TfL Hammersmith Road Permanent Cycleway 9 (C9)

Approved Executive 3 papers

AI summaryCabinet backs TfL's £20m Permanent Cycleway 9 on Hammersmith Road, agrees to enter a Section 8 Agreement and seeks no new Council capital spending.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSupport TfL scheme and Section 8 Agreement
Moneyapproximately £20mTfL investment, no Council capital sought
What happens nextFinalise legal agreementComplete Section 8 Agreement and statutory processes
Who it affectsThree Hammersmith wardsHammersmith Broadway, Avonmore, Brook Green

What was decided

The Cabinet agreed to support implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to completion of the necessary legal, governance and operational arrangements. Report P4

The Cabinet approved the Council entering into a Section 8 Agreement and any associated agreements with Transport for London under the Highways Act 1980, to set out roles, liabilities and safeguards for the Council as Highway Authority. Report P5, P19, P22

Authority to take all necessary steps and decisions to deliver the scheme was delegated to the Executive Director of Place, in consultation with the Cabinet Member for Climate Emergency and Travel. Report P6

Why

The recommended option secures significant external transport investment in the borough, delivers walking, wheeling and cycling benefits, and allows continued officer influence through the Section 8 Agreement. Report P111, P112, P113, P115

Some detailed design, maintenance and governance matters are still under discussion, but officers consider these can be managed through the Section 8 Agreement and ongoing work with TfL. Report P75, P76, P77, P78, P114

What happens next

Officers will work with TfL to finalise the Section 8 Agreement, complete statutory processes including traffic orders, and progress detailed design and construction planning. Report P93, P94, P95, P96, P97

Officers will continue discussions with TfL on future maintenance, monitoring and any commuted sums, with a further delegated authority report to set out the final agreement. Report P13, P14, P15, P89, P90

The money

  • approximately £20m Estimated TfL investment within Hammersmith and Fulham Report P2, P8, P10

Options considered

  • Rejected: Do nothing. Would lose TfL investment and active travel benefits, and leave the temporary cycleway in place Report P98, P99, P100, P101
  • Rejected: Delay decision. Could cause programme delays, funding uncertainty and impact TfL's delivery programme Report P101, P102, P103
  • Chosen: Support the scheme and enter a Section 8 Agreement. Secures significant investment, delivers transport and public realm benefits, and is the most efficient and lowest-risk route through TfL's established programme Report P104, P105, P106, P111, P112
  • Rejected: Council-led delivery of the scheme. Would place significant additional resource, financial, delivery and programme risk on the Council, with no certainty TfL would transfer funding and delivery Report P107, P108, P109, P110

Implications

  • Financial: TfL is expected to fully fund and deliver the scheme; no additional Council capital expenditure is sought, but the Council anticipates taking on future inspection, maintenance, renewal and lifecycle costs for assets handed over, with details to be confirmed in the Section 8 Agreement. Report P2, P10, P11, P12, P13, P14, P15
  • Legal: The Council will enter a Section 8 Agreement under the Highways Act 1980 and make traffic management orders under the Road Traffic Regulation Act 1984, with a 21-day objection period and 6-week challenge window for permanent orders; works can only start once the agreement and orders are in place. Report P19, P20, P23, P24, P25
  • Equalities: An Equality Impact Assessment has been prepared, informed by TfL's EqIA, and will remain a live document; concerns raised by disabled residents and representative groups on bus stop bypasses and crossings will continue to be addressed through design, monitoring and mitigation. Report P118, P119, P120, P121, P122, P123
  • Climate: The scheme is considered likely to have a positive climate impact by supporting modal shift from private cars to walking, wheeling and cycling, and may allow green infrastructure within corridor improvements. Report P129, P130, P131, P132
  • Risk: Risk advisors rate governance and delivery risk as high, recommending embedded staff, defined governance, RAID logs, communications plan and an independent assurance review by midpoint; there is a medium risk of judicial review by residents or pressure groups, to be monitored. Report P126
  • Other: Procurement: scheme is procured and delivered by TfL under its existing arrangements, so it is not a Council-led procurement under the Procurement Act 2023, though the agreement should still secure value for money, risk allocation and lifecycle provisions. Report P135, P136, P137

Who and where

  • Residents and businesses in Hammersmith Broadway, Avonmore and Brook Green wards along Hammersmith Road Report P7, P41, P42
  • People walking, wheeling and cycling along the Hammersmith Road corridor Report P48, P50, P58
  • Disabled residents and accessibility groups, including the Council's Disabled Residents Team and Active Travel Working Group Report P44, P121, P146
  • Bus users and road users affected by bus stop bypasses and junction changes including at Blythe Road Report P63, P64, P65, P73
  • Visitors, employees and residents linked to the Olympia redevelopment Report P55, P65

Timeline

  • September and October 2017: TfL first consulted on Cycle Superhighway 9 (now Cycleway 9) proposals Report P32
  • December 2019: Cabinet considered wider Safer Cycle Pathway proposals for King Street, Hammersmith Road and the A4 corridor Report P34
  • 2021: Council and TfL introduced the interim Safer Cycle Pathway through Hammersmith Town Centre Report P35
  • March 2023: Council approved progression of the Safer Cycle Pathway to a permanent arrangement Report P35
  • 2023 to present: TfL has continued development of the permanent Hammersmith Road section of Cycleway 9 with Council engagement Report P36
  • January 2026: Department for Transport and Active Travel England published 'Floating bus stops provision and design' statutory guidance, expected to inform bus stop bypass design Report P73
  • 12 October 2026: Cabinet decision to support the scheme and enter a Section 8 Agreement Report P4, P5, P6
  • 21-day objection period for permanent traffic orders (plus 6 weeks to challenge): Statutory process for traffic orders required before the scheme can be implemented Report P23

Plain English for the jargon

  • Section 8 Agreement: An agreement under section 8 of the Highways Act 1980 between a local highway authority and a strategic highway authority covering construction, alteration, improvement or maintenance of a highway.
  • Highway Authority: The body responsible for maintaining and managing a particular highway; here, the Council is the local Highway Authority for Hammersmith Road and TfL is the strategic Highway Authority.
  • Cycleway 9 (C9): Part of Transport for London's strategic cycling network providing a continuous, segregated cycle route linking Kensington Olympia, Hammersmith, Chiswick and Brentford.
  • Bus stop bypass: A design where a cycle lane runs behind a bus stop boarding island, separating cyclists from passengers boarding and alighting.
  • EqIA: Equality Impact Assessment, an assessment of how a proposal may affect people with protected characteristics under the Equality Act 2010.
  • Commuted sum: A lump sum payment from one party to another, often paid by a developer or promoter to a highway authority to cover future maintenance of adopted infrastructure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to completion of the necessary legal, governance and operational arrangements. To approve the Council entering into a Section 8 Agreement and any associated agreements with Transport for London required to facilitate delivery of the scheme while ensuring the necessary safeguards are in place to protect the Council as highway authority. To delegate authority to the Executive Director of Place, in consultation with the Cabinet Member for Climate Emergency and Travel, to take all necessary steps and make all decisions required to facilitate delivery and implementation of the Permanent Cycleway 9 scheme whilst protecting the Council's interests in relation to the scheme. It should be noted that discussions with TfL remain ongoing. TfL has advised that the Permanent Cycleway 9 scheme remains subject to its internal governance and funding approval processes. Support from the Council is required at this stage to enable the scheme to continue progressing through those processes.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet, 17 pages

Summary

This report seeks Cabinet approval to support Transport for London's (TfL) Permanent Cycleway 9 scheme on Hammersmith Road and authorisation for the Council to enter into a Section 8 Agreement with TfL under the Highways Act 1980. Building on work TfL started in 2017, the scheme completes a key section of the strategic cycling route linking Kensington Olympia, Hammersmith, Chiswick, and Brentford.

TfL would fund and deliver the scheme, representing approximately £20 million of investment in Hammersmith & Fulham, with no additional Council capital contribution currently sought. The Council's role is as Highway Authority and to ensure appropriate legal, governance, maintenance and operational arrangements are established through the Section 8 Agreement.

The scheme supports the Council's objectives for walking, wheeling, and cycling and is expected to deliver benefits in relation to sustainable transport, safety, accessibility, connectivity, and the public realm.

Recommendations

1. To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to completion of the necessary legal, governance and operational arrangements.

2. To approve the Council entering into a Section 8 Agreement and any associated agreements with Transport for London required to facilitate delivery of the scheme while ensuring the necessary safeguards are in place to protect the Council as highway authority.

3. To delegate authority to the Executive Director of Place, in consultation with the Cabinet Member for Climate Emergency and Travel, to take all necessary steps and make all decisions required to facilitate delivery and implementation of the Permanent Cycleway 9 scheme whilst protecting the Council's interests in relation to the scheme. 4. It should be noted that discussions with TfL remain ongoing. TfL has advised that the Permanent Cycleway 9 scheme remains subject to its internal governance and funding approval processes. Support from the Council is required at this stage to enable the scheme to continue progressing through those processes.

Wards Affected: Hammersmith Broadway, Avonmore, and Brook Green

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TfL Consultation and Engagement SummaryAppendix 1 255 pages Download
PDF
LBHF Equality Impact AssessmentAppendix 2 195 KB Copy on its way
PDF
TfL Hammersmith Road Permanent Cycleway 9 (C9)Report 17 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
SC
Councillor Stephen CowanChair, expected
AS
Councillor Alex SandersonCommittee Member, expected
AJ
Councillor Andrew JonesCommittee Member, expected
RR
Councillor Rowan ReeCommittee Member, expected
FU
Councillor Frances UmehCommittee Member, expected
BK
Councillor Bora KwonCommittee Member, expected
HB
Councillor Hannah BulmerCommittee Member, expected
LH
Councillor Lisa HomanCommittee Member, expected
ZQ
Councillor Zarar QayyumCommittee Member, expected
NT
Councillor Nicole TrehyCommittee Member, expected

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open
12 Oct 2026 Approval to Enter into Agreements for the William Morris Sixth Form Land SwapThat Cabinet: Agree that Appendix 1 is not for publication on the basis that they contain information relating to the... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies