Halton Borough Council
Executive Board, Thursday 18 June 2026

2026/27 to 2028/29 Capital Programme

Approved Executive 1 paper

AI summaryHalton Borough Council's Executive Board has recommended approval of the updated three year capital programme for 2026/27 to 2028/29, with planned expenditure totalling 150,374.2 in £'000 across the period.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedForward the updated capital programme to full Council for decision
Money150,374.2 (£'000)Total planned capital expenditure across the three years
What happens nextFull Council decisionRecommendation goes to full Council for approval
Who it affectsNot stated

What was decided

The Executive Board recommended that full Council approve the updated capital programme for 2026/27 to 2028/29, including forecast spend and funding as set out in Appendix 1. Report P3

Why

New capital grant allocations have been received and slippage from 2025/26 has been rolled forward into 2026/27, so the programme needs to be brought up to date. Report 1.1

The previous capital programme was approved on 04 March 2026 with the position known to be subject to variation as further grant allocations were confirmed. Report 3.1, 3.2

An external assurance review by Local Partnerships was received on 05 May 2026 and its recommendations are being addressed by the Management Team. Report 3.4, 3.5

What happens next

The recommendation will be considered by full Council for approval. Report P3

The capital programme will be monitored and reported on a regular basis throughout the year, with any revisions brought back to Council for approval. Report 3.3, 3.6

The Council will continue to seek additional external funding, for example through Section 106 agreements, to reduce the ongoing revenue implications of borrowing. Report 3.10

The money

  • 150,374.2 Total planned capital programme expenditure across 2026/27 to 2028/29, as shown in the £'000 column of Appendix 1 Report P48
  • 81,562.4 Planned capital expenditure in 2026/27, in £'000 Report P48
  • 35,884.2 Planned capital expenditure in 2027/28, in £'000 Report P48
  • 32,927.6 Planned capital expenditure in 2028/29, in £'000 Report P48
  • 34,508.3 Borrowing funding across the three year programme, in £'000 Report P48
  • 114,151.9 Grants and external funding across the three year programme, in £'000 Report P48
  • £34.5m Share of total capital expenditure funded from future and existing borrowings, described in the report as around 23% of the programme Report 7.3
  • £1.150m Forecast increased annual revenue cost linked to borrowing in each of 2026/27, 2027/28 and 2028/29 Report 3.7, P14

Implications

  • Financial: Borrowing of 34,508.3 in £'000 funds part of the three year programme, and forecast revenue costs of £1.150m a year are linked to that borrowing over the same period. Report P48, 3.7, P14
  • Risk: Slippage on the capital programme could increase scheme costs and add revenue costs, and many grants carry conditions and clawback risk if outcomes are missed. Report 7.1, 7.2
  • Risk: There is a cashflow risk on schemes funded from future capital receipts, and any new borrowing needs a clear plan for repaying principal and interest. Report 7.3, 7.4
  • Legal: Borrowings to support the capital programme are taken in line with the Prudential Code and the Council's Treasury Management Strategy. Report 3.9
  • Other: Recommendations from the external assurance review received on 05 May 2026 are being addressed by the Management Team. Report 3.4, 3.5

Who and where

  • Children's services, including schools capital repairs, SEND provision, asbestos management, access initiatives, basic needs projects and family hubs Report P43
  • Adults needing disabled facilities grants, stair lifts, housing association adaptations and care home provision across the named homes Report P43
  • Environment and regeneration schemes covering community green space, parks, the stadium, crematoria, homelessness accommodation, CCTV and litter bins Report P44
  • Town centre and economic regeneration projects including Town Deal, Sci tech Daresbury, Astmoor Masterplan, Widnes Town Centre, Pride in Place and Picow Farm Depot Report P45
  • Transport and street lighting schemes including active travel, fleet replacement, road reconstruction and major projects such as Transport for City Regions infrastructure and Mersey Gateway land Report P46
  • Public Protection through the new database for regulatory services and the Council's own IT and Halton Smart Microgrid schemes Report P44, P47

Timeline

  • 04 March 2026: Council approved the 2026/27 Capital Strategy and the overall capital programme for 2026/27 to 2028/29 Report 1.1, 3.1, 3.2
  • Early 2026: The Council asked Local Partnerships via the LGA to undertake an external assurance review of the capital programme Report 3.4
  • 16 April 2026: Transport Infrastructure Updates were reported to the Executive Board and are incorporated into Appendix 1 Report P49
  • 05 May 2026: The final external assurance review report was received Report 3.4
  • 18 June 2026: Executive Board considers the updated capital programme and recommends approval to full Council Report P3

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government, which funded the LGA Sector led Improvement Programme that paid for the external assurance review
  • LGA: Local Government Association, which commissioned Local Partnerships to carry out the external assurance review
  • Prudential Code: The framework that sets out how local authorities should ensure borrowing is affordable, prudent and sustainable
  • Section 106 agreement: A planning obligation under which a developer contributes to infrastructure or services, which can be used to fund capital schemes
  • Minimum Revenue Provision: The amount the Council sets aside each year from revenue to repay the principal of capital borrowing
  • RSL: Registered Social Landlord, the housing association providers working with the Council on joint funded adaptations
  • CPO: Compulsory Purchase Order, the power being used to acquire land for the Sci tech Daresbury project
  • SEND: Special Educational Needs and Disabilities, the basis for the dedicated capital allocation in the Children's Directorate
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

That the Council be recommended to approve the updated capital programme for 2026/27 to 2028/29, including forecast spend and funding, as set out in Appendix 1.
Word for word from the decision Halton published for this meeting. Source: moderngov.halton.gov.uk

Follow this further

Built from Halton's papers

What the report saysPro

Report to Executive Board, 11 pages

Purpose of report

1.1Council approved an updated capital programme for 2026/27 on 04 March 2026. Since then a number of new capital grant allocations have been received and slippage to capital projects for 2025/26 has been rolled forward to 2026/27. The purpose of this report is to bring all the separate elements together and report on the Council’s total forecast capital programme expenditure and associated funding over the next three years.

2.0RECOMMENDED: That:

(i) Council be recommended to approve the updated capital programme for 2026/27 to 2028/29, including forecast spend and funding, as set out in Appendix 1.

3.0SUPPORTING INFORMATION

3.1The 2026/27 Capital Strategy was approved by Council on 04 March 2026. The document summarised the expected capital spend and financing over the medium term.

3.2The overall capital programme for 2026/27 to 2028/29 was approved by Council on 04 March 2026. Estimates of capital allocations at that time were known to be subject to variations. This report updates the latest position, which includes confirmed and indicative capital grant allocations for 2026/27 and future years.

3.3The capital programme is subject to regular review and monitoring reports are presented on a bi-monthly basis. Information is presented to show the actual spend incurred to date and how this compares to the capital allocation for the year. A forecast is provided to indicate if the capital programme will be utilised in full during the year or if there is any expected slippage to capital schemes. Capital Programme Assurance Review

3.4In early 2026 the Council asked Local Partnerships LLB (via the LGA) to undertake an external assurance review, to consider the delivery and management of the Council’s Capital Programme. This review was undertaken as part of the LGA’s Sector-led Improvement Programme funded by MHCLG, and the final report was received on 05 May 2026.

3.5The report included a number of recommendations which are currently being addressed by Management Team.

Planned Capital Programme Expenditure

3.6Appendix 1 presents the planned Capital Programme for the three year period commencing 2026/27 based on current information for approved schemes, funding available and slippage of scheme expenditure from 2025/26. The capital programme is subject to continuous change as new resources and projects are identified, and will be updated throughout the year as revisions are approved by Council.

Revenue Implications

3.7There is a revenue cost associated with financing of the capital programme. This is largely where the Council approves funding of a capital scheme through external borrowing. There will be two elements relating to revenue, the first being repayment of the principal borrowing (known as Minimum Revenue Provision) and the second being the interest cost linked to borrowing. It is forecast that the increased revenue costs linked to borrowing over the three year term of this report will be:

2026/27 - £1.150m 2027/28 - £1.150m 2028/29 - £1.150m

3.8In addition to above, there will be cashflow costs where grant or contributions are not received in advance. It is difficult to forecast these costs in advance but to minimise it, it is important that claims related to grant funding and raising of invoices are done promptly.

3.9Borrowings undertaken to support the capital programme are undertaken in line with the Prudential Code and Council’s Treasury Management Strategy. This ensures that external borrowings are affordable and within prudent and sustainable levels.

3.10The Council will continue to seek and secure further additional external resources to reduce on-going revenue implications and enhance the capital programme. For example, through Section 106 agreements. Capital Receipts

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026/27 to 2028/29 Capital ProgrammeReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
MW
Councillor Mike WhartonChair, present
AB
Councillor Angela BallMember, present
ED
Councillor Eddie DourleyMember, present
RL
Councillor Rosie LeckMember, present
TM
Councillor Tom McInerneyMember, present
PN
Councillor Paul NolanMember, present
DT
Councillor Dave ThompsonMember, present
AW
Councillor Andrea WallMember, present
MR
Mark ReaneyOfficer, expected
ED
Ed DawsonOfficer, expected
TG
Tim GibbsOfficer, expected
ZF
Zoe FearonOfficer, expected

All 13 on the meeting page

On this subject at Halton

Search all
  1. 2026/27 to 2028/29 Capital ProgrammeThis decision
  2. Schools Capital Programme – 2026/27 - Key DecisionNoted
  3. Capital Programme – 2025/26 - Key DecisionNoted
  4. 2024/25 to 2026/27 Capital Programme - EXB17Approved
  5. 2024/25 to 2026/27 Capital ProgrammeApproved
  6. ICT Rolling Capital ProgrammeNoted

More from Halton Executive Board

All decisions
MeetingDecisionOutcome
22 Oct 2026 Halton Housing Trust Annual ReportThe Board thanked Halton Housing for the presentation and noted the report. Noted Open
22 Oct 2026 Highway Asset Management Plan (HAMP)That 1) approves the Highway Asset Management Plan (HAMP) 2026-2029 (contained in Appendix A) for adoption and public... Approved Open
22 Oct 2026 Waste Management and Recycling Contract - Key DecisionThat 1) Members approve the continued delegation of defined elements of the Council’s Waste Disposal Authority functi... Approved Open
22 Oct 2026 Waste Strategy and Household Waste Collection PolicyThat 1) Members approve the draft Waste Management Strategy and the draft Household Waste & Recycling Collection Poli... Approved Open
22 Oct 2026 Specialist DA Therapeutic Support for Children: Request for Waiver of Standing OrdersThat the Board 1) are advised of the Domestic Abuse Board mapping work of the domestic abuse system and support offer... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies