CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Halton Borough Council
Executive Board, Thursday 12 February 2026

Public Sector Decarbonisation Fund - Picow Farm Road Depot

Decided Executive 1 paper

AI summaryHalton Borough Council's Executive Board will ask full Council to add £1,161,300 of energy efficiency works at Picow Farm Road depot to the Capital Programme, funded by a Public Sector Decarbonisation Fund grant with a Council contribution of £162,000 to £200,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRecommendedTo include scheme in Capital Programme
Money£1,161,300Total estimated project cost
What happens nextFull Council approvalBefore works start by March 2026
Who it affectsPicow Farm Road depotCouncil depot in Halton

What was decided

The Executive Board agreed to ask the Council to include £1,161,300 of energy efficiency works at Picow Farm Road within the Capital Programme. Report P2

The work would be funded mainly by a Public Sector Decarbonisation Fund grant, with a Council contribution of between £162,000 and £200,000. Report P2

Air source heat pumps, solar PV, LED lighting and wall insulation will be installed at Picow Farm Road by the appointed contractor Optimus. Report 4.1

Why

Halton was awarded £2,816,409.20 from the Public Sector Decarbonisation Fund as part of a Liverpool City Region bid of £30.5m covering Picow Farm, Kingsway Learning Centre and Runcorn Town Hall. Report 3.2, 3.3, P6

Picow Farm Road is the first site because works must begin before March 2026 in order to draw down the grant. Report 3.5

The measures support the Council's Climate Change Action Plan and its commitment to decarbonise its buildings where financially practicable. Report 5.1, 7.5, P29

What happens next

The full Council will consider adding the £1,161,300 to the Capital Programme. Report P2

Works at Picow Farm Road must commence before March 2026 to meet the grant deadline. Report 3.5

Kingsway Learning Centre and Runcorn Town Hall schemes will be subject to a further report once more detailed costings are known, with completion needed by March 2027. Report 3.5

The money

  • £1,161,300 Total estimated cost of energy efficiency works at Picow Farm Road Report P2
  • £162,000 - £200,000 Estimated Council contribution towards Picow Farm Road works Report P2, 4.3
  • £2,816,409.20 Total Public Sector Decarbonisation Fund award to Halton Report 3.3
  • £3,200,465 Overall estimated cost of works at all three Halton sites Report 3.3
  • £448,065.10 Total Council match funding required across all three sites Report 3.3, 3.4
  • £949,478.68 Current contractor cost for Picow Farm Road excluding any District Network Operator costs Report 4.2
  • £559,491 Estimated savings from a 135kw Solar PV system over the 30 year panel life
  • £10,000 Estimated annual reduction in running costs from LED lighting at Picow Farm
  • £200,000 Estimated cost to replace Picow Farm gas boilers within 2 to 3 years if not replaced now Report 4.6
  • £30.5m Total Public Sector Decarbonisation Fund award to the Liverpool City Region Report 3.3

Options considered

  • Chosen: Proceed with energy efficiency works at Picow Farm Road using the Public Sector Decarbonisation Fund grant and a Council contribution of between £162,000 and £200,000. The report presents this as the route to draw down the grant and begin works before the March 2026 deadline. Report P2, 3.5

Implications

  • Financial: The Council's contribution is expected to be repaid through savings and income in approximately 6 years. Report 4.5, 6.1
  • Climate: Estimated carbon saving of around 1646 tonnes of CO2 over the lifetime of the project, supporting the Council's Climate Change Action Plan. Report 4.5, 5.1
  • Financial: Solar PV and LED lighting are expected to deliver a net annual saving despite higher electric load from the air source heat pumps.
  • Financial: Progressing the scheme avoids an estimated £200,000 boiler replacement cost at Picow Farm within 2 to 3 years. Report 4.6
  • Risk: A detailed risk register will be provided by the contractor before installation. Report 8.1
  • Equalities: None identified. Report 9.1

Who and where

  • Halton residents, through improved air quality from reduced CO2 emissions Report P21
  • Local economy, through job creation and supply chain linked to energy efficiency investment Report P23
  • Council staff and operations at Picow Farm Road depot Report 4.1
  • The Council, as funder of the £162,000 to £200,000 contribution and beneficiary of long-term savings Report 4.3, 6.1

Timeline

  • Before March 2026: Works at Picow Farm Road must commence to meet grant conditions. Report 3.5
  • By March 2027: Works at Kingsway Learning Centre and Runcorn Town Hall must be completed. Report 3.5
  • Within 2 to 3 years: Picow Farm gas boilers would otherwise need replacement at an estimated £200,000. Report 4.6
  • Approximately 6 years: Time for the Council's contribution to be repaid through savings and income. Report 4.5
  • 30 year lifetime: Solar PV panels expected to generate around £559,491 of savings.

Plain English for the jargon

  • Public Sector Decarbonisation Fund: A grant scheme providing funding to public sector bodies for heat decarbonisation and energy efficiency measures such as solar PV and LED lighting.
  • Capital Programme: The Council's planned spending on major or long term schemes, as referenced for inclusion of the £1,161,300.
  • Air Source Heat Pumps: Heating systems to be installed at Picow Farm Road as a replacement for the existing gas boilers.
  • Solar PV: Solar photovoltaic panels, listed in the report as an energy efficiency measure funded by the scheme.
  • LED Lighting: Light emitting diode lighting, listed in the report as an energy efficiency measure funded by the scheme.
  • District Network Operator: The operator of the local electricity distribution network, referenced in relation to possible network improvement costs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item102

Resolved

That Council be requested to include £1,161,300 total estimated cost of the energy efficiency works at Picow Farm Road within the Capital Programme, to be funded by grant funding from the Public Sector Decarbonisation Fund and including a Council contribution of between £162,000 - £200,000.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 4 pages

Purpose of the report

1.1To outline details of grant funded awarded to the Council via the Public Sector Decarbonisation Fund and to seek approval to implement energy efficiency measures at Picow Farm Road.

Recommendation

That Council be asked to include £1,161,300 total estimated cost of the energy efficiency works at Picow Farm Road within the capital programme, to be funded by grant funding from the Public Sector Decarbonisation Fund and including a Council contribution of between £162,000 - £200,000

3.0SUPPORTING INFORMATION

3.1The Public Sector Decarbonisation Scheme provides grants for public sector bodies to fund heat decarbonisation and energy efficiency measures such as solar PV and LED lighting.

3.2During 2025 the Liverpool City Region Combined Authority submitted a bid to Phase 4 of the Fund which included the following buildings in Halton.

 Picow Farm,  Kingsway Learning Centre  Runcorn Town Hall

3.3The Bid was successful with the City Region awarded £30.5m. In respect of Halton a total of £2,816,409.20 was awarded. The overall costs of the works are estimated at £3,200,465 which includes a Council contribution of £448,065.10. Picow Farm £1,161,330 Kingsway Learning Centre £716,150 Runcorn Town Hall £ 1,322,985

3.4To draw down the funds the Council needs to provide total match funding of £448,065.10

3.5The initial focus of work following the bid has been on Picow Farm Road as there is a requirement to commence works prior to March 2026. The work at Kingsway Learning Centre and Runcorn Town Hall will be subject to further design work following a tender process with work needed to be completed by March 2027. These schemes will be subject to a further report when more detailed costing are known.

4.0PICOW FARM ROAD

4.1The Combined Authority had run a tender process and Optimus were appointed as the approved contractor for Picow Farm. Since their appointment they have completed design works at Picow Farm with a view to installing Air Source Heat Pumps, Solar PV, LED Lighting and wall insulation

4.2The total cost of the work is £949,478.68 excluding any District Network Operator costs. None are anticipated for these works but some network improvements will be needed as the Council shifts its Data Centre facility to Picow Farm Road and these costs will be picked up as part of that project. The current estimate of £949,478.68 for the works will likely increase as the contractor will have to provide more temporary welfare accommodation over and above what they have allowed for at Picow Farm but it is anticipated will remain in budget.

4.3The cost of the works are within the overall projected costs of £1,161,300 but the Council would need to make a contribution of between £162,000 and £200,000 towards the costs of the works. 4.4 The works will lead to costs savings from the installation of the Solar PV and LED. The 135kw Solar system would generate savings in the region of £559,491 over the 30 year life time of the panels. It is also estimated that the LED would reduce annual running costs by £10,000 per annum. Whilst the Air Source Heat Pumps will increase the electric load and running costs overall the savings from the Solar PV and LED will provide a net saving per annum.

4.5The savings/income generated would be sufficient to repay the Council’s contribution in approximately 6 years. The estimated carbon saving over the life time of the project is in the region of 1646 tonnes of CO2 emissions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Public Sector Decarbonisation Fund: Picow Farm Road DepotReport 4 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 22 attended
MW
Councillor Mike WhartonChair, present
LB
Councillor Laura BevanMember, present
AB
Councillor Angela BallMember, present
MD
Councillor Mark DennettMember, present
PH
Councillor Phil HarrisMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, present
AW
Councillor Andrea WallMember, present
MW
Councillor Marie WrightMember, present
GC
Gill CookOfficer, present
RM
Rod McGarrigleCouncil Staff, expected

All 22 on the meeting page

On this subject at Halton

Search all
  1. Public Sector Decarbonisation Fund - Picow Farm Road DepotThis decision
  2. Public Sector Decarbonisation Fund - Picow Farm Road Depot (EXB102 refers)Decided
  3. Public Sector Decarbonisation FundApproved
  4. Public Sector Decarbonisation FundNoted
  5. Halton Borough Council Update on Apprenticeship Policy/Apprenticeship Levy and Public Sector TargetNoted
  6. Halton Borough Council Update on Apprenticeship Policy Apprenticeship Levy & Public Sector TargetNoted

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open
22 Oct 2026 Specialist DA Therapeutic Support for Children: Request for Waiver of Standing OrdersThat the Board 1) are advised of the Domestic Abuse Board mapping work of the domestic abuse system and support offer... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies