CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hampshire County Council
Hampshire Fire and Rescue Authority, Thursday 12 July 2018 at 2.00pm

Outturn Report 2017/18

Approved Committee 7 papers

Hampshire Fire and Rescue Authority approved this item on Thursday 12 July 2018. Below is the council's own wording, with the papers it was decided on.

Item109

Resolved

The accounts for 2017/18, including the use of reserves set out in paragraph 22, and Appendix D of this report was approved by Hampshire Fire and Rescue Authority; 2. That the carry forward requested in paragraph 2 of this report was approved; 3. The request that funding be taken from the 2017/18 underspend to cover one-off IT spend as set out in paragraph 4 of this report was approved; 4. The changes to the capital payments in 2017/18 and the impact on the capital spend profile going forward as set out in Appendices B & C was approved by Hampshire Fire and Rescue Authority; 5. The financing for capital payments as set out in paragraph 18 was approved by Hampshire Fire and Rescue Authority; 6. That the annual treasury outturn report set out in Appendix E of this report was approved by Hampshire Fire and Rescue Authority; and 7. The refresh of the Reserves Strategy detailed in Appendix F was approved by Hampshire Fire and Rescue Authority. 8. The increase in the net cost of pensions and support staff would be investigated by the Treasurer and reported back to Full Authority at the next meeting.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Hampshire Fire and Rescue Authority

Executive summary

1. The final year end position for 2017/18 is an underspend of £434,800 against budget. This is after having absorbed the significant overspend on the ICT Transformation project and a small overspend on Property Services that has already been reported during the year. These overspends have been offset by lower than budgeted employee costs as vacancies in the current structure are being held in preparation for the restructure for Service Delivery Redesign.

2. A carry forward request has been received from the Technical Services Department to allow them to carry forward £224,400 for the purchase of equipment that had been planned during 2017/18, but due to delays with the procurement process, this was not possible.

3. The carry forward request has provisionally been approved by the Chairman of the Authority due to the timing of this report, therefore leaving a net underspend of £210,400. This amount has been transferred to the Transformation Reserve, in line with current policy.

4. IT is continuing to enhance their service provision. Two elements of this, upgrading to Windows 10 and provision of Mobile Presentation Units (MPU) for training and service updates, will need additional one-off funding to cover implementation costs. Preparation for the Windows project will cost £10,000, with any further costs being assessed during this period. MPU provision is expected to cost £40,000 for full implementation.

5. It is proposed that these costs be funded from the 2017/18 underspend, with any additional requirements being reported back to the Authority for approval.

6. The opportunity is also taken in this report to provide a brief update to the Authority on the monitoring position for the first 2 months of 2018/19 and to provide an updated version of the Reserves Strategy which was first published back in 2013.

7. This report requests Members of the Authority to review the figures as laid out in the Appendices and recommends that the outturn report, including reserves and capital financing are approved, along with the annual treasury outturn for 2017/18. BACKGROUND

8. This is an annual report which sets out the financial position at the end of 2017/18 as per the draft Statement of Accounts. Budget monitoring for the first two months of the current financial year is also included for information.

REVENUE EXPENDITURE 2017/18

9. The revenue outturn position is shown in functional and subjective summary at Appendix A.

10. Early savings have been made through the Service Delivery Redesign (SDR) Programme, with the pilots enabling the service to run with a number of vacancies against the current budget in order to reduce to the required level by March 2019.

11. There were vacant retained firefighter posts throughout the whole of 2017/18, which has resulted in an underspend of £348,800. However, significant effort has been put into recruitment and the numbers are now closer to the required level under the SDR structure.

12. These underspends have been offset by the ICT overspend that was reported to HFRA during the year and the subsequent investigations and proposed management actions were reported through to Standards and Governance Committee. This overspend is reflected partly in Staff costs and partly in Supplies and Services in the Appendix.

13. There has also been a slight overspend on premises, caused by additional costs for reactive maintenance. This is being addressed in the planned maintenance programme to avoid future uncontrollable spend and was reported to the Authority during the year.

14. Income has been higher than budgeted in a number of areas, with the highest increases coming from interest on balances, Technical Services collaborations and the use of our estate.

15. There has been an increase in the requirement for provisions of £521,000, which is explained further in section 21 below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 59 KB Download
PDF
Appendix BAppendix B 102 KB Download
PDF
Appendix CAppendix C 61 KB Download
PDF
Appendix DAppendix D 34 KB Download
PDF
Appendix EAppendix E 112 KB Download
PDF
Appendix FAppendix F 91 KB Download
PDF
Outturn Report 2017/18Report 165 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
CC
Councillor Christopher Carter Hampshire County CouncilChairman, present
LF
Councillor Liz Fairhurst Hampshire County CouncilVice-Chairman, present
RC
Councillor Roz Chadd Hampshire County CouncilCommittee Member, present
JF
Councillor Jason Fazackarley Portsmouth City CouncilCommittee Member, present
JG
Councillor Jonathan Glen Hampshire County CouncilCommittee Member, present
GH
Councillor Geoffrey Hockley Hampshire County CouncilCommittee Member, present
SM
Councillor Sharon Mintoff Southampton City CouncilCommittee Member, present
RP
Councillor Roger Price Hampshire County CouncilCommittee Member, present
DS
Councillor David Simpson Hampshire County CouncilCommittee Member, present
RV
Councillor Rhydian Vaughan Hampshire County CouncilCommittee Member, present

On this subject at Hampshire

Search all
  1. Outturn Report 2017/18This decision
  2. Treasury Management Outturn Report 2025/26Noted
  3. Outturn ReportDecided
  4. Annual Treasury Outturn Report 2025/26Noted
  5. River Hamble Final Accounts 2025/26 and Forecast Outturn 2026/27Approved
  6. River Hamble Final Accounts 2025/26 and Forecast Outturn 2026/27Noted

More from Hampshire Hampshire Fire and Rescue Authority

All decisions
MeetingDecisionOutcome
22 Jul 2020 Outturn Report 2019/20a) The accounts for 2019/20, including the use of reserves set out in paragraph 24 and Appendix D of the report were ... Approved Open
22 Jul 2020 Exclusion of Press and PublicIt was resolved that the public be excluded from the meeting during the following items of business, as it was likely... Decided Open
3 Jun 2020 Appointments ReportRESOLVED a) The Authority noted the Local Authorities and Police and Crime Panels (Coronavirus) (Flexibility of Local... Noted Open
3 Jun 2020 Year End Performance ReportRESOLVED Hampshire Fire and Rescue Authority noted the performance for 2019/20 detailed in the report. Noted Open
3 Jun 2020 Service Plan 2015-2020 Performance Review and Close ReportRESOLVED The closure of the 2015-2020 Service Plan was approved by the Authority. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies