AI summaryHalton Executive Board notes spending forecast to come in under budget by £1.273m for 2025/26, approves capital programme changes, and asks Council to confirm them.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet spend forecast £1.273m below budget for year
Money£1.273m under budgetForecast outturn underspend, with £29.385m EFS used
What happens nextCouncil to approve capital changesCapital programme revisions to be put to full Council
Who it affectsAll council directoratesPlus High Needs funded pupils and Council reserves
What was decided
Executive Directors are to keep implementing the approved 2025/26 saving proposals set out in Appendix 4. Report P3
Executive Directors are to keep finding further spending reductions or extra income so the council wide forecast outturn stays within budget. Report P4
The report is to be shared with each Policy and Performance Board; full Council is asked to approve the capital programme revisions at paragraph 3.31 and Appendix 5; and the High Needs funded pupil costs position in paragraphs 3.18 to 3.24 and Appendix 3 is noted. Report P5, P6, P7
Why
Net Council spending to 31 January 2026 was £1.236m below budget, with a year end forecast £1.273m under budget and a £2.554m improvement on the November 2025 forecast, reflecting progress in all departments. Report 3.2, 3.4
The 2025/26 budget of £183.052m was set using £29.385m of Exceptional Financial Support, so spending must stay below budget and one off grants used this year may not be available in 2026/27. Report 3.3, 3.9, 3.12
High Needs funded pupil costs are forecast at £42.981m against a budgeted allocation of £29.760m, pushing the projected cumulative Dedicated Schools Grant deficit to £27.690m by 31 March 2026. Report 3.22
What happens next
Full Council is asked to approve revisions to the 2025/26 capital programme covering Stair Lifts, RSL Adaptations, Stadium Minor Works, Halton Leisure Centre, Playground Equipment, Pickerings Pasture Café, Homeless Accommodation Refurbishment, Equality Act Improvement Works, Foundry Lane Residential Area, Town Deal, Pride in Place, Mersey Gateway Crossings Board, and HR Unit 4 Implementation. Report 3.31, P110
A Cipfa led external assurance review has been completed; an action plan is being drawn up and the Council is awaiting details of the SEND Reform Plan from Government ahead of responsibility for High Needs overspends moving to Central Government from 01 April 2028. Report 3.8, 3.19
The money
£1.236m Net spending below budget at 31 January 2026 Report 3.2
£1.273m Forecast outturn underspend for 2025/26 Report 3.2, 4.1
£2.554m Improvement on the November 2025 forecast outturn Report 3.4
£183.052m 2025/26 annual net budget approved 5 March 2025 Report 3.9, 3.12
£29.385m Exceptional Financial Support used to set 2025/26 budget Report 3.3, 3.9
£33.555m Budget growth (22%) added to 2025/26 budget Report 3.12
£7.325m Total agreed savings for 2025/26 Report 3.14
£52.8 million Total capitalisation direction Government was minded to approve on 10 February 2025 Report 3.7
£20.8 million Capitalisation direction element for 2024-25 Report 3.7, P19
£32 million Capitalisation direction element for 2025-26 Report 3.7, P19
£100k Approximate annual cost of every £1m of EFS borrowing over 20 years Report 3.9
£1.096m Forecast interest cost of EFS in 2025/26 Report 3.10
£0.500m Forecast EFS principal repayment in 2025/26 Report 3.10
£14.469m Dedicated Schools Grant deficit at 31 March 2025 Report 3.18
£42.981m Forecast 2025/26 High Needs costs
£29.760m Budgeted High Needs allocation for 2025/26
£27.690m Forecast cumulative DSG deficit at 31 March 2026 Report 3.22
£0.891m Forecast interest cost of DSG deficit in 2025/26 Report 3.23
£5.149m General Reserve at 31 January 2026 (2.81% of net budget) Report 3.27, P104
£54.850m Total earmarked reserves at 31 January 2026 Report P107
£37.802m Capital spending at 31 January 2026 (70% of programme) Report 3.32
£54.320m Total 2025/26 Capital Programme assuming 20% slippage Report 3.32
Options considered
Chosen: Continue implementing approved 2025/26 savings (Appendix 4). To deliver agreed savings and minimise Exceptional Financial Support borrowing Report P3, 3.14, 4.2
Chosen: Directors identify further spending reductions or income. To keep forecast outturn within overall budget Report P4, 4.2
Chosen: Share the report with each Policy and Performance Board. So members have a full picture of the councilwide financial position Report P5
Chosen: Approve revisions to the capital programme (paragraph 3.31 and Appendix 5). Schemes and funding profiles have changed since the original approval Report P6, 3.31, P110
