London Borough of Hammersmith & Fulham
Cabinet, Monday 12 October 2026 at 6.30pm

Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)

Noted Executive 1 paper

AI summaryLondon Borough of Hammersmith & Fulham Cabinet noted the £209.3m 2026/27 capital forecast and approved a £12.9m net change in investment across the £532.1m 2026 to 2030 capital programme, including new borrowing that will increase the council's outstanding debt.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the forecast and approved investment changes.
Money£209.3m 2026/27 forecastDown £51.1m from £260.5m; £532.1m four year total.
What happens nextImplement approved changesOfficers to deliver programme and manage borrowing costs.
Who it affectsAll borough wardsCapital spend covers housing, transport, schools and public realm.

What was decided

Cabinet noted the £209.3m forecast for 2026/27 capital expenditure, which is £51.1m less than the revised budget at 2025/26 outturn. Report P7

Cabinet approved a £12.9m net change in investment across the four year programme, including new additional borrowing. Report P8

Cabinet approved the updated four year capital programme for 2026 to 2030 totalling £532.1m. Report P9

Why

The forecast reduction brings the budget closer to the £163m set at full council in February 2026. Report P27

Capital investment supports the council's priorities on housing, transport, public realm and the climate emergency. Report P3, P11, P13

Borrowed amounts will increase the Capital Financing Requirement and require Minimum Revenue Provision from revenue budgets. Report P16, P36, P37

What happens next

Officers to implement the additions and reductions set out in Appendix 1 of the report. Report P8, P34

Officers to monitor the Capital Financing Requirement and Minimum Revenue Provision within the medium term financial strategy. Report P16, P38

Work continues on the Civic Campus project, with the Health and Safety Executive report on the site incident still awaited. Report P46

The money

  • £209.3m 2026/27 capital expenditure forecast at quarter one Report P4, P7
  • £260.5m Revised capital budget at 2025/26 outturn Report P7
  • £51.1m Net decrease in 2026/27 forecast against revised budget Report P7, P27
  • £12.9m Net change in investment across the four year programme Report P8, P9
  • £532.1m Updated four year capital programme 2026 to 2030 Report P9, P31
  • £545m Forecast four year programme at 2025/26 outturn Report P9
  • £987m to £1.132bn Forecast Capital Financing Requirement from end of 2026/27 to end of 2029/30 Report P43
  • £3m per year Potential cost of breaching the VAT partial exemption threshold Report P60

Options considered

  • Chosen: Manage the variance through programme slippages and accelerations between financial years. Matches the forecast timing of project delivery to expected expenditure without changing the overall budget envelope. Report P28

Implications

  • Financial: Borrowing will increase the Capital Financing Requirement from £987m at end of 2026/27 to £1.132bn at end of 2029/30, with corresponding Minimum Revenue Provision. Report P16, P39, P43
  • Financial: Two new borrowing funded additions (£0.249m for business intelligence and £1.2m for parking schemes and CCTV) bring estimated extra annual revenue costs of £0.07m and £0.275m. Report P29
  • Risk: Risks include slower housing development sales, lower Right to Buy receipts, completion of the Civic Campus, cost inflation and interest rate movements. Report P45, P46, P47, P48
  • Risk: Up to £20.7m of spend on early stage regeneration schemes across the General Fund (£5.3m) and HRA (£15.4m) could be written off if schemes do not progress, partly mitigated by £5m and £3.5m in earmarked reserves. Report P49
  • Legal: No direct legal implications; legal advice will be sought for each procurement in line with the Council's Contract Standing Orders and Financial Regulations. Report P17
  • Equalities: No direct equalities implications; recommendations relate to financial management only. Report P50
  • Climate: Investments support the council's Climate and Ecology Strategy and target of net zero greenhouse gas emissions in the borough by 2030. Report P13
  • Other: Capital projects create a VAT partial exemption risk that could cost the council around £3m per year if breached. Report P60

Who and where

  • All wards across the London Borough of Hammersmith and Fulham Report P10
  • Council housing tenants, with £56m in planned maintenance and £51m in new affordable housing and supported accommodation Report P5
  • Disabled residents needing home adaptations through the Disabled Facilities Grant Report P13, P29, P70
  • Children and young people, through school maintenance, decarbonisation and special educational needs sufficiency schemes Report P5, P29, P70
  • Residents and visitors using transport infrastructure including Hammersmith Bridge stabilisation, public realm and parks Report P5, P13
  • Local businesses and arts users, through continued Civic Campus development Report P6, P46

