Approved Executive 2 papers

AI summaryHalton Executive Board approved starting statutory consultations and capital spend to expand SEND provision at up to 14 schools, using about £1.2M of government funding, aiming for 178 new places.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConsultation and capital spend agreed for SEND expansion
MoneyCirca £1.2MHigh Needs Provision Capital grant from DfE
What happens nextFurther report to BoardOn outcome of LA-led statutory consultations
Who it affectsHalton SEND pupils and schoolsUp to 178 additional SEND places in borough

What was decided

The Board approved starting the statutory consultation process for schools where the Council is the decision maker, covering new SEND provision detailed in Appendix A. Report P5

The Board approved progressing projects and capital expenditure for schools where no statutory consultation is required. Report P6

The Board approved allocating capital funding to academy schools listed in Appendix A, provided they run their own statutory consultation if needed, and agreed to receive a further report on outcomes of Council-led consultations. Report P7

Why

The Council received about £1.2M from the Department for Education in March 2025 to create or expand places for pupils with high needs. Report 1.2, 3.1

Officers invited expressions of interest from schools in autumn 2025, based on the SEND Sufficiency Strategy; 14 of 18 submissions met priority needs. Report 3.2, 3.3

In-borough provision is intended to cut expensive out-of-borough placements and transport costs, which are paid from the High Needs block of the Dedicated Schools Grant. Report 3.9, 5.3, 4.1

What happens next

Officers will start statutory consultation for maintained schools and progress feasibility for the 14 projects, with capital works value engineered to fit the available budget. Report 3.6, 3.7, 5.2, 5.4

Some new or expanded places are intended to open from September 2026, with the rest by September 2027. Report 5.4, 12.1

A further report will come back to the Board on the outcome of the Council-led statutory consultations. Report P7

The money

  • circa £1.2M Further High Needs Provision Capital Allocation from the Department for Education, notified March 2025 Report 1.2, 3.1
  • circa £1.2M Set aside for capital works proposed in Appendix A Table 1, subject to feasibility and procurement Report 5.4

Options considered

  • Chosen: Approve statutory consultation, progression of projects and capital spend as set out in Appendix A. To deliver the High Needs Provision Capital programme, meet SEND Sufficiency Strategy priorities and reduce out-of-borough costs Report 2.0, 3.3, 10.1, 10.2
  • Rejected: Alternative options. The report records that none were considered Report 11.0, 11.1

Implications

  • Financial: Projects will be funded from the High Needs Provision Capital Allocation grant and value engineered if they exceed available funding; expected to reduce High Needs block spend on out-of-borough placements and transport. Report 5.1, 5.2, 5.3, 5.4
  • Equalities: Schools have duties under the Equality Act 2010 towards disabled children; expansion supports the SEND code of practice 2015 by widening inclusive local provision. Report 8.1, 4.2, P47
  • Climate: New lighting will use LED panels to support the Carbon Management Programme, and more in-borough places are expected to cut fuel use and emissions from travel. Report 6.5, P30, 9.1
  • Legal: Statutory consultation will follow the Making Significant Changes (Prescribed Alterations) to Maintained Schools 2023 guidance and the 2013 Regulations where schools have no existing SEND Resource Base or Unit, or are adding a different category of provision. Report 3.4
  • Risk: Demand for SEND places is rising and current in-borough places are limited; expanding provision addresses that pressure and demonstrates spend against assessed need. Report 7.1, 7.2

Who and where

  • Halton resident pupils with high needs and their families Report 3.7, 3.9, 4.1
  • Mainstream schools in Halton hosting new or expanded SEND Resource Bases or Units (14 schools identified in Appendix A Table 1) Report 3.3, 3.4
  • Academy schools listed in Appendix A, which must run their own statutory consultation if required Report 3.4, P7
  • Council services paying for SEND placements and transport, principally the High Needs block of the Dedicated Schools Grant Report 5.3, 7.1

Timeline

  • 12th December 2024: Executive Board previously approved spend of the balance of High Needs Provision Capital allocations up to 2024/25 (now listed for information in Appendix A Table 2) Report 3.5
  • March 2025: Department for Education notified the Council of a further circa £1.2M High Needs Provision Capital Allocation Report 1.2, 3.1
  • Autumn term 2025: Officers wrote to all schools seeking expressions of interest for new or additional SEND provision Report 3.2
  • 12 March 2026: Executive Board approved the consultation, project progression and capital allocation described in this report
  • From September 2026: First phase of additional SEND provision intended to open Report 5.4, 12.1
  • By September 2027: Remainder of additional SEND provision intended to open Report 5.4, 12.1

Plain English for the jargon

  • High Needs Provision Capital Allocation: Capital grant from the Department for Education used to create or expand places for children and young people with high needs
  • SEND: Special Educational Needs and Disability
  • SEND Sufficiency Strategy: The Council's assessment of where additional specialist places are needed in Halton
  • Resource Base / SEND Unit: Specialist SEND provision attached to a mainstream school; adding a new one or changing category usually triggers a statutory consultation
  • Statutory consultation / prescribed alterations: Formal process under the School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013 and the 2023 statutory guidance, required before significant changes to a maintained school
  • High Needs block of the Dedicated Schools Grant: The schools funding stream that pays for SEND support, including out-of-borough placements
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item106

