Decision made by Cabinet Member on: 14 January 2013 1. That approval is given to proceed to a procurement and place OJEU contract notices for the Queensmill new-build project, and the Holy Cross expansion and co-location with the French Lysee /Bi-lingual at Clancarty Road 2. That approval is given to delegate authority to the Executive Director of Children’s Services to select a shortlist of contractors from Pre-Qualification Questionnaires as recommended by a Tender Appraisal Panel consisting of officers from Children’s Services, Corporate Procurement, Legal Services, and Corporate Finance.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1This report seeks approval to proceed to a procurement and place OJEU contract notices for the Queensmill new-build project, and the Holy Cross expansion and co-location with the French Lysee/Bi-lingual at Clancarty Road
Recommendations
2.1That approval is given to proceed to a procurement and place OJEU contract notices for the Queensmill new-build project, and the Holy Cross expansion and co-location with the French Lysee/Bi-lingual at Clancarty Road 2.2 That approval is given to delegate authority to the Executive Director of Childrens Services to select a shortlist of contractors from Pre- Qualification Questionnaires as recommended by a Tender Appraisal Panel consisting of officers from Childrens Services, Corporate Procurement, Legal Services, and Corporate Finance.
Reasons for decision
3.1This recommendation will enable the procurement to proceed in a timely fashion to meet programme requirements.
3.2The anticipated programme for each project is as follows:
Project Queensmill Holy Cross Cabinet Member’s Decision 7th Dec 2012 7th Dec 2012
Issue Pre-Qualification Questionnaire 10th Dec 2012 10thDec 2012
Appoint Contractor 15th June 2013 15th May2013 Start on Site: 10th July 2013 15th June 2013
Completion: 30th July 2014 30thJuly 2015
4. INTRODUCTION AND BACKGROUND
4.1The School Organisation Strategy Report 2012/13, approved by Cabinet 30th January 2012 gave approval to progress the Queensmill and Holy Cross projects up to tender stage within an approved cash envelope.
4.2In order to progress these projects within the project programme it is now necessary to procure a suitably experienced contractor for the construction phase for each project.
4.3Each of these two projects will be the subject of a separate and distinct procurement, and will be the subject of two separate contracts.
4.4The Queensmill New-Build project comprises of the construction of fit for purpose accommodation for an all through school for 120 ASD pupils with integrated respite accommodation. The pre-tender estimate for this project is within the project budget of £11m approved by Cabinet in March 2011.
4.5The Holy Cross expansion and co-location project comprises extensive remodelling of the Grade 2 listed former Peterborough Primary School building, with a new build Hall and Kitchen extension. The new accomodation will accommodate up to 900 pupils. The pre-tender estimate for this project is within the project budget of £6.5m approved by Cabinet in March 2011.
4.6Listed building consent and planning approval has been granted for both projects
5. PROPOSAL AND ISSUES
5.1It is proposed that the selection of the main contractor will be undertaken via the restricted OJEU process. The relative advantages and disadvantages of selecting the main contractor via the restricted OJEU process following are summarised below:
5.1.1 Advantages
• Enable the Council to tender to a wide base of contractors • Creates significant competition between contractors; • Enables the Council to shortlist selected contractors based upon a bespoke and relevant evaluation criteria at the pre-qualification stage; • Maximises the opportunity of recruiting a contractor with expertise relevant to the project, e.g. delivering SEN educational facilities; • This procurement route can be utilised without compromising the anticipated operational date for either project.
5.1.2 Disadvantages
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bishops Park Public Toilet ImprovementsDecision Taken by Cabinet Member on 24 June 2016: That Amey be instructed to carry out these works. It is also recomm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.