Resolved
that the out-turn Quarter Three 2011-2012 revenue and capital budgets be noted.
Overview & Scrutiny Board noted this item on Wednesday 25 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
that the out-turn Quarter Three 2011-2012 revenue and capital budgets be noted.
London Borough of Hammersmith & Fulham
OVERVIEW AND SCRUTINY BOARD DATE TITLE Wards
25 April 2012 HIGH LEVEL REVENUE AND CAPITAL ALL BUDGET MONITORING REPORT 2011-12 QUARTER THREE
SYNOPSIS
The report sets out the forecast outturn position for 2011-12 revenue and capital budgets as at Quarter 3 and explains significant variances.
CONTRIBUTORS RECOMMENDATION(S):
All Departments To note and comment on the projected outturn position.
CONTACT NEXT STEPS Jane West Director of Finance & The Overview and Scrutiny Board will continue Corporate Services, to monitor the forecast outturn position revenue Hammersmith Town and capital budgets at each quarter. Hall.
Tel: 020 8753 1900 1. EXECUTIVE SUMMARY
1.1This report gives details of the projected revenue and capital outturn position for 2011/12 as at the end of December 2011 (Quarter 3).
1.2The General Fund Revenue Account is projected to underspend by £6.779m resulting in an increase in the General Fund balance to £22.847m (on the assumption the underspend is not applied elsewhere).
1.3The Housing Revenue Account (HRA) is projected to overspend by £0.371m. There has also been a one off transfer of balances to the HRA from Hammersmith & Fulham Homes of £1.868m. In total the HRA balances are forecast to increase to £4.696m
1.4The Council debt (Capital Finance Requirement – CFR) position is forecast to reduce to £77.7m by 2015/16. The closing CFR for 2011/12 at quarter 3 is forecast to be £111.5m.
1.5The General Fund capital programme is forecasting a surplus in resources of £7.2m in 2011/12 at quarter 3. The Decent Neighbourhoods capital programme is forecasting a surplus of £10.4m in 2011/12 at quarter 3. The Housing Revenue Account (HRA) capital programme is reporting a balanced position for 2011/12 at quarter 3 - dependent on the risk of the achievement of £4.6m of leaseholder contributions and dependent upon the re-phasing of capital expenditure of £313K into future years.
2. INTRODUCTION
2.1The report provides an update on the revenue and capital financial position and highlights significant budget variances.
3. FORECAST REVENUE OUTTURN 2011/12 – GENERAL FUND
3.1The projected revenue outturn for 2011/12 at the end of quarter 3 is an underspend of £6.779m, analysed by Department in Table 1. Figures in brackets denote underspends or income in excess of the Budget. Table 1: 2011/12 General Fund Forecast Outturn – Departmental Analysis
Revised Forecast Forecast Budget at Year End Year End Quarter 3 Variance Variance Departmental Budgets at Quarter 3 at Quarter 2 £000s £000s £000s Children’s Services 61,732 0 398 Unaccompanied Asylum 1,300 0 223 Seeking Children Community Services 79,075 (2,019) (1,625) Transport and Technical 20,986 273 206 Services Finance and Corporate 15,983 (370) (315) Services Environment, Leisure and 36,296 (283) 0 Residents Services Housing & Regeneration 10,144 (550) (518) Centrally Managed Budgets 3,169 (1,129) (515) Controlled Parking Account (16,023) (2,701) (2,306) Net Operating Expenditure 212,662 (6,779)* (4,452)
*note numbers in brackets represent underspends.
3.2Table 2 shows the impact of the £6.779m underspend assuming the resources are not applied elsewhere. Cabinet will consider if some of the underspend should be earmarked to meet future financial pressures as part of the month 10 Corporate Revenue Monitor Report.
Table 2: The General Fund Balance as at 31 March 2012 £m Balance as at 31 March 2011 (16.068) Plus: Projected underspend (6.779) Projected Balances as at 31 March 2012 (22.847)
3.3An explanation of the major budget variances for each department is set out in Appendix 1.
4. 2011/12 – HOUSING REVENUE ACCOUNT FORECAST OUTTURN
4.1The Housing Revenue Account is forecast to overspend by £0.371m as at Quarter 3. The HRA is benefiting from a £1.848m transfer of balances from Hammersmith & Fulham Homes following the transfer of the Housing Management function back to the council. An explanation of the major variances is provided in Appendix 2.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
High Level Revenue and Capital Budget Monitoring Report 2011-2012Report | 119 KB | DownloadRead as text |
PDF |
Scrutiny Qtr3 Capital: Appendices 3 to 6Report | 92 KB | Download |
PDF |
Scrutiny Quarter 3 Revenue Appendix 1Appendix | 71 KB | Download |
PDF |
Scrutiny Quarter 3 Revenue Appendix 2Appendix | 43 KB | Download |
Follow Overview & Scrutiny Board at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Apr 2014 | Update on the tri-borough ICT programmeRESOLVED – That the Board note the progress made delivering a tri-borough IT programme. | Noted | Open |
| 8 Apr 2014 | High level revenue budget monitoring quarter 3 report 2013-14RESOLVED – That the Board note the forecast General Fund underspend of £7.66m and the forecast HRA underspend of £0.3... | Noted | Open |
| 8 Apr 2014 | High Level Capital Budget Monitoring Report, 2013/14 Quarter 3RESOLVED – That the report be noted. | Noted | Open |
| 8 Apr 2014 | The Business Rates Scrutiny Task Group: Final ReportIt was agreed that the wording of the recommendation should be revised to replace ‘town centres’ with ‘shopping areas... | Agreed | Open |
| 8 Apr 2014 | Select Committee ReportsRESOLVED – That the reports be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.