Chosen: Note the forecast position for High Needs funded pupil costs (paragraphs 3.18 to 3.24 and Appendix 3). For awareness, with SEND Reform Plan details awaited from Government Report P7, 3.19, 3.22
Implications
Financial: Every £1m of Exceptional Financial Support borrowing costs the Council about £100k per year over 20 years, so any underspend helps reduce future borrowing and EFS interest of £1.096m and principal of £0.500m in 2025/26. Report 3.9, 3.10
Financial: Capital receipts are expected to be fully exhausted by year end, with a potential £0.651m shortfall to be covered from the revenue budget. Report 3.33
Financial: General Reserve of £5.149m (2.81% of net budget) is at the minimum level and all other earmarked reserves of £54.850m are committed to specific purposes. Report 3.27, 3.30, P104, P107
Risk: A budget risk register of significant financial risks is maintained at Appendix 6 and a Cipfa review of financial resilience and management has been completed with an action plan being drawn up. Report 3.8, 7.1, 7.2
Equalities: The report records no equality and diversity issues arising from the spending position. Report 8.0, 8.1
Climate: The report records no direct climate change implications from this update. Report 9.0, 9.1
Who and where
All Council directorates, especially Adult Social Care, Children and Families, and Education, Inclusion and Provision Report 3.4, P14, P15, P16
Children in care and care leavers, given residential care and Independent Fostering Agency pressures Report P40, P41, P42, P43, P44, P45, P46, P47, P48
Adult social care users including 562 residents in external residential and nursing homes, 771 home care service users, and 620 direct payment recipients Report P58, P65, P67
High Needs pupils with Education, Health and Care Plans, given forecast £42.981m of costs against £29.760m of funding Report 3.21
Council staff, through ongoing agency reduction work and restructures, particularly in Planning and Transportation Report 3.15, P31, P85
Members of each Policy and Performance Board, who are to receive the full report Report P5
Care home residents and families, with 13 enhanced dementia beds planned at St Lukes Report P63
Timeline
10 February 2025: Government issued a letter confirming it was minded to approve a capitalisation direction totalling not exceeding £52.8 million (£20.8m for 2024-25 and £32m for 2025-26) Report 3.7, P19
5 March 2025: Council approved the 2025/26 budget of £183.052m including £29.385m of Exceptional Financial Support Report 3.9, 3.12, 3.31
September 2025: Council commissioned Cipfa to undertake an external assurance review of its financial resilience and management Report 3.8
30 November 2025: Previous revenue spending position was reported; this update shows a £2.554m improvement on that forecast Report 3.2, 3.4
31 January 2026: Revenue spending position date used in this report Report 1.1, 3.1
31 March 2026: Forecast cumulative DSG deficit expected to reach £27.690m Report 3.22
Autumn 2026: New Home to School and College Travel and Transport Policy for Children and Young People with SEND due to be implemented Report P230
31 March 2028: Statutory override allowing the DSG deficit to be carried forward on the balance sheet is due to end Report 3.19
01 April 2028: Responsibility for Dedicated Schools Grant overspends switches from Local Government to Central Government, with up to 90% of High Needs deficits at 31 March 2026 to be funded subject to a SEND Reform Plan Report 3.19
Plain English for the jargon
Exceptional Financial Support (EFS): Government support allowing the Council to borrow or use capital receipts to fund revenue spending, costing roughly £100k per £1m of borrowing each year over 20 years
Dedicated Schools Grant (DSG): Statutory ring fenced grant for schools, with a High Needs block for SEND pupils; the Council has a forecast cumulative deficit of £27.690m by 31 March 2026
High Needs funding: DSG funding for pupils with special educational needs and disabilities, including those with Education, Health and Care Plans
Capitalisation direction: Government permission for a council to treat revenue spending as capital spending, used to support Exceptional Financial Support requests
Cipfa: Chartered Institute of Public Finance and Accountancy, commissioned to review the Council's financial resilience and management
MHCLG: Ministry of Housing, Communities and Local Government, the Government department considering the Council's EFS application
RAG rating: Red, amber, green status used in Appendix 4 to track progress on agreed budget savings
Prevention and Wellbeing Service (PWS): Adult Social Care service using a huddle approach to screen referrals and signpost to community support before commissioned services
