RESOLVED : Planning permission was granted subject to the update report and conditions listed in Appendix A. Voting: Favour: 16 (unanimous)
Regulatory Committee decided this item on Wednesday 21 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : Planning permission was granted subject to the update report and conditions listed in Appendix A. Voting: Favour: 16 (unanimous)
1. That planning permission be granted subject to the conditions listed in Appendix A.
2. The planning application is for variation of condition 1 of Planning Permission 30633/034 to extend the time period of extraction to 31 December 2022 and completion of restoration within a further period of 2 years at Grundon Sand and Gravel Ltd Frith End Sand Quarry, Frith End, Bordon GU35 0QR.
3. This application is being considered by the Regulatory Committee as it was requested to do so by County Councillor Kemp-Gee, in accordance with the Hampshire County Council Scheme of Delegation for planning matters.
4. Key issues raised are: Repair flood damage to the site to allow recommencement of supply of mineral resources and site restoration; and Local public impact and amenity.
5. A committee site visit by Members did not take place due to Covid-19 restrictions. Site plans and photographs have been added in Appendix B to support members of the Committee.
6. The proposed development is not an Environmental Impact Assessment development under the Town & Country Planning (Environmental Impact Assessment) Regulations 2017.
7. The site is an existing mineral extraction quarry which is safeguarded by Policy 16 (Safeguarding – minerals infrastructure) and contributes towards an adequate and steady supply of aggregates for Hampshire and surrounding areas. It is considered that the proposal would be in accordance with the relevant policies of the adopted Hampshire Minerals and Waste Plan (2013) and that the proposed development would:
Allow for the repair of the site from flood damage to the site to allow recommencement of supply of mineral resources; Allow for the approved restoration scheme to be implemented; and Not cause an increase in the level of adverse impacts, but rather extend those impacts considered acceptable by previous permissions to continue for a further two years.
8. Therefore, it is recommended that planning permission be granted subject to the conditions listed in Appendix A.
The Site
9. Frith End quarry is an active sand quarry that comprises approximately 17.4 hectares of land located to the north of Bordon, Hampshire. The quarry is accessed by means of a purpose built access road direct off the A325 and the site has good access onto the strategic road network. The quarry has been in operation for approximately 30 years.
10. The quarry is identified in the adopted Hampshire Minerals and Waste Plan (2013) as a safeguarded site for the extraction of soft and silica sand with the current planning permission (30633/034) allowing extraction of sand until 31 December 2020 and complete restoration by 31 December 2022. The quarry has been extended a number of times, both in terms of area and the length of time to complete operations.
11. The site also contains hedgerows and blocks of woodland, with remnant areas of grassland. A single large remnant hedgerow approximately 440 metres long bisects the site in an east/west alignment along the northern side of public footpath no.26. Dense scrub woodland also exists along 300 metres of the south side of the footpath. Pasture fields bisected by native species‐rich hedgerows and blocks of broad‐leaved woodland extends in all other directions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Grunden Sand and Gravel Ltd. Frith End Sand Quarry Frith End BordonReport | 1.6 MB | DownloadRead as text |
PDF |
PlanReport | 1.8 MB | Download |
Follow Regulatory Committee at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Update to the Validation GuidanceRESOLVED That the Committee note the contents of the draft Planning Application Validation Guidance and approve the d... | Noted | Open |
| 10 Jun 2026 | Monitoring and Enforcement UpdateRESOLVED The Regulatory Committee noted the content of the report. | Noted | Open |
| 10 Jun 2026 | Impending legislation changes for Regulatory Committee including changes to the committee sizeRESOLVED The Regulatory Committee noted the anticipated legislation to come into force on 31 October 2026. The Regula... | Noted | Open |
| 18 Mar 2026 | Silverlake Automotive Recycling Ltd, Botley Road, Shedfield, SouthamptonThat planning permission be REFUSED for the reasons set out in the report of the Director of Universal Services. | Refused | Open |
| 18 Mar 2026 | Monitoring and Enforcement UpdateMembers noted the contents of the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.