Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)
NotedExecutive1 paper
AI summaryLondon Borough of Hammersmith & Fulham Cabinet noted the £209.3m 2026/27 capital forecast and approved a £12.9m net change in investment across the £532.1m 2026 to 2030 capital programme, including new borrowing that will increase the council's outstanding debt.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the forecast and approved investment changes.
Money£209.3m 2026/27 forecastDown £51.1m from £260.5m; £532.1m four year total.
What happens nextImplement approved changesOfficers to deliver programme and manage borrowing costs.
Who it affectsAll borough wardsCapital spend covers housing, transport, schools and public realm.
What was decided
Cabinet noted the £209.3m forecast for 2026/27 capital expenditure, which is £51.1m less than the revised budget at 2025/26 outturn. Report P7
Cabinet approved a £12.9m net change in investment across the four year programme, including new additional borrowing. Report P8
Cabinet approved the updated four year capital programme for 2026 to 2030 totalling £532.1m. Report P9
Why
The forecast reduction brings the budget closer to the £163m set at full council in February 2026. Report P27
Capital investment supports the council's priorities on housing, transport, public realm and the climate emergency. Report P3, P11, P13
Borrowed amounts will increase the Capital Financing Requirement and require Minimum Revenue Provision from revenue budgets. Report P16, P36, P37
What happens next
Officers to implement the additions and reductions set out in Appendix 1 of the report. Report P8, P34
Officers to monitor the Capital Financing Requirement and Minimum Revenue Provision within the medium term financial strategy. Report P16, P38
Work continues on the Civic Campus project, with the Health and Safety Executive report on the site incident still awaited. Report P46
The money
£209.3m 2026/27 capital expenditure forecast at quarter one Report P4, P7
£260.5m Revised capital budget at 2025/26 outturn Report P7
£51.1m Net decrease in 2026/27 forecast against revised budget Report P7, P27
£12.9m Net change in investment across the four year programme Report P8, P9
£532.1m Updated four year capital programme 2026 to 2030 Report P9, P31
£545m Forecast four year programme at 2025/26 outturn Report P9
£987m to £1.132bn Forecast Capital Financing Requirement from end of 2026/27 to end of 2029/30 Report P43
£3m per year Potential cost of breaching the VAT partial exemption threshold Report P60
Options considered
Chosen: Manage the variance through programme slippages and accelerations between financial years. Matches the forecast timing of project delivery to expected expenditure without changing the overall budget envelope. Report P28
Implications
Financial: Borrowing will increase the Capital Financing Requirement from £987m at end of 2026/27 to £1.132bn at end of 2029/30, with corresponding Minimum Revenue Provision. Report P16, P39, P43
Financial: Two new borrowing funded additions (£0.249m for business intelligence and £1.2m for parking schemes and CCTV) bring estimated extra annual revenue costs of £0.07m and £0.275m. Report P29
Risk: Risks include slower housing development sales, lower Right to Buy receipts, completion of the Civic Campus, cost inflation and interest rate movements. Report P45, P46, P47, P48
Risk: Up to £20.7m of spend on early stage regeneration schemes across the General Fund (£5.3m) and HRA (£15.4m) could be written off if schemes do not progress, partly mitigated by £5m and £3.5m in earmarked reserves. Report P49
Legal: No direct legal implications; legal advice will be sought for each procurement in line with the Council's Contract Standing Orders and Financial Regulations. Report P17
Equalities: No direct equalities implications; recommendations relate to financial management only. Report P50
Climate: Investments support the council's Climate and Ecology Strategy and target of net zero greenhouse gas emissions in the borough by 2030. Report P13
Other: Capital projects create a VAT partial exemption risk that could cost the council around £3m per year if breached. Report P60
Who and where
All wards across the London Borough of Hammersmith and Fulham Report P10
Council housing tenants, with £56m in planned maintenance and £51m in new affordable housing and supported accommodation Report P5
Disabled residents needing home adaptations through the Disabled Facilities Grant Report P13, P29, P70
Children and young people, through school maintenance, decarbonisation and special educational needs sufficiency schemes Report P5, P29, P70
Residents and visitors using transport infrastructure including Hammersmith Bridge stabilisation, public realm and parks Report P5, P13
Local businesses and arts users, through continued Civic Campus development Report P6, P46
Timeline
February 2026: Original £163m 2026/27 capital budget set at full council Report P19, P27
2025/26 outturn: Revised budget baseline of £260.5m and four year programme of £545m Report P7, P9
By 2030: Council's target for net zero greenhouse gas emissions in the borough Report P13
12 October 2026: Cabinet decision to note forecast and approve programme changes
Q1 2026/27: Quarter one capital programme monitoring position Report P4, P20
Plain English for the jargon
Capital Financing Requirement (CFR): The council's outstanding debt from borrowing used to fund capital programmes.
Minimum Revenue Provision (MRP): The annual amount councils must set aside from revenue to repay outstanding debt.
Housing Revenue Account (HRA): The ringfenced account that holds income and spending on council housing.
General Fund (GF): The main council account for services funded by general taxation, grants and other income.
Section 106 and Community Infrastructure Levy (CIL): Developer contributions used to fund local infrastructure.
Right to Buy: The scheme allowing council tenants to buy their homes at a discount, generating capital receipts for the council.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparison to the revised budget of £260.5m at 2025/26 outturn. To approve the overall change in investment of £12.9m across the revised four year programme, including new additional borrowing. Details of this investment are set out in Appendix 1. To approve the updated four-year capital programme for 2026-2030 of £532.1m, as detailed in the report. This is a net decrease of £12.9m in comparison to the forecast four-year programme as at outturn 2025/26 (£545m).
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The Council’s Corporate Plan for 2023-26 sets out the Council’s strategy for delivering on the ambitions and vision to transform its services and spend and invest money to help protect high-quality essential services for its residents.
A key value is Building Shared Prosperity, and the Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies. These are:
• build a better future for children and young people • foster inclusive, sustainable economic growth for everyone • build more affordable, accessible, safe and sustainable housing • deliver high-quality housing services • Ensuring our borough is a safer, stronger, kinder borough to live in, work and visit through expansion of our CCTV infrastructure to prevent and deter crime.
All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The 2026/27 capital programme is forecast to spend £209.3m as at quarter one. Some major areas of spend with the 2026/27 budget are:
• £56m maintaining the existing council homes to ensure compliance • £51m investment in acquiring and building new affordable housing and supported accommodation in the Borough; • £20.8m investment in transport infrastructure; • £12m spend on public realm and protection and climate change initiatives; • £5.5m investment in school maintenance and decarbonisation schemes and SEN sufficiency provision; • £1m ensuring the safety of Hammersmith Bridge and progressing the stabilisation work; and • £2.6m investment in disabled facilities adaptation works and social care capital projects.
Work is also continuing to complete the Civic Campus development that will re-open the iconic town hall to the public, which will rejuvenate and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture. The details of the forecast capital programme for the financial year 2026/27 (including the financing of the programme for the year) and the future years are set out in the report.
Recommendations
1. To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparison to the revised budget of £260.5m at 2025/26 outturn.
1. To approve the overall change in investment of £12.9m across the revised four- year programme, including new additional borrowing. Details of this investment are set out in Appendix 1
2. To approve the updated four-year capital programme for 2026-2030 of £532.1m, as detailed in the report. This is a net decrease of £12.9m in comparison to the forecast four-year programme as at outturn 2025/26 (£545m).
Wards Affected: All
The capital programme contains schemes and projects which are directly linked to the Council’s priorities.
Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to be efficient underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.