Disabled Facility Grant (DFG): Grant used to adapt homes for disabled people, with some Adult Social Care staffing and equipment costs being capitalised against it
Direct Payment (DP): Money paid to a social care user so they can arrange their own support, with 620 service users in Halton
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item104
Resolved
That 1) Executive Directors continue to implement the approved 2025/26 saving proposals as detailed in Appendix 4; 2) Executive Directors continue to identify areas where they can further reduce their directorate’s spending or generate income, in order to ensure the council wide forecast outturn overspend position for the year remains within budget; 3) this report be shared with each Policy and Performance Board in order to ensure they have a full appreciation of the councilwide financial position, in addition to their specific areas of responsibility; 4) Council be asked to approve the revisions to the capital programme set-out in paragraph 3.31 and incorporated within Appendix 5; and 5) the forecast position for High Needs funded pupil costs set-out in Para 3.18 to 3.24 and Appendix 3, be noted.
Word for word from the decision Halton published for this meeting.Source: moderngov.halton.gov.uk
1.1To report the Council’s overall revenue net spend position as at 31 January 2026 together with a 2025/26 forecast outturn position.
2.0RECOMMENDED: That;
(i) Executive Directors continue to implement the approved 2025/26 saving proposals as detailed in Appendix 4;
(ii) Executive Directors continue to identify areas where they can further reduce their directorate’s spending or generate income, in order to ensure the council wide forecast outturn overspend position for the year remains within budget.
(iii) This report be shared with each Policy and Performance Board, in order to ensure they have a full appreciation of the councilwide financial position, in addition to their specific areas of responsibility.
(iv) Council be asked to approve the revisions to the capital programme set-out in paragraph 3.31 and incorporated within Appendix 5;
(v) The forecast position for High Needs funded pupil costs set- out in Para 3.18 to 3.24 and Appendix 3, be noted.
3.0SUPPORTING INFORMATION
Revenue Spending
3.1Appendix 1 presents a summary of spending against the operational revenue budget up to 31 January 2026 (period 10) and Appendix 2 provides detailed figures for each individual Department.
3.2In overall terms, net Council spending as at 31 January 2026 is £1.236m below budget. The outturn forecast for the year estimates that net spending will be below budget by £1.273m based on current assumptions. The position represents a significant improvement on forecasts from earlier in the year. Bringing forecast spend down to now be within the overall budget for the year, is significant positive progress by all Departments.
3.3It should be noted that the 2025/26 budget was set using £29.385m of Exceptional Financial Support (EFS), therefore, it is essential for spending to remain below budget. In addition, to assist with bringing outturn spend within budget, there has been use of one-off grant monies notably within Children’s and Adult Social Care. It will be important to continue to control spending going forward into 2026/27, when these one-off monies may not be available.
3.4The forecast outturn shows an improved position of £2.554m from that reported at the end of November 2025. This improvement can be seen across all directorates, a few notable areas include:
Adult Social Care Directorate – The forecast outturn position for the directorate has improved by £0.499m from that reported as at the end of November 2025. Some of this is due to capitalisation of qualifying staffing and equipment costs against the Disabled Facility Grant (DFG), which might not be possible in future years. There has also been a decrease in Domiciliary and Supported Living costs due to a reduction in numbers and average package costs. This has been supported through the Prevention and Wellbeing Service, whose work has revised the focus upon prevention and wellbeing with improved signposting to community based services.
Children and Families Department – The outturn position for the department has improved by £1.437m since the last reporting period. The Department is now forecasting that net spend for the year will be £1.228m under budget, for the first time in a number of years. Forecast employee costs for the year have reduced by £0.951m, largely due to utilisation of a number of grants. At this stage this approach is considered to be non-recurring, as the grants will be required in future years for other purposes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.