Timeline

  • February 2026: Original £163m 2026/27 capital budget set at full council Report P19, P27
  • 2025/26 outturn: Revised budget baseline of £260.5m and four year programme of £545m Report P7, P9
  • By 2030: Council's target for net zero greenhouse gas emissions in the borough Report P13
  • 12 October 2026: Cabinet decision to note forecast and approve programme changes
  • Q1 2026/27: Quarter one capital programme monitoring position Report P4, P20

Plain English for the jargon

  • Capital Financing Requirement (CFR): The council's outstanding debt from borrowing used to fund capital programmes.
  • Minimum Revenue Provision (MRP): The annual amount councils must set aside from revenue to repay outstanding debt.
  • Housing Revenue Account (HRA): The ringfenced account that holds income and spending on council housing.
  • General Fund (GF): The main council account for services funded by general taxation, grants and other income.
  • Section 106 and Community Infrastructure Levy (CIL): Developer contributions used to fund local infrastructure.
  • Right to Buy: The scheme allowing council tenants to buy their homes at a discount, generating capital receipts for the council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparison to the revised budget of £260.5m at 2025/26 outturn. To approve the overall change in investment of £12.9m across the revised four year programme, including new additional borrowing. Details of this investment are set out in Appendix 1. To approve the updated four-year capital programme for 2026-2030 of £532.1m, as detailed in the report. This is a net decrease of £12.9m in comparison to the forecast four-year programme as at outturn 2025/26 (£545m).
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet, 17 pages

Summary

The Council’s Corporate Plan for 2023-26 sets out the Council’s strategy for delivering on the ambitions and vision to transform its services and spend and invest money to help protect high-quality essential services for its residents.

A key value is Building Shared Prosperity, and the Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies. These are:

• build a better future for children and young people • foster inclusive, sustainable economic growth for everyone • build more affordable, accessible, safe and sustainable housing • deliver high-quality housing services • Ensuring our borough is a safer, stronger, kinder borough to live in, work and visit through expansion of our CCTV infrastructure to prevent and deter crime.

All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The 2026/27 capital programme is forecast to spend £209.3m as at quarter one. Some major areas of spend with the 2026/27 budget are:

• £56m maintaining the existing council homes to ensure compliance • £51m investment in acquiring and building new affordable housing and supported accommodation in the Borough; • £20.8m investment in transport infrastructure; • £12m spend on public realm and protection and climate change initiatives; • £5.5m investment in school maintenance and decarbonisation schemes and SEN sufficiency provision; • £1m ensuring the safety of Hammersmith Bridge and progressing the stabilisation work; and • £2.6m investment in disabled facilities adaptation works and social care capital projects.

Work is also continuing to complete the Civic Campus development that will re-open the iconic town hall to the public, which will rejuvenate and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture. The details of the forecast capital programme for the financial year 2026/27 (including the financing of the programme for the year) and the future years are set out in the report.

Recommendations

1. To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparison to the revised budget of £260.5m at 2025/26 outturn.

1. To approve the overall change in investment of £12.9m across the revised four- year programme, including new additional borrowing. Details of this investment are set out in Appendix 1

2. To approve the updated four-year capital programme for 2026-2030 of £532.1m, as detailed in the report. This is a net decrease of £12.9m in comparison to the forecast four-year programme as at outturn 2025/26 (£545m).

Wards Affected: All

The capital programme contains schemes and projects which are directly linked to the Council’s priorities.

Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to be efficient underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)Report 17 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
SC
Councillor Stephen CowanChair, expected
AS
Councillor Alex SandersonCommittee Member, expected
AJ
Councillor Andrew JonesCommittee Member, expected
RR
Councillor Rowan ReeCommittee Member, expected
FU
Councillor Frances UmehCommittee Member, expected
BK
Councillor Bora KwonCommittee Member, expected
HB
Councillor Hannah BulmerCommittee Member, expected
LH
Councillor Lisa HomanCommittee Member, expected
ZQ
Councillor Zarar QayyumCommittee Member, expected
NT
Councillor Nicole TrehyCommittee Member, expected

On this subject at Hammersmith & Fulham

Search all
  1. Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)This decision
  2. Capital Programme Outturn 2025/26Noted
  3. Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)Noted
  4. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  5. Four Year Capital Programme 2026-30 and Capital Strategy 2026/27Approved
  6. Capital Programme Monitor and Budget Variations 2025/26 (Second Quarter)Noted

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open
12 Oct 2026 Approval to Enter into Agreements for the William Morris Sixth Form Land SwapThat Cabinet: Agree that Appendix 1 is not for publication on the basis that they contain information relating to the... Agreed Open