1 Spring Vale Terrace, London W14 0AE, Brook Green, 2025/01812/FUL
AgreedPlanning1 paper
AI summaryHammersersmith and Fulham's Planning Committee authorised its Director of Planning to grant permission for 18 new homes at 1 Spring Vale Terrace, Brook Green, subject to a legal agreement and 50 conditions.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to legal agreement and conditions
MoneyNot stated
What happens nextComplete legal agreementThen issue planning permission
Who it affects1 Spring Vale TerraceBrook Green ward, conservation area
What was decided
The Committee resolved to authorise the Director of Planning and Property to grant planning permission once a satisfactory legal agreement is completed and subject to the conditions listed in the report. Report P9
The Director is also authorised, after consulting the Assistant Director of Legal Services and the Committee Chair, to make minor changes to the legal agreement or to the conditions. Report P10
Why
Officers considered the loss of employment floorspace justified, and the scheme would add to the borough's market and affordable housing stock, with all 9 flats (50% of units) to be affordable, split 67% social rent and 33% London Living Rent. Report P104, 2.4
The design was found acceptable and not harmful to the Lakeside/Sinclair/Blythe Road Conservation Area, and subject to conditions the scheme would not harm neighbouring residents' amenities. Report P104, 1.2
Highways, transport, energy, sustainability, flood risk, air quality, land contamination, and ecology matters were addressed through conditions and the legal agreement. Report P104
What happens next
A satisfactory legal agreement must be completed before the planning permission is issued. Report P9
A total of 50 planning conditions must be complied with, including pre-commencement requirements on construction management, materials, drainage, air quality, contamination, and accessibility. Report P11, P18, P21, P23, P29, P35, P66, P71
Options considered
Chosen: Grant planning permission subject to a legal agreement and conditions. Officer recommendation; scheme found acceptable on land use, design, heritage, neighbour amenity, and technical matters Report P8, P9, P104
Implications
Legal: Permission is dependent on a satisfactory legal agreement covering affordable housing and other obligations. Report P9, 2.4
Equalities: 10% of dwellings (House 6 and Flat 4) must be built to wheelchair accessible standard M4(3), with the remaining 90% to accessible and adaptable standard M4(2). Report P35
Climate: Conditions require Air Source Heat Pumps or similar electrical heating, solar panels, a private energy microgrid for the flats, electric vehicle charging, and waste water heat recovery. Report P16, P29, P70, P95, P98, P100, P101
Risk: A staged land contamination investigation is required before development begins, given potentially contaminative past uses near the site. Report P71, P73, P75, P76, P78, P79
Other: The site lies within Flood Zone 3, so the development must follow the approved Flood Risk Assessment, with surface water discharge limited to 2 litres per second. Report 1.4, P66, P68
Other: A Secured by Design statement and Secured by Design accreditation are required to address crime prevention. Report P45, 3.8
Who and where
Future residents of the 18 new homes, comprising 9 townhouses and 9 flats Report P6, 2.1
Occupants of surrounding properties in Brook Green, including 29 objectors and 4 supporters who wrote to the council Report 3.1, 3.2
Businesses in Berghem Mews, including Monkey Puzzle Day Nursery at 17 Spring Vale Terrace Report 1.2
The Lakeside/Sinclair/Blythe Road Conservation Area Report 1.2, P5
Timeline
3rd July 2025: Application form received Report P107
10.02.2026: Planning and Development Control Committee decision Report P5
Plain English for the jargon
Class C3: Use class for single dwellinghouses (residential homes)
Class C4: Use class for houses in multiple occupation
Class E(g): Use class covering offices, research, and light industry
Class B8: Use class for storage and distribution
SuDS: Sustainable Drainage System, used to manage surface water runoff
PTAL: Public Transport Accessibility Level, a 0 to 6 score used by Transport for London
Secured by Design: A police crime prevention accreditation scheme for new buildings
AQDMP: Air Quality Dust Management Plan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
RESOLVED That the Director of Planning and Property be authorised to grant planning permission upon the completion of a satisfactory legal agreement and subject to the conditions listed in the report and changes made in the addendum. That the Director of Planning and Property, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal agreement or proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Date Valid: Conservation Area: 14.08.2025 Constraint Name: Lakeside/Sinclair/Blythe Road Conservation Area - Number 36 Committee Date: 10.02.2026 Applicant: Numa Capital Limited 30 St George's Street London United Kingdom
Description: Demolition of existing building (Class E(g) and Class B8) and erection of 18no residential units (Class C3), comprising a terrace of 6no part-three and part-four storey townhouses with roof terraces, a terrace of 3no three-storey townhouses, together with a four-storey building to provide 9no self-contained flats with roof terraces; installation of solar panels at roof level, associated plant, landscaping, refuse and cycle storage, and formation of 5 off-street car parking spaces together with other associated works. Drg Nos: Refer to condition 2.
Application Type: Full Detailed Planning Application
Officer Recommendation:
1) That the Committee resolve that the Director of Planning and Property be authorised to grant planning permission upon the completion of a satisfactory legal agreement and subject to the conditions listed below.
2) That the Committee resolve that the Director of Planning and Property, after consultation with the Assistant Director of Legal Services and the Chair of the Planning and Development Control Committee be authorised to make any minor changes to the proposed Heads of Terms of the legal agreement or proposed conditions, which may include the variation, addition or deletion of conditions, any such changes shall be within their discretion.
Conditions:
1) The development hereby permitted shall not commence later than the expiration of 3 years beginning with the date of this planning permission.
Condition required to be imposed by section 91(1)(a) of the Town and Country Planning Act 1990 (as amended by section 51 of the Planning and Compulsory Purchase Act 2004).
2) The development shall be carried out and completed in accordance with the following approved drawings: The development shall be carried out and completed in accordance with the following approved drawings:
+ Approved documents: o Fire Statement, Rev P03, dated 10/06/2025, prepared by Elev8 Fire Engineering Ltd. o Flood Risk Assessment, ref. P452012-WW-XX-XX-RP-C-0001, Rev. P2, prepared by Whitby Wood o Energy and Sustainability Statement, Version 01, dated June 2025, prepared by Love Design Studio
In order to ensure full compliance with the planning application hereby approved and to prevent harm arising through deviations from the approved plans, in accordance with Policies DC1, DC4, and DC8 of the Local Plan (2018).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Control Committee at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.