RESOLVED THAT: That application 2020/0112/FUL be refused for the reasons set out above.
Planning and Development Control Committee refused this item on Wednesday 5 May 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: That application 2020/0112/FUL be refused for the reasons set out above.
-------------------------------------------------------------------------------------------------------------------- Ward: North End
Site Address: 32A Vereker Road London W14 9JS
© Crown Copyright. All Rights Reserved. London Borough Hammersmith and Fulham LA100019223 (2013). For identification purposes only - do not scale.
Reg. No: Case Officer: 2020/01112/FUL Graham Simpson
Date Valid: Conservation Area: 04.05.2020 Constraint Name: Baron's Court Conservation Area - Number 27 Committee Date: 05.05.2021 Description: Replacement of existing roof; Insertion of No. 8 skylights on flat section of the replaced roof, excavation of the basement to provide accommodation at lower ground floor in connection with an existing residential unit. Repairs to the brickwork, parapet and doorway portico and replacement of the existing window with double glazing and replacement of front door to Fairholme Road.
Drg. Nos: GA03; GA 04; GA 05; EL 02; EL 03; EL 04 Rear elevation; SC 02; DET 01 (All dated 2 June 2020)
Application type: Full Detailed Planning Application
Officer Recommendation: That the application be approved subject to the condition(s) set out below
1) The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2) The development hereby permitted shall be built in complete accordance with the submitted drawings: GA03; GA 04; GA 05; EL 02; EL 03; EL 04 Rear elevation; SC 02; DET 01 (All dated 2 June 2020)
In order to ensure full compliance with the planning permission hereby approved and to prevent harm arising through deviations from the approved plans, in accordance with Policies DC1, DC4 and DC8 of the Local Plan (2018).
3) A detailed structural engineer's report and method statement bespoke to the site for the development hereby approved, including details of any temporary works required to facilitate the excavation and construction works, the proposed means of protection of the structure of the retained elements of the existing building during excavation and construction works, and confirmation that there will be no damage to the structure of the elements of the existing building to be retained as a result of the excavation and construction works, shall be submitted to and approved in writing by the Council prior to the commencement of development. The works shall be carried out in accordance with the approved details.
In order to protect the structure of the building and to safeguard the special architectural or historic interest of the Barons Court Conservation Area in accordance with policy DC1 and DC8 of the Local Plan (2018). 4) Prior to commencement of the development hereby approved, a Construction Logistics Plan (in compliance with TfL Construction Logistics Plan Guidance) and a Construction Management Plan shall be submitted to and approved in writing by the Council. Details shall include control measures for dust, noise, vibration, lighting, delivery locations, restriction of hours of work and all associated activities audible beyond the site boundary to 0800-1800hrs Mondays to Fridays and 0800-1300hrs on Saturdays, advance notification to neighbours and other interested parties of proposed works and public display of contact details including accessible phone contact to persons responsible for the site works for the duration of the works. The details shall also include the numbers, size and routes of demolition and construction vehicles, provisions within the site to ensure that all vehicles associated with the construction works are properly washed and cleaned to prevent the passage of mud and dirt onto the highway, and other matters relating to traffic management to be agreed. Approved details shall be implemented throughout the project period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
32A Vereker Road, London, W14 9JS, North End, 2020/01112/FULReport | 317 KB | DownloadRead as text |
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Unit 1b, Waterside Tower, The Boulevard, London, SW6 2UB, Sands End, P/2026/01012/FULRESOLVED That the Director of Planning and Property be authorised to grant planning permission subject to the conditi... | Decided | Open |
| 15 Sep 2026 | 40 Barclay Road, London, Hammersmith and Fulham, SW6 1EH, Walham Green, P/2026/01137/FULRESOLVED That the Director of Planning and Property be authorised to grant planning permission subject to the conditi... | Decided | Open |
| 15 Sep 2026 | Land North of Westfield London Shopping Centre, Ariel Way, London W12, Shepherd's Bush Green, 2025/03376/VARRESOLVED That subject to there being no contrary direction from the Mayor of London, the Director of Planning and Pro... | Agreed | Open |
| 15 Sep 2026 | Land At Albert Wharf and Swedish Wharf, Wandsworth Bridge Road, London SW6 2TY, Sands End, 2025/02448/VARRESOLVED That subject to there being no contrary direction from the Mayor for London, that the Director of Planning a... | Agreed | Open |
| 15 Sep 2026 | 1 - 3 Sussex Place, London, W6 9EA, Hammersmith Broadway, P/2026/00633/FULRESOLVED That subject to there being no contrary direction from the Mayor for London, that the Director of Planning a... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.