RESOLVED a) It was agreed that deliverable (c) in the Year 5 activities be changed to: “ deliver in-year efficiencies and identify and implement where possible saving options”by the HIWFRA Full Authority. b) Work to produce the Fire Authority’s next Safety Plan was noted and the approach to consult was approved by the HIWFRA Full Authority.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. This report seeks Fire Authority approval to change one of our previously agreed Year 5 activities and publicly consult on our proposals for our next Safety Plan covering the period 2025-30.
2. Earlier this year, the Fire Authority agreed our Year 5 (2024/25) activities. One activity was to deliver efficiencies this year. However, as previously been mentioned, we are now facing a higher than forecasted funding gap. As a result, we are needing to carry out additional work this year to reduce our costs and raise income, going further than what the deliverable originally envisaged. We therefore need Fire Authority approval for this work.
3. Separately, to produce our next Safety Plan, we must meet the requirements of the Community Risk Management Plan fire standard and the Fire and Rescue National Framework for England. These include a requirement to consult our communities. The draft consultation document and plan are tabled for Fire Authority approval.
4. Our new Safety Plan will provide the Fire Authority’s strategic intent during the period of the plan. Through the public consultation, a mandate for the new Safety Plan and proposals contained therein will be gained. Should the Fire Authority be content, we will run a 10-week consultation. The final plan will go to February’s Fire Authority for approval. RECOMMENDATION
5. That deliverable (c) in our Year 5 activities be changed to: “deliver in-year efficiencies and identify and implement where possible saving options” be approved by the HIWFRA Full Authority
6. That work to produce the Fire Authority’s next Safety Plan be noted and our approach to consult be approved by the HIWFRA Full Authority
Background
CHANGES TO YEAR 5
7. Earlier this year, the Fire Authority agreed our year 5 (2024-25) activities. The focus was around completing the work already agreed and part actioned, together with setting ourselves up for the introduction of a new strategic Safety Plan (2025-2030). The plan had 6 objectives. These were:
(a) creating the Fire Authority’s new policy framework
(b) producing a new Safety Plan covering 2025-30
(c) deliver in-year efficiencies
(d) further measures to enhance the management of fireground contamination
(e) respond to and create an action plan from the Grenfell Tower Inquiry phase 2 report
(f) complete the implementation of National Operational Guidance and to agree a sustainable ongoing plan.
8. It has now become apparent that the level of efficiencies originally anticipated needs to go further to meet our emerging £6m funding gap. We therefore need to broaden part (c). A new board – Fire Futures – has been established, chaired by the Chief Fire Officer, to lead work to identify and release the efficiencies needed. These efficiencies will be subject to our change management procedure and will involve consultation/approval as considered appropriate depending on the scale of change.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.