RESOLVED The River Hamble Harbour Board: a) Noted the projected outturn for the 2021/22 financial year; b) Approved the proposed forward budget; c) Noted the balances held within the reserves and the position of the balances; and d) Approved the proposal to fund the pump replacement at Warsash jetty from revenue, rather than the Asset Enhancement Reserve as budgeted.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. The purpose of this report is to present the 2021/22 outturn forecast as at the end of September 2021 and the proposed 2022/23 forward budget to the River Hamble Harbour Board for comment.
Recommendation(s)
2. That the projected outturn for the 2021/22 financial year is noted.
3. That the proposed forward budget is approved.
4. That the balances held within the reserves and the position on the reserve balances are noted.
5. That the proposal to fund the pump replacement at Warsash jetty from revenue, rather than the Asset Enhancement Reserve as budgeted, be approved. Executive Summary
6. For the 2021/22 financial year, the River Hamble is projected to achieve a surplus of £57,000 on revenue funded expenditure, compared to a revised budgeted surplus of £59,000. This would allow for the £35,000 annual transfer from the Revenue Reserve (RR) to the Asset Replacement Reserve (ARR) to be made, and for an increase in the balance in the RR from £43,829 to £65,829 by March 2022.
7. In 2022/23 the budgeted surplus on revenue funded expenditure is £37,000. This would potentially increase the Revenue Reserve to £67,829.
8. For both 2021/22 and 2022/23, the projected balance in the RR would slightly exceed the maximum per the reserves policy of no more than 10% of the gross revenue budget, and therefore a potential option to address this issue is considered later within this report.
9. The detailed revised budget for 2021/22, the 2021/22 outturn forecast and the proposed 2022/23 forward budget are set out in Appendices 1 and 2, with the current and projected reserves balances shown in Appendix 3.
10. The forward budget includes the 1% increase to harbour dues, as approved by the River Hamble Harbour Board on 30 July 2021.
2021/22 Forecast Outturn
11. The outturn forecast for 2021/22 as at the end of September 2021 is detailed in Appendix 1. It is projected that a surplus on standard revenue activity of £57,000 will be achieved, £2,000 lower than the budgeted surplus of £59,000.
12. It was agreed by the Board in May 2007, that a contribution of £43,000, later reduced to £35,000 per annum would be made to the Asset Replacement Reserve (ARR) to fund the cost of replacing assets in future years. This contribution is met from the surplus on revenue funded expenditure, supplemented by a transfer from the Revenue Reserve as required.
13. The £35,000 will therefore be transferred to the ARR in full, with the projected remaining £22,000 being transferred to the RR, which would increase to a balance of £65,829 as at 31 March 2022. This projected balance would be slightly above the £62,200 maximum approved RR balance of 10% of the gross revenue budget. A potential solution is proposed within the Reserves section of this report. 14. Total gross expenditure is projected at £640,000, £18,000 higher than the budgeted £622,000. The variance mainly relates to higher staffing costs due to the 1.75% offer for the 2021/22 pay award, with the budget provision for the pay award having been removed from the revised budget following the public sector pay freeze announcement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.