Hampshire Fire and Rescue Authority agreed this item on Wednesday 5 December 2018. Below is the council's own wording, with the papers it was decided on.
a) It was agreed that Revenue Contributions to Capital Outlay (RCCO) be reduced in order to balance the budget, after all other savings and adjustments had been taken into account, if necessary. b) The Authority noted the significant risk in respect of employers pension contributions beyond 2019/20. c) It was agreed that £1.2m of the 2018/19 underspend be transferred to the Transformation Reserve and used to fund the items highlighted in paragraph 15 of the report. d) It was agreed that delegated authority be given to the Chief Fire Officer to approve the use of all specific reserves up to £200,000. e) Approval was given for £303,000 from the Transformation Reserve for the NFSP system refresh and upgrades. f) Approval was given for £130,000 from the Transformation Reserve for the changes associated with moving to Windows 10 and that the ongoing costs of £25,000 are taken into account when the budget for 2019/20 is set in February 2019. g) Authority approved the approach for dealing with Information and Communications Technology (ICT) pressures as outlined in the report. The mid-year review of treasury management activities were approved.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. This report is to provide an update to members on the current financial position for the 2018/19 Revenue Budget and an update on the 2019/20 budget setting process.
2. An underspend of £1.6m is currently forecast for 2018/19 as detailed in paragraphs 12-15 below, although this will be impacted by further pressures within ICT as outlined in this report.
3. An assumed 2.99% increase in precept for 2019/20 would leave a shortfall of £0.7m based on the MTFP presented to the Authority in September, this report discusses the proposal to meet that gap in the short term, including reducing the RCCO for the year if necessary in line with current policy.
4. The position in respect of the change in the valuation basis for unfunded public- sector pension schemes has progressed since it was reported verbally to the Authority in September. It is now anticipated that there will be an increase in the employer’s contribution rate in excess of 12%, which for Hampshire would be an increase in costs of around £3m. However, the Government has agreed that it will fund around 90% of this sum for 2019/20 only and will deal with this issue on an ongoing basis as part of the Spending Review planned for 2019. The Home Office is currently consulting on the proposed methodology for distributing this funding, but at this stage it removes the majority of this risk from the 2019/20 budget setting process.
Background
5. The Medium Term Financial Plan was updated and reported to the Authority in September this year. The plan showed a £0.7m funding shortfall for 2019/20, which is down from the £2.2m shortfall expected within the October 2017 MTFP due to the reductions made as part of the 2018/19 budget.
1 6. Each October, the local precepting authorities provide an updated council tax base estimate, which is usually close to the final figure. This year the amounts provided give a 1.47% rise in the Council Tax Base, which equates to an increase in income of around £200,000 on the figure included within the September MTFP report.
7. The detailed budget setting process is currently underway, which will review all budget lines with the aim of ensuring that they are valid and accurate and will remove any excess funding that is held within departments.
8. A separate Zero Based Budgeting (ZBB) exercise has also been carried out and the results of this are included within this report. The changes identified reflect a greater attention to budget setting and monitoring across the Service in this financial year and the fact that budgets have been reviewed and challenged as part of the organisational changes being implemented this year.
9. The overall net changes from the ZBB exercise have themselves been balanced to zero, but this is an important exercise to ensure that the budgets reflect current structures and activity and will aid in budget monitoring and control during the financial year.
10. Separate to this, extensive work has been undertaken on the position of our ICT set up, following further reviews of our infrastructure and security arrangements and work undertaken by the new interim head of ICT. There are additional one off and recurring costs associated with bringing the ICT infrastructure and applications up to a standard that is fit for purpose for an emergency service and these are detailed in this report.
11. The £0.7m shortfall in the MTFP included the full level of RCCO required for funding the current capital programme. This was reduced in 2018/19 to balance the budget, which could also be done for 2019/20 in line with the existing strategy, now that the risk around the pension changes has been clarified. The actual figure will be dependent on the local government finance settlement and final figures from Districts on council tax base and the surpluses or deficits in their collection funds.
2018/19 QUARTER 2 BUDGET MONITORING
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.