Resolved

That the Board 1) approves the commencement of the statutory consultation process for those schools where the Local Authority (LA) is designated as the ‘Decision Maker’ (Detailed in Appendix A), with regard to the implementation of new SEND provision; 2) approves the progression of projects and capital expenditure for any school (LA maintained or Academy) where a statutory consultation is not required (detailed in Appendix A); 3) approves the allocation of funding for capital expenditure incurred at those Academy schools detailed in Appendix A providing those schools undertake their own statutory consultation if required; and 4) receives a further report detailing the outcome of any Local Authority led statutory consultations (providing the Board agree at this meeting to commence with those consultations).
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 6 pages

Purpose of the report

1.1The Council has previously received High Needs Provision Capital Allocation funding from the Department for Education to expand its Special Educational Needs and Disability provision in Halton.

1.2In March 2025 the Council received notification from the Department for Education that it would be allocated a further circa £1.2M in High Needs Provision capital funding to support the provision of new places and/or to expand existing provision for pupils and students with high needs at LA maintained and academy schools.

1.3This report seeks the Board’s approval for the proposals made with regard to the continued expansion of special educational needs and disability provision in Halton’s schools.

2.0RECOMMENDED: That

1) the Board approves the commencement of the statutory consultation process for those schools where the Local Authority is designated as the “Decision Maker” (detailed in Appendix A), with regard to the implementation of new SEND provision;

2) the Board approves the progression of projects and capital expenditure for any school (LA maintained or academy) where a statutory consultation is not required (detailed in Appendix A);

3) the Board approves the allocation of funding for capital expenditure incurred at those academy schools detailed in Appendix A providing those schools undertake their own statutory consultation if required, and 4) The Board receives a further report detailing the outcome of any Local Authority led statutory consultations (providing the Board agree at this meeting to commence with those consultations).

3.0SUPPORTING INFORMATION

3.1In March 2025 the Council received notification from the Department for Education that it would be allocated a further circa £1.2M of capital funding (High Needs Provision Capital Allocation) to support the provision of new places or to expand existing provision for pupils and students with high needs.

3.2In the autumn term 2025, officers wrote to all schools to seek expressions of interest from them in offering new or additional SEND provision at their school, based against the required need as set out in the most recent SEND Sufficiency Strategy.

3.3Eighteen Expressions of Interest from schools were received, fourteen were identified for progression as detailed in Appendix A, as those Expressions of Interest met the priority needs identified within the SEND Sufficiency Strategy.

3.4Table 1 in Appendix A details the Expressions of Interest proposed for progression and indicates whether a statutory consultation is/is not required, and also indicates the responsible body required to lead the consultation i.e. the LA for maintained schools or academy trust for academy schools. A statutory consultation is required where a school has no existing SEND Resource Base or SEND Unit, or where there is existing SEND provision, but the Expression of Interest submitted by the school is for a different category of SEND provision than the school currently has.

3.5Table 2 in Appendix A is for information only and details the Expressions of Interest received which will be funded from the balance remaining from previous High Needs Provision Capital allocations up to 2024/25 – this spend has previously been approved by the Executive Board on the 12th December 2024.

3.6This report seeks the Executive Board’s approval to commence a statutory consultation process for those schools that the Local Authority is responsible for (identified within Table 1 in Appendix A) and to approve capital spend for academy schools (subject to statutory consultation if required).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
High Needs Provision Capital Allocation: Proposed Expansion of Special Educational Needs & Disability Provision: Key DecisionDecisions 6 pages DownloadRead as text
PDF
SEND Report Appendix A (002).docxAppendix 3 pages Download

At this meeting

Whole meeting

Who was there

18 of 23 attended
MW
Councillor Mike WhartonChair, present
LB
Councillor Laura BevanMember, present
AB
Councillor Angela BallMember, present
MD
Councillor Mark DennettMember, present
PH
Councillor Phil HarrisMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, present
AW
Councillor Andrea WallMember, present
MW
Councillor Marie WrightMember, present
GC
Gill CookOfficer, present
RM
Rod McGarrigleCouncil Staff, expected

All 23 on the meeting page

On this subject at Halton

Search all
  1. High Needs Provision Capital Allocation – Proposed Expansion of Special Educational Needs & Disability Provision - Key DecisionThis decision
  2. Proposed expansion of Special Educational Needs & Disability Provision – Statutory Consultation Outcome, and Further High Needs Provision Capital Allocation 2026-27 – Key DecisionNoted
  3. DSG Funding - High Needs 2025-26Noted
  4. High Needs Provision Capital Allocations – Proposed Expansion of Special Educational Needs & Disability Provision: Statutory Consultation feedback - Key DecisionApproved
  5. High Needs Provision Capital Allocations – Proposed Expansion of Special Educational Needs & Disability Provision: Statutory Consultation - Key DecisionApproved
  6. DSG High Needs Block 2024-25Noted

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open
22 Oct 2026 Specialist DA Therapeutic Support for Children: Request for Waiver of Standing OrdersThat the Board 1) are advised of the Domestic Abuse Board mapping work of the domestic abuse system and support offer... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies