Resolved
that the revenue budget outturn position for the 2011/12 revenue budget be noted.
Overview & Scrutiny Board noted this item on Tuesday 24 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
that the revenue budget outturn position for the 2011/12 revenue budget be noted.
London Borough of Hammersmith & Fulham
OVERVIEW AND SCRUTINY BOARD DATE TITLE Wards
24th July, 2012 HIGH LEVEL REVENUE BUDGET ALL MONITORING OUTTURN REPORT 2011-12
SYNOPSIS
The report sets out the outturn position for 2011- 12 revenue budgets and explains significant variances.
CONTRIBUTORS RECOMMENDATION(S):
All Departments To note and comment on the projected outturn position.
CONTACT NEXT STEPS Jane West Director of Finance & The High Level Revenue Budget will continue to Corporate Services, be monitored by the Overview and Scrutiny Hammersmith Town Board throughout the year on a quarterly basis. Hall. Tel: 020 8753 1900 1. PURPOSE OF REPORT
1.1This report sets out: • The revenue outturn position for 2011/12. • Significant variances. • The level of reserves and balances at the year end.
All figures are subject to both audit and Member approval.
2. REVENUE OUTTURN – GENERAL FUND
2.1The accounts for 2011-12 have been completed, with a final version of the Statement of Accounts, signed by the Executive Director Of Finance and Corporate Governance, submitted to the external auditors by the statutory deadline of 30 June. Following external audit, the accounts must be signed off by 30 September 2012 by the Audit Committee.
2.2The revenue outturn for 2011/12 shows an underspend of £6.9m after departmental carry forwards of £3.4m. This represents 1% of the gross budget. The details are summarised in Table 1 and expanded on in Appendix 1.
Table 1: General Fund Outturn 2011/12
Department Revised Actual Variance Budget
£m £m £m Children’s Services 67.2 67.1 (0.1) Unaccompanied Asylum Seeking Children 1.3 1.3 0.0 Adult Social Care 79.2 78.5 (0.7) Transport and Technical Services 19.8 20.0 0.2 Finance and Corporate Services 18.6 18.3 (0.3) Environment, Leisure & Residents Services 38.3 38.3 (0.0) Housing & Regeneration 8.7 7.4 (1.3) Centrally Managed Budgets (13.9) (16.1) (2.2) Controlled Parking Account (17.0) (19.5) (2.5) Net Operating Expenditure 202.2 195.3 (6.9) Proposed Transfers to Reserves Efficiency Reserve 2.5 IT Infrastructure Reserve 1.9 Capital Items Reserve 0.4 White City Neighbourhood Reserve 0.7 Net contribution to General Fund 1.4 Balance Total Contribution to Reserves and 6.9 Balances * Numbers in brackets represent underspends 3. RESERVES, BALANCES AND PROVISIONS
3.1The favourable revenue outturn has allowed the Council to make year end transfers to general balances and earmarked reserves of £6.9m (this is in addition to the previously approved carry forward of planned underspends of £3.4m).
3.2The proposed net contribution to General Fund Balances of £1.4m will increase the balances brought forward to 2012/13 to £17.5m. The latest assessment of the financial risks and challenges facing the Council is £24.4m in 2013/14 rising to £43.9m in 2015/16. The increase in balances will help mitigate against such risk. As a proportion of gross budget expenditure balances have increased to 2.6%. Earmarked reserves are projected to be £52.2m at the close of 2011/12.
4 2011/12 OUTTURN – HOUSING REVENUE ACCOUNT (HRA)
4.1The HRA came in virtually on budget for the year (appendix 2). Additionally £1.9m was received in the HRA from H&F Homes Ltd as a result of the successful return of the management of the Councils Housing Stock to the Council and close performance management of the closure process during 2011/12. This is illustrated in the table 3 below:
Table 3: The Housing Revenue Account Balance as at 31 March 2012
£m Balance as at 31 March 2011 (3.1) Plus; successful HFH Balance Transfer (1.9) Plus; other net movements 0 Projected Balance as at 31 March 2012 (5.0) APPENDIX 1:
DEPARTMENTAL ANALYSIS - BUDGET REVENUE MONITORING 2011-12 OUTTURN
CHIDRENS SERVICES DEPARTMENT
Variance Analysis by Departmental Division
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
High Level Revenue Budget Monitoring Out-turn Report 2011: 2012Report | 103 KB | DownloadRead as text |
Follow Overview & Scrutiny Board at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Apr 2014 | Update on the tri-borough ICT programmeRESOLVED – That the Board note the progress made delivering a tri-borough IT programme. | Noted | Open |
| 8 Apr 2014 | High level revenue budget monitoring quarter 3 report 2013-14RESOLVED – That the Board note the forecast General Fund underspend of £7.66m and the forecast HRA underspend of £0.3... | Noted | Open |
| 8 Apr 2014 | High Level Capital Budget Monitoring Report, 2013/14 Quarter 3RESOLVED – That the report be noted. | Noted | Open |
| 8 Apr 2014 | The Business Rates Scrutiny Task Group: Final ReportIt was agreed that the wording of the recommendation should be revised to replace ‘town centres’ with ‘shopping areas... | Agreed | Open |
| 8 Apr 2014 | Select Committee ReportsRESOLVED – That the reports be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.