its advertising period in December 2025 with no objections received.

3.11There is now a high level of support for the scheme from Members, businesses, residents, and transport providers.

3.12Scheme Advantages The scheme will generate synergy with the wider town centre by drawing shoppers up Albert Road. Food and drink establishments will be enabled to provide outside on-street seating (via a table & chair licence) for customers in the new space created. Pedestrianisation will make the local environment safer for shoppers and those with mobility issues, together with young people. It will also reduce noise and enhance local air quality in this section of Albert Road.

3.13Scheme Disadvantages The disadvantages of the scheme include the removal of parking options immediately outside the businesses on this section of Albert Road. The existing bus stop on Albert Road will require relocation to just beyond the junction. The scheme will also require a short diversion of traffic along Robert Street.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albert Road (North) Pedestrianisation SchemeReport 5 pages DownloadRead as text
PDF
EB Feb26 Albert Rd: Appendix1Appendix 1 pages Download

At this meeting

Whole meeting

Who was there

18 of 22 attended
MW
Councillor Mike WhartonChair, present
LB
Councillor Laura BevanMember, present
AB
Councillor Angela BallMember, present
MD
Councillor Mark DennettMember, present
PH
Councillor Phil HarrisMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, present
AW
Councillor Andrea WallMember, present
MW
Councillor Marie WrightMember, present
GC
Gill CookOfficer, present
RM
Rod McGarrigleCouncil Staff, expected

All 22 on the meeting page

On this subject at Halton

Search all
  1. Albert Road (North) Pedestrianisation SchemeThis decision
  2. - 18/00368/FUL - Proposed development of three storey apartment block comprising 13 no. apartments with ancillary development at Former Albert Hotel, 160 Albert Road, WidnesApproved
  3. Procurement of a Housing Support Service for the Albert Road Scheme for Homeless Single PersonsApproved
  4. - 13/00174/FUL - Proposed 39 no self contained apartments providing short term accommodation with associated car parking and landscaping at 88A - 92 Albert Road, WidnesApproved
  5. - 10/00368/S73 - Application to extend time limit for a further 3 years (application 07/00716/FUL) for proposed four storey mixed use development comprising 24 No two bed apartments and 4 No retail units at 88A - 92 Albert Road, WidnesApproved
  6. - 10/00078/OUT - Outline application (with landscape matters reserved) for proposed erection of four storey development consisting of 24 No. apartments and ground floor retail space at 88A – 92 Albert Road, WidnesAgreed

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open
22 Oct 2026 Specialist DA Therapeutic Support for Children: Request for Waiver of Standing OrdersThat the Board 1) are advised of the Domestic Abuse Board mapping work of the domestic abuse system and support offer... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies