Public Sector Decarbonisation Fund - Picow Farm Road Depot (EXB102 refers)

Decided Committee 1 paper

AI summaryHalton Borough Council adds £1,161,300 of energy efficiency works at Picow Farm Road depot to its Capital Programme, funded mainly by a Public Sector Decarbonisation Fund grant with a Council contribution of £162,000 to £200,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEnergy efficiency works at Picow Farm Road
Money£1,161,300Total cost, grant funded with £162,000-£200,000 Council contribution
What happens nextWorks to start before March 2026Further report due for other sites
Who it affectsPicow Farm Road depotHalton Borough Council estate

What was decided

Council agreed to include £1,161,300 in the capital programme for energy efficiency works at Picow Farm Road. Report P2

The works will be funded by a Public Sector Decarbonisation Fund grant, with a Council contribution of between £162,000 and £200,000. Report P2, 4.3

Air source heat pumps, solar PV, LED lighting and wall insulation will be installed at Picow Farm Road. Report 4.1

Why

A bid by the Liverpool City Region Combined Authority to Phase 4 of the Public Sector Decarbonisation Fund was successful, awarding Halton £2,816,409.20. Report 3.2, 3.3

Works at Picow Farm must start before March 2026, while gas boilers there are reaching the end of their useful life. Report 3.5, 4.6

The scheme supports the Council's Climate Change Action Plan and reduces carbon emissions. Report 5.1, 7.5, P29

What happens next

Optimus, the appointed contractor, will install the measures and provide a detailed risk register before installation. Report 4.1, 8.1

A further report will come forward on Kingsway Learning Centre and Runcorn Town Hall once detailed costs are known; works there must complete by March 2027. Report 3.5

The Council's contribution is expected to be repaid through savings and income in approximately 6 years. Report 4.5

The money

  • £1,161,300 Total estimated cost of Picow Farm energy efficiency works Report P2, 4.3
  • £162,000 - £200,000 Council contribution towards Picow Farm works Report P2, 4.3
  • £30.5m Award to Liverpool City Region from Public Sector Decarbonisation Fund Phase 4 Report 3.3
  • £2,816,409.20 Total awarded to Halton from the Fund Report 3.3
  • £3,200,465 Overall estimated cost of works across Halton sites Report 3.3
  • £448,065.10 Total Council match funding required across all three sites Report 3.3, 3.4
  • £1,161,330 Picow Farm share of overall Halton costs (as listed in paragraph 3.3) Report 3.3
  • £716,150 Kingsway Learning Centre share of overall costs Report 3.3
  • £1,322,985 Runcorn Town Hall share of overall costs Report 3.3
  • £949,478.68 Current cost estimate for Picow Farm contractor works, excluding network operator costs Report 4.2
  • £559,491 Estimated savings from 135kw Solar PV system over 30 year panel life
  • £10,000 Estimated annual reduction in running costs from LED lighting
  • £200,000 Estimated cost of replacing Picow Farm gas boilers within 2-3 years if not replaced under this scheme Report 4.6

Options considered

  • Chosen: Include £1,161,300 in the capital programme funded by PSDF grant with Council contribution of £162,000-£200,000. Allows the Council to draw down grant funding and meet the March 2026 works deadline Report P2, 3.5

Implications

  • Financial: The Council must provide £162,000 to £200,000 of match funding, repayable from savings and income in about 6 years. Report 4.3, 4.5, 6.1
  • Financial: Future boiler replacement costs of around £200,000 in 2-3 years are avoided by the scheme. Report 4.6
  • Climate: Estimated carbon saving of about 1,646 tonnes of CO2 over the lifetime of the project. Report 4.5, 5.1
  • Risk: Picow Farm works cost may rise above £949,478.68 due to extra temporary welfare provision; expected to stay within budget. Report 4.2
  • Equalities: No equality and diversity issues identified. Report 9.1
  • Other: Network upgrade costs linked to moving the Council's Data Centre to Picow Farm will be picked up separately. Report 4.2

Who and where

  • Halton Borough Council as funder and estate operator Report P2, 4.1
  • Users of the Picow Farm Road depot Report 4.0, 4.1
  • Liverpool City Region Combined Authority, which submitted the bid and awarded the contractor Report 3.2, 4.1
  • Optimus, the appointed contractor for Picow Farm Report 4.1

Timeline

  • Prior to March 2026: Works at Picow Farm Road must commence to meet the funder's deadline Report 3.5
  • March 2027: Works at Kingsway Learning Centre and Runcorn Town Hall must be completed Report 3.5
  • Within 2-3 years: Existing gas boilers at Picow Farm would otherwise need replacement at around £200,000 Report 4.6
  • Approximately 6 years: Expected time for savings and income to repay the Council's contribution Report 4.5
  • 30 year lifetime of the solar panels: Period over which £559,491 of Solar PV savings and 1,646 tonnes of CO2 savings are estimated Report 4.5

Plain English for the jargon

  • Public Sector Decarbonisation Fund: Government grant scheme for public bodies to fund heat decarbonisation and energy efficiency measures
  • Solar PV: Solar photovoltaic panels that generate electricity from sunlight
  • LED lighting: Light Emitting Diode lighting, a low energy form of electric lighting
  • Air Source Heat Pump: Heating system that extracts heat from outside air to provide heating and hot water
  • District Network Operator: Company that manages the local electricity distribution network
  • Capital Programme: A council's planned spending on long-term assets and infrastructure
  • Match funding: Money the Council must contribute alongside the grant to draw it down
  • Optimus: Contractor appointed by the Combined Authority to deliver the Picow Farm works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item74

Resolved

That Council be requested to include £1,161,300 total estimated cost of the energy efficiency works at Picow Farm Road within the Capital Programme, to be funded by grant funding from the Public Sector Decarbonisation Fund and including a Council contribution of between £162,000 - £200,000.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Council, 4 pages

Purpose of the report

1.1To outline details of grant funded awarded to the Council via the Public Sector Decarbonisation Fund and to seek approval to implement energy efficiency measures at Picow Farm Road.

Recommendation

That Council be asked to include £1,161,300 total estimated cost of the energy efficiency works at Picow Farm Road within the capital programme, to be funded by grant funding from the Public Sector Decarbonisation Fund and including a Council contribution of between £162,000 - £200,000

3.0SUPPORTING INFORMATION

3.1The Public Sector Decarbonisation Scheme provides grants for public sector bodies to fund heat decarbonisation and energy efficiency measures such as solar PV and LED lighting.

3.2During 2025 the Liverpool City Region Combined Authority submitted a bid to Phase 4 of the Fund which included the following buildings in Halton.

 Picow Farm,  Kingsway Learning Centre  Runcorn Town Hall

3.3The Bid was successful with the City Region awarded £30.5m. In respect of Halton a total of £2,816,409.20 was awarded. The overall costs of the works are estimated at £3,200,465 which includes a Council contribution of £448,065.10. Picow Farm £1,161,330 Kingsway Learning Centre £716,150 Runcorn Town Hall £ 1,322,985

3.4To draw down the funds the Council needs to provide total match funding of £448,065.10

3.5The initial focus of work following the bid has been on Picow Farm Road as there is a requirement to commence works prior to March 2026. The work at Kingsway Learning Centre and Runcorn Town Hall will be subject to further design work following a tender process with work needed to be completed by March 2027. These schemes will be subject to a further report when more detailed costing are known.

4.0PICOW FARM ROAD

4.1The Combined Authority had run a tender process and Optimus were appointed as the approved contractor for Picow Farm. Since their appointment they have completed design works at Picow Farm with a view to installing Air Source Heat Pumps, Solar PV, LED Lighting and wall insulation

4.2The total cost of the work is £949,478.68 excluding any District Network Operator costs. None are anticipated for these works but some network improvements will be needed as the Council shifts its Data Centre facility to Picow Farm Road and these costs will be picked up as part of that project. The current estimate of £949,478.68 for the works will likely increase as the contractor will have to provide more temporary welfare accommodation over and above what they have allowed for at Picow Farm but it is anticipated will remain in budget.

4.3The cost of the works are within the overall projected costs of £1,161,300 but the Council would need to make a contribution of between £162,000 and £200,000 towards the costs of the works. 4.4 The works will lead to costs savings from the installation of the Solar PV and LED. The 135kw Solar system would generate savings in the region of £559,491 over the 30 year life time of the panels. It is also estimated that the LED would reduce annual running costs by £10,000 per annum. Whilst the Air Source Heat Pumps will increase the electric load and running costs overall the savings from the Solar PV and LED will provide a net saving per annum.

4.5The savings/income generated would be sufficient to repay the Council’s contribution in approximately 6 years. The estimated carbon saving over the life time of the project is in the region of 1646 tonnes of CO2 emissions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Public Sector Decarbonisation Fund: Picow Farm Road Depot (EXB102 refers)Report 4 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

49 of 61 attended
JA
Councillor John AbbottMember, present
AB
Councillor Angela BallMember, present
SB
Councillor Sandra BakerMember, present
VB
Councillor Victoria BeggMember, present
LB
Councillor Laura BevanMember, present
IB
Councillor Irene BramwellMember, present
CC
Councillor Chris CarlinMember, present
NC
Councillor Neil ConnollyMember, present
MD
Councillor Mark DennettMember, present
SD
Councillor Sian DavidsonMember, present
ED
Councillor Eddie DourleyMember, present
MF
Councillor Mike FryMember, present

All 61 on the meeting page

On this subject at Halton

Search all
  1. Public Sector Decarbonisation Fund - Picow Farm Road Depot (EXB102 refers)This decision
  2. Public Sector Decarbonisation Fund - Picow Farm Road DepotDecided
  3. Public Sector Decarbonisation FundApproved
  4. Public Sector Decarbonisation FundNoted
  5. Halton Borough Council Update on Apprenticeship Policy/Apprenticeship Levy and Public Sector TargetNoted
  6. Halton Borough Council Update on Apprenticeship Policy Apprenticeship Levy & Public Sector TargetNoted

More from Halton Council

All decisions
MeetingDecisionOutcome
20 May 2026 Election of Mayor and Deputy MayorThat Councillor Pamela Wallace be elected Mayor of the Borough for the Municipal Year 2026/27. Moved by Councillor Th... Noted Open
20 May 2026 Municipal Election Results 2026/27That the election results be noted. Noted Open
20 May 2026 Leader and Deputy Leader of the CouncilThat Councillor Mike Wharton be appointed Leader of the Council for the Municipal Year 2026/27 and Councillor Dave Th... Decided Open
20 May 2026 Boards, Committees and PanelsThat the Boards and Committees be constituted with the membership as shown for the Municipal Year 2026/27:- Executive... Decided Open