RESOLVED a) Planning permission was GRANTED for planning application, 30633/041 subject to the conditions listed in Appendix A (30633/041). b) Planning permission was GRANTED for planning application 30633/040, subject to the conditions listed in Appendix B . Both recommendations were voted on together with the following outcome: Favour: 13 Against: 1
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. It is recommended that planning permission be GRANTED for planning application, 30633/041 subject to the conditions listed in Appendix A (30633/041).
2. It is recommended that planning permission be granted for planning application 30633/040, subject to the conditions listed in Appendix B.
Executive summary
3. Two planning applications have been submitted: Planning application 30633/041 – Seeks permission for a 2.1 hectare extension to the south-west of the existing extraction area at Frith End Quarry on an area known as Ranks Hill. This proposed extension site will be known throughout this report as the ‘Hill Extension’. This is for the extraction of approximately 100,000 tonnes of soft sand and for the restoration of the extension site. This is an Environmental Impact Assessment (EIA) application; and Planning application 30633/040 – Seeks Variation of Conditions 1 (Timescale), 4 (Phasing) and 10 (Landscaping) of Planning Permission 30633/039 to enable the proposed extension sought in application 30633/041 by adopting revised phasing for extraction and restoration and to allow the existing site facilities to accommodate the proposed extension.
4. A committee site visit by Members took place on 8 November 2021 in advance of the proposal being considered by the Regulatory Committee.
5. Key issues raised are: Need for minerals; Flood management and hydrology; Restoration; Ecology; Landscape and visual impact; Arboriculture; and Cumulative impact on residential amenity.
6. The existing quarry is currently permitted by Planning Permission 30633/039 to extract sand until 31 December 2022 and to complete restoration by 31 December 2024. It is proposed that this proposed extension will be extracted and restored within the current agreed restoration deadline for the quarry, 31 December 2024. The lifespan of the quarry will remain unchanged.
7. The existing site is stated to have approximately 120,000 tonnes of soft sand left to be extracted (as of the submission date of April 2021). A portion of the mineral extracted at the quarry is also classified as silica sand as it can be used for silica uses such as horticulture and recreational uses.
8. The applications seek to allow the extraction of the proposed Ranks Hill area once extraction of minerals on the existing site is completed on or before the existing deadline of 31 December 2022. The proposed extension will provide approximately 100,000 tonnes of soft sand. The timing of the potential extraction of Ranks Hill before the remaining reserves in existing quarry and the site closes, would ensure that as much of the safeguarded mineral at the quarry site is extracted. The Rank Hill area would be too small an area to be viably extracted as a stand-alone site once the quarry has closed. The extraction of this area would take place over 15-18 months during the 24- month period currently conditioned for the restoration of Frith End Quarry. The proposal would see the completion of the restoration for the entire site completed within the existing deadline of 31 December 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update to the Validation GuidanceRESOLVED That the Committee note the contents of the draft Planning Application Validation Guidance and approve the d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.