Resolved
That the Buildings, Land and Procurement Panel recommends to the Executive Member for Policy and Resources that: a) Progress of each of the programmes is noted.
Buildings, Land and Procurement Panel noted this item on Tuesday 27 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Buildings, Land and Procurement Panel recommends to the Executive Member for Policy and Resources that: a) Progress of each of the programmes is noted.
1.1The purpose of this paper is to provide an update on the major programmes and issues currently being progressed relating to:
New Schools Delivery Programme Traded Services One Public Estate (OPE) Adult Services Programme Capital Receipts Construction Frameworks Construction Industry Appraisal
2. New Schools Delivery Programme
2.1All new schools are now required to be established as Free Schools by the Department for Education (DfE). Free Schools are sponsored and operated by an Academy Trust. The Academy Trust will provide the education and will be responsible for the buildings maintenance and operating costs. The Local Authority will retain the freehold of the site and grant a long lease (usually 125 years) to the Trust. There are two routes available to open a new Free School and construct the building: One option is for the Local Authority to seek a sponsor through a ‘presumption’ route, where the Authority is responsible for providing the site for the new school and meeting the associated capital and building establishment costs. A competitive process is undertaken and the preferred sponsor is recommended to the DfE for approval by the Secretary of State. The second option is through an ‘approved’ sponsor (pre-registered by the DfE) making a direct application to the DfE. The Local Authority can support (but not lead) such an application and is consulted on the submission.
To date, HCC has successfully worked in Partnership with Academy sponsors making Free School applications to the DfE direct to provide additional school places (Basic Need). 2.2 The County Council’s 350 strong Property Services team has a proven track record over many years of delivering new school buildings and it is proposed they continue to play a role in the process to ensure that good quality environments are constructed for the benefit of Hampshire children. The DfE now requires that all new schools are constructed to a benchmark funding envelope to maximise the number of places provided for the funding available nationally. This is in the context of reduced public spending and austerity and will be at a lower cost than schools previously delivered in Hampshire. The County Council is proposing to construct schools to acceptable standards at this lower cost target through a combination of careful planning and appropriate design. 2.3 There are currently seven new schools identified to be delivered in the next four years (2017-2021). These are listed below: East Anton Primary School, Andover (Extension to existing School) Boorley Green Primary (Free School) Horton Heath All Through School (Free School): to be delivered as two projects for Primary and Secondary places Basingstoke Special Educational Needs (Free School) Chestnut Avenue Primary, Eastleigh (Free School – Presumption route) Cornerstones Primary, Whiteley (Church of England Aided School) Whiteley Secondary (Governance TBC)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Major Programmes Update ReportAppendix | 123 KB | DownloadRead as text |
Follow Buildings, Land and Procurement Panel at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2022 | Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... | Approved | Open |
| 14 Jun 2022 | Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... | Approved | Open |
| 14 Jun 2022 | Business Services Group – 2021/22 Annual Report and AccountsThat the Buildings, Land and Procurement Panel recommend to the Executive Member for Commercial Strategy, Estates and... | Approved | Open |
| 14 Jun 2022 | Exclusion of the press and publicThe press and public were excluded from the meeting during the following item of business, as it was likely, in view ... | Decided | Open |
| 6 Apr 2022 | Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.